Draft of Biodiversity Action Plan (BAP)

Transkrypt

Draft of Biodiversity Action Plan (BAP)
ERM Polska Sp. z o.o.
FINAL REPORT
ERM Polska Sp. z o.o.
5 Ratuszowa ST.
03-461 Warsaw, Poland
Ph.: +48 0 22 518 4970
Fax: +48 0 22 518 4999
www.erm.com
[email protected]
LNG TERMINAL
ŚWINOUJŚCIE, POLAND
Biodiversity Action Plan
(BAP)
October, 2010
Managing Director
Martin Gundert
NIP/VAT no: 113-00-15-957
REGON: 010154103
KRS: 0000181135
Kapitał zakładowy:
168 500 PLN
Prepared for:
POLSKIE LNG S. A.
ul. Fińska 7,
72-602 Świnoujście
Poland
A member of the Environmental
Resources Management Europe
and the ERM International Group
ERM Polska Sp. z o.o.
This report has been prepared by ERM with all reasonable
skill, care and diligence within the terms of the Mandate
Agreement with the client and taking account of the
manpower and resources devoted to it by agreement with
the client.
ERM disclaims any responsibility to the client and others in
respect of any matters outside the scope of the above.
This report is confidential to the client, and ERM accepts no
responsibility of whatsoever nature to third parties whom this
report, or any part thereof, is made known. Any such party
relies upon the report at their own risk.
ERM Polska Sp. z o.o.
Warsaw/Neu-Isenburg, 20 October 2010
Ppa. Raimund Vogelsberger
(Project Director)
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
Dr. Norber Raschke
(Project Manager)
FINAL
i
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
1
2
3
INTRODUCTION
1
1.1
1.2
1.3
1
2
4
PROJECT OVERVIEW
6
2.1
2.2
2.3
2.4
2.5
6
6
7
7
8
INTRODUCTION
LNG TERMINAL
BREAKWATER
JETTY
PIPELINE
ENVIRONMENTAL BASELINE
3.1
3.2
3.3
3.4
3.5
3.6
4
PURPOSE OF THIS BIODIVERSITY ACTION PLAN
INTERNATIONAL REFERENCE STANDARDS FOR BIODIVERSITY
SCOPE AND STRUCTURE OF THIS BAP DOCUMENT
9
MARINE AND SHORE ENVIRONMENT
LAND ENVIRONMENT
PIPELINE ROUTE
NATURA 2000 SITES
PROTECTED AREAS
SPECIES OF CONSERVATION INTEREST
9
10
12
13
20
21
OVERVIEW OF POLISH ENVIRONMENTAL REGULATIONS
4.1
4.2
4.3
23
GENERAL OVERVIEW OF THE POLISH ENVIRONMENTAL
REGULATORY SYSTEM
KEY ENVIRONMENTAL REGULATORY CONDITIONS
COMPLIANCE
23
29
32
5
BASELINE STUDIES SUMMARY
34
6
OVERVIEW OF POTENTIAL IMPACTS TO BIODIVERSITY
40
6.1
6.2
6.3
6.4
6.5
6.6
40
44
46
46
47
6.7
CONSTRUCTION
OPERATION
DECOMMISSIONING
TRANSBOUNDARY IMPACTS
CUMULATIVE IMPACTS
SUMMARY IMPACTS TO BIODIVERSITY, CRITICAL HABITATS
AND SPECIES OF CONSERVATION INTEREST
APPROPRIATE ASSESSMENT
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
ii
48
51
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
7
8
Figure 2.1
Figure 3.1
Figure 4.1
PROPOSED MITIGATION MEASURES
52
7.1
7.2
7.3
7.4
54
60
65
74
BREAKWATER
JETTY
LNG TERMINAL
PIPELINE
MONITORING PROGRAMME
85
8.1
8.2
8.3
8.4
86
88
91
92
BREAKWATER
JETTY
LNG TERMINAL
PIPELINE
LIST OF FIGURES
Visualisation of the Future LNG Terminal and New Harbour Including the
Jetty
8
Natura 2000 Sites and Areas of Biodiversity
14
Decision-making Process for Appropriate Assessment
25
LIST OF TABLES
Table 3.1
Table 3.2
Table 3.3
Table 3.4
Table 4.1
Table 4.2
Table 4.3
Table 4.4
Table 5.1
Table 5.2
Table 6.1
Table 7.1
Table 7.2
Table 7.3
Table 7.4
Table 8.1
Table 8.2
Table 8.3
Table 8.4
Protected Vascular Plants and Fungi
PLH 320019 Habitats
PLH 320018 Habitats
PLH 320033 Habitats
Breakwater
Jetty
LNG Terminal
Pipeline
Existing Baseline Studies in Support of Present EIA
Existing Technical Studies in Support of Present EIA
Summary of Impacts to Biodiversity, Critical Habitats and Species of
Conservation Interest
Mitigation Measures - Breakwater
Mitigation Measures - Jetty
Mitigation Measures – LNG Terminal
Mitigation Measures - Pipeline
Breakwater Monitoring
Jetty Monitoring
LNG Terminal
Monitoring - Pipeline
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
iii
10
15
18
19
29
30
30
31
34
37
48
54
60
65
74
86
88
91
92
