project name: Wastewater treatment – Ruda Śląska
beneficiary: City Hall in Ruda Śląska
region: śląskie
fund: Cohesion Fund
operational programme:
project value: 177 658 746.29 zł
EU grant value: 115 478 184.48 zł
punktor projekt realizowany
w latach
Project description
The Project entitled "Wastewater treatment - Ruda Śląska" aims at solving the problem of wastewater
transport and treatment on the area of the city.
The project will result in increasing the amount of wastewater treated in Ruda Śląska according to Polish and
UE norms from 60% to 95%. The project is based on the "Wastewater Management Master Plan in Ruda
Śląska" adopted by the City in 1996 and updated in December 2001 for the needs of the project.
The project implementation will establish a coherent wastewater management system. The city area will be
divided into three catchments: "Halemba Centrum" - newly constructed wastewater treatment plant,
"Brzegów" - modernized wastewater treatment plant and "Barbara" - existing wastewater treatment plant.
The technologies applied in these facilities will ensure the achievement of the required level of wastewater
treatment and proper management of the wastewater sludge. The following wastewater treatment plants will
be closed: "Halemba I", "Halemba II", "Ruda Południowa" and "Mickiewicz", and the areas on which these
are situated will be recultivated.
The project implementation will make it possible to achieve the following objectives: achieving the quality of
treated wastewater that is compliant with the rules of law; visible decrease in the load of pollutants
introduced to the receiving facility; clear improvement in the condition of surface waters; improved sanitary
conditions and decreased risk of diseases; improved standard of life of the residents; establishment of a
sustainable and efficient wastewater management system; increased attractiveness of the area for the
investors.