Stabilizacja skarp
SNUFF MILLS, GB
SNUFF MILLS
Stabilizacja skarp
Projekt
miejsce
kraj/region
Snuff Mills
Frenchay, Bristol
Wielka Brytania
Rok instalacji
2001
klient
Projektowanie
Wykonawca
Bristol City Council - Neighbourhood and Housing Services
Bristol City Council
BAM Ritchies / BAM Nuttall Ltd.
Situation
A commercial building within an old quarry was at risk of falling rocks from the back wall of the quarry.
opis
A total number of 44 rock bolts and 4 anchors were installed at height into a sub-vertical to overhanging
®
cliff. 420 m² of high tensile TECCO G65/3 steel mesh was installed to work with the rock bolts. These
ranged in length between 3 and 12 [m] and the anchors were between 8 and 12 m. As the works were
generally greater than 6 m in height above ground level, supplementary man access via ropes or mobile
®
elevating work access platform was used. The low weight of TECCO G65/3 mesh rolls was ideal for this
project.
Chroniony Objekt
Systemy
Building
®
TECCO G65/3
Ochrona przeciwerozyjna
GEOBRUGG SUPERCOATING
Geology
Sandstone.
zabezpieczona powierzchnia
420 m²
Wysokość skarpy
Nachylenie skarpy
10 m
70 ° - 80 °
środki ochronne
Active slope stabilization
Wystawy
-
®
W razie pytań prosimy o kontakt ze specjalistą Geobrugga.
Roger Moor
Country Manager Eastern Switzerland & Liechtenstein (GL, LU, NW, OW, SH, SZ, UR, ZG, ZH)
Phone 071 466 81 52
Mobile 078 783 46 81
[email protected]
Geobrugg AG
Aachstrasse 11 | 8590 Romanshorn | Szwajcaria
[email protected] | www.geobrugg.com
Ein Unternehmen der Gruppe BRUGG | ISO 9001 zertifiziert
Stabilizacja skarp | Snuff Mills, GB
2/2