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Table 8.5
Table 8.6
Table 8.7
Table 8.8
Table 8.9
Table 8.10
Table 8.11
Table 8.12
Table 8.13
Table 8.14
Table 8.15
Table 8.16
Table 8.17
PLH 320019 Species
PLH990002 Species
PLB990003 Species
PLB 320002 Species
PLB 320009 Species
PLH 320018 Species
PLH 320033 Species
PLB 320007 Species
PLB 320011 Species
PLB 320012 Species
Other Important Species of Flora and Fauna - PLH320019
Other Important Species of Flora and Fauna - PLH320018
Other Important Species of Flora and Fauna - PLH320033
2
5
6
7
9
11
15
17
18
20
22
25
26
ANNEXES
Annex A:
Natura 2000 Species List
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
iv
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
1
INTRODUCTION
1.1
PURPOSE OF THIS BIODIVERSITY ACTION PLAN
Polskie LNG S.A. (PLNG) engaged a consulting company (ERM Polska
Sp.z.o.o.) to prepare this Biodiversity Action Plan (BAP) in the context of the
overall environmental and social assessment for the planned construction of
the LNG Terminal Project in Swinoujscie (see Project Description in Sec 2.1).
The BAP is a supplement to the four separate Environmental Impact
Assessments (EIAs) previously prepared for the LNG Project components,
with the purpose being to provide a summary of the known risks and
potential impacts to the regional biodiversity and to determine the need of
mitigation and monitoring measures necessary to avoid, minimise or mitigate,
or as a last resort, offset or compensate any unwanted impacts. This is
achieved by:
an assessment of how proposed Project-related activities affect
biodiversity and renewable natural resources;
an analysis of how biodiversity and renewable natural resources can be
managed as part of the Project activities and how adverse impacts can be
mitigated;
an identification of responsibilities (internally and externally) and
resources for management and mitigation.
The approach followed in this BAP is based on the application of the Equator
Principles to this Project and the relevant standards/requirements of the
International Finance Institution (IFC) and the European Bank for
Reconstruction and Development (EBRD) as discussed below.
The BAP is linked to the Environmental and Social Action Plan (ESAP) that
contains the environmental and social action items that were agreed for the
Project.
As a stand-alone document, this BAP will serve as a management tool for use
by the responsible LNG Project staff and contractors as a common basis for
action and compliance with respect to biodiversity protection.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
1
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
1.2
INTERNATIONAL REFERENCE STANDARDS FOR BIODIVERSITY
The IFC‟s Performance Standard (PS) 6 on Biodiversity is the most widely
accepted international standard for dealing with biodiversity and ecosystems
in ESIAs, and is a requirement for Equator Principle bank financing. PS6 has
been developed to „reflect the objectives of the Convention on Biodiversity (CBD)’,
and as such, to ensure that „the Assessment will take into account the differing
values attached to biodiversity by specific stakeholders, as well as identify impacts on
ecosystem services‟. The EBRD effectively adopt the same performance
standard and refers to it as Performance Requirement (PR) 6.
The main elements of IFC‟s PS 6 and EBRD‟s PR 6 on Biodiversity that are of
note include:
1) Firstly, taking an approach based on identifying the type of „habitat‟
impacted, in terms of whether the habitat is „natural’ or ‘modified’ (i.e.
human activity has modified the areas primary ecological functions, for
example, through fishing or the introduction of alien species); secondly,
determining whether that habitat is considered „critical‟. This categorisation
then influences the nature and extent of acceptable impacts, mitigation and
compensation measures.
2) Based on this „habitat‟ approach, the overall aim of PS 6 is to achieve „no net
loss’ of biodiversity, where feasible. EBRD‟s PR 6 suggests no net loss or a
„net gain of the affected biodiversity‟.
3) Ascertaining whether the proposed project is located within a legally
protected area, and if so, adhering to certain requirements.
4) In relation to invasive species, the development „will not intentionally
introduce alien or non-native species‟ (unless it is in accordance with regulatory
frameworks or is subject to a risk assessment), and it „will exercise due diligence
to prevent accidental or unintended introductions’, and ‘identify measures to
minimise the potential for release, if any’.
5) Other aspects of the guidance also recommend: taking into account material
impacts on biodiversity arising through „supply chains’ or other „third party
relationships‟, considering short-term, long-term and cumulative impacts,
and considering impacts to ‘ecosystem services’.
Together the IFC PS 6 and EBRD PR 6 define “critical habitat” as either natural
or modified habitats that meet at least one of the following requirements and
so deserves particular attention.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
2
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Critical habitat includes:
Areas with high biodiversity value (1);
Habitat required for the survival of critically endangered or endangered
species as defined by the IUCN Red List of Threatened Species or as
defined in any national legislation;
Areas having special significance for endemic or restricted-range species;
Sites that are critical for the survival of migratory species;
Areas supporting globally significant concentrations or numbers of
individuals of congregatory species;
Areas with unique assemblages of species or which are associated with key
evolutionary processes or provide key ecosystem services;
Areas having biodiversity of significant social, economic or cultural
importance to local communities; and
Areas of importance to species vital to the ecosystem as a whole (keystone
species).
The EBRD is guided by and supports conservation and protection measures
written into international law, conventions and EU directives, including
adopting a precautionary approach to the conservation and sustainable use of
biodiversity and the management of impacts upon it.
Key within the context of the present study is that the project is located within
or in the vicinity of Natura2000 sites, a coherent network of protected areas in
EU member states. The legal basis for the Natura 2000 network comes from
the Birds Directive which dates back to 1979 and the Habitats Directive from
1992. Together these Directives constitute the backbone of the EU's policy on
biodiversity protection.
(1) Such as areas that meet the criteria of the World Conservation Union (IUCN) classification.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
3
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
The objectives of the EBRD‟s PR 6 include, inter alia, statements to:
Protect and conserve biodiversity;
Avoid, minimise and mitigate impacts on biodiversity and offset significant
residual impacts, where appropriate, with the aim of achieving no net loss
or a net gain of biodiversity; and
Promote the sustainable management and use of natural resources.
1.3
SCOPE AND STRUCTURE OF THIS BAP DOCUMENT
The scope of the present BAP has been defined on the basis of Annex A
included in IFC Guidance Note 6 (1). The chapters in the present report are
structured accordingly, as follows:
Chapter 1 (this chapter) explains the rationale and approach to the present
study.
Chapter 2 provides an overview of the project, with emphasis on project
components occurring within protected and/or Natura2000 sites.
Chapter 3 describes the protected areas and includes information on
when/why they were designated as protected areas/Natura2000 sites.
Chapter 4 provides an overview of the Polish environmental regulatory
system, with specific emphasis on the PLNG approval process and decisions
to date related to the LNG project and pipeline alignment within the
Natura2000 sites (including any key environmental regulatory "conditions").
Chapter 5 summarises the baseline studies conducted to date, and lists relevant
additional studies that were carried out in support of the ESIA.
Chapter 6 provides an overview of potential impacts to biodiversity, including
a clear description on whether the project will/will not impact critical habitat
as defined by PR6. The impact section also provides a summary of total
habitat loss and highlights the potential for habitat fragmentation.
Chapter 7 provides a summary of proposed mitigation measures, including
permit/approval conditions and potential offsets or compensation should the
(1) IFC Guidance Note 6: Biodiversity Conservation and Sustainable Natural Resource
Management; July 31, 2007.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
4
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
project result in significant habitat loss (especially within the Natura2000
sites).
Finally, Chapter 8 includes pertinent elements of the monitoring programme,
with a focus on keystone species that can be used as "indicators" to measure
implementation success of the project's mitigation/biodiversity management
program.
Annex A lists the species of conservation interest that are known to occur in
the Natura2000 sites and that warrant specific mitigation measures to be
undertaken as part of the project.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
5
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
2
PROJECT OVERVIEW
2.1
INTRODUCTION
Polskie LNG S.A (PLNG,) is planning to construct and operate a Liquefied
Natural Gas (LNG) Regasification Terminal in Świnoujście, Poland.
Świnoujście is in the most north-western part of the Western Pomeranian
Province and about 4.5 km from the German border. The project will consist
of four components: LNG terminal, breakwater, jetty and pipeline. In
addition to the project components dredging will be required to allow LNG
tankers to access the jetty (see Section 2.3 for details).
The date for the terminal to become fully operational and shipment of first
LNG by tanker is expected in June 2014.
2.2
LNG TERMINAL
The LNG terminal will be located on Wolin Island between the southern coast
of Pomeranian Bay and the Odra estuary. It will contain facilities for:
Servicing/offloading LNG ships with capacities ranging from 75,000 m3 to
216,000 m3;
Storage of LNG in two onshore cooled tanks with gross capacities of
160,000 m3 each; the height of the tanks and the flare will be approximately
50 metres;
Re-gasification of stored LNG with a capacity of 5 billion Nm3 per year,
with the possibility of increasing regasification capacity to 7.5 billion Nm3
per year by adding a third tank without the need to expand the site;
Uploading LNG to road-tankers with a planned dispatch capacity of
approximately 95,000 tonnes of LNG per year. It is planned that
approximately 5 % of the LNG received by sea will be shipped onwards via
road tankers in the further years of terminal operating.
Preparatory site clearance for the LNG terminal was completed in 2009 and
works for road access started in spring 2010. Construction is planned to start
in mid-2010 after the contract with the selected EPC contractor has been
finalised.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
6
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
2.3
BREAKWATER
A new breakwater will be constructed into the Baltic Sea to the east of the
existing breakwater at the mouth of Świna River, extending from the beach to
the north and north-west for about 2 km. The breakwater will protrude
approximately 6.5 metres above the water level. The fairway to the port, the
port basin and a turning circle for ships will be dredged to 14.5 m depth. The
berthing area will be dredged for a maximum draught of 12.5 m depth. The
dredging spoils excavated during construction of the new harbour basin and
jetty will be deposited at two locations on the seabed northeast of Świnoujście:
a 12 km² area starting about 12 km from shore and a 3 km² area about 20 km
from shore. The breakwater, together with the new jetty (see below), will form
a new external port facility that provides space for five additional berths that
may be developed in the future.
Construction of the breakwater is scheduled to start in July 2010 and be
completed in December 2012. The general contractor was contracted in May
2010. The fairway to, the new harbour basin, the turning circle and the
berthing area will be dredged out to the required depths simultaneously with
the construction of the breakwater.
2.4
JETTY
The new jetty will be located within the new external harbour and will serve
as the mooring site for the LNG carriers during unloading and will be
equipped with all necessary devices for this purpose, such as navigation
equipment and mooring equipment. It is estimated that 65 tankers will berth
at the LNG terminal per year. The tankers will be Q-Flex type vessels with a
capacity up to 216,000 m3, length of 315 m, width of 50 m and draught of
12.5 m.
Construction of the jetty is scheduled to start in October 2010 after the first
800 m of the new breakwater have been completed. Piling works, the erection
of the support structures of the jetty platform and the pipeline bridge will be
completed in June 2011 with the outfitting of the jetty unloading facilities
planned for completion by November 2012.
The figure below presents a visualisation of the LNG Terminal and the new
breakwater that encloses the new external harbour and jetty.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
7
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Source: PLNG
Figure 2.1
Visualisation of the Future LNG Terminal and New Harbour Including the
Jetty
2.5
PIPELINE
In order to feed the re-gasified natural gas into the Polish national gas
transmission pipeline grid after its re-gasification in the LNG terminal, GazSystem will build an approximately 6 kilometre long high-pressure connector
gas pipeline (nominal diameter of 800 mm) from the LNG terminal to the
vicinity of Łunowo. There it will be connected to the planned approx. 74
kilometre long Świnoujście-Szczecin high pressure gas transmission pipeline
(also 800 mm nominal diameter) connecting to a new grid station in the village
of Budno near Goleniów. About 95% of the length of the new gas transmission
pipeline will run parallel with the existing gas transmission pipeline. The
overall route runs from the LNG terminal, east across the Wolin island to the
city of Wolin and, having crossed the Dziwna River at the longitude of the city
of Wolin, turns south toward Stępnica and then Goleniów. The route of the
gas transmission pipeline will run through the following municipalities:
Świnoujście, Międzyzdroje, Wolin, Stępnica, Goleniów (fig. 3.1)
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
8
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
3
ENVIRONMENTAL BASELINE
3.1
MARINE AND SHORE ENVIRONMENT
The seabed of the nearshore environment is inhabited by common benthic
species typical of the brackish conditions in the Pomeranian Bay, notably the
soft-shell clam Mya arenaria, Baltic clam Macoma baltica, various species of
amphipods, ragworms, nematodes and mussel. There is no seagrass or other
aquatic plants. Common macro-algae and benthic diatoms dominate. Algae
are also found on and in the crevices of the existing breakwater. The rock
armour provides a habitat to mussels or barnacles. The water column hosts a
variety of phytoplankton and zooplankton species, representative of a
freshwater and brackish water environment. There are large seasonal
differences in the number of species observed.
The sandy beach is home to a protected species under Polish law, the
amphipod Talitrus saltator which thrives on accumulated beach wrack in the
drift line. The species is also found on beaches to the east of the project area.
The fish fauna comprises typical marine species (eg eelpout, cod, herring,
flatfish) and freshwater fish species from the lagoon, notably pike and perch.
A few protected species that are listed on Annex II of the Habitat Directive are
occasionally observed in the area, including the twaite shad Alosa fallax, allis
shad Alosa alosa, salmon, ziege, the sea and river lamprey, eel, and two species
of sturgeon. Eel and sturgeon are stocked in Polish rivers and also the
Szczecin Lagoon was restocked with eels.
Marine mammals that occasionally frequent the Pomeranian Bay include the
harbour porpoise Phocaena phocaena, the white-beaked dolphin, the gray seal
and common seal. There are no known seal haul out sites near the project
area. These species are also listed on Annex II or Annex IV of the Habitat
Directive.
The existing breakwater is an important resting place for many bird species,
mostly waders, gulls and terns including the dunlin, the Bar-tailed godwit and
the purple sandpiper in notable numbers. Among the more than 100 species
of birds, some 26 are listed on Annex I of the Bird Directive, and 22 are listed
in the Polish Red Book of Animals. The Pomeranian Bay and Odra Delta
(which includes Szczecin lagoon) are an important stopover for migratory
birds. Large numbers of birds flock to the area in spring and autumn.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
9
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Behind the beach lies an area of sand dunes with successive zones of
strandline vegetation including grassleaf orach Atriplex littoralis seaward of
the dunes, pioneer vegetation (including sand couch grass Elymus farctu) on
shifting dunes, white dunes and more mature grey dunes covered with
grassland. The pioneer vegetation adapts to a continually changing landscape
from windswept sand. The sand dune areas are listed on Annex I of the
Habitat Directive.
3.2
LAND ENVIRONMENT
The LNG Terminal site is located within a designated Natura 2000 site (PLH
320019 Wolin I Uznam SCI). A number of different habitats are situated
parallel to the sea shore including a sand dune succession with white stage
dunes (with willow) and grey dunes. Within the LNG terminal site itself there
are six protected types of natural habitat according to Annex I Habitats
Directive (one of them, grey dunes is a priority habitat). Thirty four protected
species of vascular plants and fungi occur in the vicinity of the site (Table 3.1).
Table 3.1
Protected Vascular Plants and Fungi
Latin name
English name
Vascular plants
Atriplex litoralis
Grassleaf Orache
Carex arenaria
Sand sedge
Convallaria mayalis
Lily of the valley
Elymus farctus
Bulrush couch grass
Epipactis atrorubens
Dark red helloborine
Frangula alnus
Alder buckthorn
Goodyera repens
Creeoing rattlesnake plantain
Hedera helix
Common ivy
Helichrysum arenarium
Dwarf everlast
Hippophaë rhamnoides
Common sea buckthorn
Ledum palustre
Marsh tea
Lonicera periclymenum
Common honeysuckle
Moneses uniflora
One-flowered Wintergreen
Ornithogallum umbellatum
Grass lily
Pinus mugo
Dwarf mountain pine, Swiss mountain pine
Polypodium vulgare
Common polypody
Ribes nigrum
Black currant
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
10
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Latin name
English name
Rumex sanguineus
Wood dock
Salsola kali
Prickly glasswort
Stellaria uliginosa
Bog stitchwort
Utricularia vulgaris
Common bladderwort
Viburnum opulus
Cranberry-bush
Fungi
Cystodermella granulosum
Cystoderma granosum
Disciseda bovista
Disciseda bovista
Galerina paludosa
Bog bell
Geastrum floriforme
Daisy earthstar
Geastrum minimum
Tiny earthstar
Gyrodon lividus
Alder bolete
Helvella lacunosa
Elfin saddle
Leccinum niveum
Marsh birch bolete
Lyophyllum palustre
domecap
Psilocybe uda
Peat Brownie
Russula coerulea (‘caerulea’)
Light blue russula
Tulostoma (Tylostoma’) fimbriatum
stalkball
The wildlife survey conducted within the EIA studies identified a large
number of species in the area. The pool frog (Pelophylax lessonae also named
Rana lessonae), moor frog (Rana arvalis) and sand lizard (Lacerta agilis) are
included in the Habitat Directive as species requiring strict conservation (socalled Annex IV species). In addition, three bird species listed in Appendix I
of the Birds Directive (species requiring special conservation measures) were
noted during the field investigations; woodlark (Lullula arborea), red-backed
shrike (Lanius collurio) and black woodpecker Dryocopus martius). The most
valuable breeding species on the site are the woodlark and red-backed shrike.
The section of beach located between the land part and sea part of the LNG
terminal, besides breeding, is a very important place of prey and rest for many
gulls and shore birds (Charadriformes). Former military fortifications and
shelters located near the proposed LNG site are important structures for bats.
Five bat species (Myotis nattereri, Myotis daubentonii, Eptesicus serotinus,
Plecotus auritus, Myotis myotis) identified in the area during the field
investigations are protected at EU level (listed in Annex II or IV).
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
11
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
3.3
PIPELINE ROUTE
The pipeline route runs through several habitat types as it travels from the
LNG terminal in Świnoujście to Poland‟s transmission system in Goleniów:
maritime, grassland, meadows, tall herbs, heathland, undergrowth, forests
and coniferous forests. Maritime habitats include wooded dunes of the sea
region (habitat code 2180) and wet dune slacks (habitat code 2190). Habitats
in grassland, meadows, tall herbs, heathland and undergrowth include dry
heaths (habitat code 4030), dry xeric sand calcareous grassland (priority
habitat, code 6120) and Molinia meadows (habitat code 6410). Forest and
coniferous forest habitats include Luzulo-Fagetum beech forest (habitat code
9110) and bog woodland (priority habitat 91D0).
In addition the pipeline runs within the vicinity of the boundaries of three
animal protection zones. In three places, the pipeline route runs at a distance
of 20 m to the boundaries of (partial) protection areas of breeding pairs of
white-tailed eagles within the Międzyzdroje Forest District at a distance and
near the boundary of Woliński National Park.
The following Habitats Directive Annex II species have been found to live on
the pipeline route:
Crested newt (Triturus cristatus);
European fire-bellied toad (Bombina bombina);
River otter (Lutra lutra);
The large blue butterfly (Maculinea arion)
The following species specified in Annex I to the Bird Directive 79/409/EEC
have been found along the pipeline route:
Tawny pipit (Anthus campestris);
Golden plover (Pluvialis apricaria);
Bluethroat (Luscinia svecica);
Kingfisher (Alcedo atthis);
Smew (Mergus albellus);
Barred warbler (Sylvia nisoria);
Woodlark (Lullula arborea);
Nightjar (Caprimulgus europaeus);
Red-backed shrike (Lanius collurio);
Black woodpecker (Dryocopus martius);
Corncrake (Crex crex);
Crane (Grus grus);
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
12
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
White stork (Ciconia ciconia);
Honey buzzard (Pernis apivorus);
Red kite (Milvus milvus); and
White-tailed eagle (Halieaetus albicilla).
3.4
NATURA 2000 SITES
The Project components are located within or in close proximity to areas that
are identified as Special Areas of Conservation (SACs) or Sites of Community
Importance (SCIs) under the EU Habitats Directive 92/43/EEC or classified as
Special Protection Areas (SPAs) under the Birds Directive 79/409/EEC. These
areas are commonly referred to as “Natura 2000” sites.
The project components interact with the following Natura 2000 sites:
LNG Terminal
Located within PLH 320019 Wolin I Uznam (SCI);
Approaching the southern border of PLH 990002 Ostoja na Zatoce
Pomorskiej (SCI);
Located 0.9 km SW of PLB 990003 Zatoka Pomorska (SPA); and
Located 2.5 km N of PLH 320002 Delta Swiny (SPA).
Jetty
Located within PLH 990002 Ostoja na Zatoce Pomorskiej (SCI); and
Located 1 km from PLB 990003 Zatoka Pomorska (SPA).
Breakwater
Located partially within PLH 990002 Ostoja na Zatoce Pomorskiej (SCI)
(Natura 2000 site); and
Located 1 km from PLB 990003 Zatoka Pomorska (SPA).
Pipeline
Passes through PLH 320019 Wolin i Uznam (SCI);
Passes through PLB 320002 Delta Świny (SPA);
Passes through PLB 320009 Zalew Szczeciński (SPA);
Passes through PLH 320018 Ujscie Odry I Zalew Szczecinski (SCI);
Passes through PLH 320033 Uroczyska w Lasach Stepnickich (SCI);
Passes through PLB 320007 Laki Skoszewskie (SPA);
Passes through PLB 320011 Zalew Kamienski I Dziwna (SPA); and
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
13
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Passes through PLB320012 Puszcza Goleniowska (SPA).
Figure 3.1presents the Natura 2000 sites and the Wolinski National Park within
the vicinity of the project components. Details of the individual Natura 2000
sites and protected areas are presented below.
Figure 3.1
Natura 2000 Sites and Areas of Biodiversity
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
14
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
3.4.1
PLH 320019 Wolin i Uznam
PLH320019 Wolin i Uznam was designated as a Site of Community
Importance (SCI) in November 2007. This area consists of two islands (Wolin
and Uznam) along with a chain of coastline water. It covers an area of
30,792 ha comprising river mouths, cliffs, marine salt flats, dunes, heathland,
grassland and woodland. The Annex I habitats under protection are detailed
in Table 3.2 below.
Table 3.2
PLH 320019 Habitats
Code
Type
%
Cover
Global
assessment
6410
Molinia meadows on calcareous, peaty or clayey-silt-laden
soils
0.16
C
7110
Active raised bogs
0.16
B
7140
Transition mires and quaking bogs
0.16
B
7150
Depressions on peat substrates of the Rhynchosporion
0.16
B
7210
Calcareous fens with Cladium mariscus and species of the
Caricion davallianae
0.03
7230
Alkaline fens
0.5
C
9110
Luzulo-Fagetum beech forests
10
A
9130
Asperulo-Fagetum beech forests
10
A
9150
Medio-European limestone beech forests of the
Cephalanthero-Fagion
0.7
A
9190
Old acidophilous oak woods with Quercus robur on sandy
plains
5
B
91D0
Bog woodland
0.5
C
1130
Estuaries
1
B
1210
Annual vegetation of drift lines
0.16
C
1230
Vegetated sea cliffs of the Atlantic and Baltic Coasts
0.6
A
1330
Atlantic salt meadows (Glauco-Puccinellietalia maritimae)
1.6
A
2110
Embryonic shifting dunes
1.6
C
2120
Shifting dunes along the shoreline with Ammophila arenaria 1.5
("white dunes")
B
2130
Fixed coastal dunes with herbaceous vegetation ("grey
dunes")
2.6
A
2140
Decalcified fixed dunes with Empetrum nigrum
0.2
B
2180
Wooded dunes of the Atlantic, Continental and Boreal
region
0.8
B
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
15
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Code
Type
%
Cover
Global
assessment
2330
Inland dunes with open Corynephorus and Agrostis
grasslands
0.16
B
3140
Hard oligo-mesotrophic waters with benthic vegetation of
Chara spp.
0.16
B
3150
Natural eutrophic lakes with Magnopotamion or
Hydrocharition - type vegetation
0.6
C
3270
Rivers with muddy banks with Chenopodion rubri p.p. and
Bidention p.p. vegetation
0.15
C
4030
European dry heaths
0.16
6120
Xeric sand calcareous grasslands
0.3
C
6210
Semi-natural dry grasslands and scrubland facies on
calcareous substrates (Festuco-Brometalia) (* important
orchid sites)
0.16
C
Note: Global Assessment is a function of representativity, relative cover and degree of
conservation in accordance with the Standard Data Form for Natura 2000 Sites applied to all
Natura 2000 sites across Europe: A – excellent value; B – good value; C – significant value; no
code signifies that the habitat in question is not significant within the site.
There are 50 species of Annex I birds that occur in PLH320019 Wolin i Uznam,
along with an addition 14 species of regularly occurring migratory birds not
listed on Annex I. Three species of Annex I birds are listed on the IUCN Red
List as Vulnerable or Near Threatened; Acrocephalus paludicola (Aquatic
warbler) is listed as Vulnerable and Aythya nyroca (ferruginous duck) and
Ficedula parva (Red-breasted Flycatcher) are listed as near threatened on the
IUCN Red list as Near Threatened. Six species of mammal (European bison,
Eurasian beaver, grey seal, Eurasian otter, greater mouse-eared bat and
harbour porpoise), two species of amphibian (fire-bellied toad and northern
crested newt), three species of fish (twaite shad, ziege and sea lamprey) and
three beetle species (greater capricorn beetle, stag beetle and hermit beetle) are
included in Annex II to the Council directive 92/43/EEC and are protected.
From the Annex II species found in this site the European bison (Bison bonasus)
and greater capricorn beetle (Cerambyx cerdo) are listed as Vulnerable and the
Eurasian Otter (Lutra lutra) and hermit beetle (Osmoderma eremita) are listed as
Near Threatened on the IUCN Red List. It is anticipated that the presence of
the large yellow-spotted dragonfly and the greater mouse-eared bat may be
observed within the proposed investment site. Full species lists, including
population residency and site assessment can be found in Annex A.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
16
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
3.4.2
PLH 990002 Ostoja na Zatoce Pomorskiej
PLH 990002 Ostoja na Zatoce Pomorskiej was designated as a Site of
Community Importance (SCI) in December 2008 and covers 243132.7 ha of
marine sea, of which 25% is sandbanks slightly covered by sea water at all
times (Code 1110). The Annex I habitat under protection is the shallow Odra
sand bank located approximately 23 km north of the project area. Four species
of Annex I birds occur in PLH990002 Ostoja na Zatoce Pomorskiej, along with
an addition eight species of regularly occurring Migratory Birds not listed on
Annex I. Annex II species listed within Ostoja na Zatoce Pomorskiej are
twaite shad and harbour porpoise. Full species lists, including population
residency and site assessment can be found in Annex A.
3.4.3
PLB 990003 Zatoka Pomorsk
PLB 990003 Zatoka Pomorsk was designated as a Special Protection Area
(SPA) in July 2004. It covers 311877.3 ha of marine sea. The site was
designated for the conservation of 12 species of bird; four Annex I species and
8 species of regularly occurring migratory birds not listed on Annex I. Full
species lists, including population residency and site assessment can be found
in Annex A.
3.4.4
PLB 320002 Delta Świny
PLB 320002 Delta Swiny was designated as a Special Protection Area (SPA) in
July 2004. It covers 8286 ha, including inland water bodies (29%), bogs,
marshes, water fringed vegetation, fens, grassland and woodland. The site
was designated for the conservation of 39 bird species listed on Annex I and 6
migratory birds not listed on Annex I. The Annex I species Acrocephalus
paludicola (aquatic warbler) and Ficedula parva (red-brested flycatcher) are
listed as vulnerable and near threatened on the IUCN Red List respectively.
Full species lists, including population residency and site assessment can be
found in Annex A.
3.4.5
PLB 320009 Zalew Szczeciński
PLB320009 Zalew Szczeciński was designated as a Special Protection Area
(SPA) in July 2004. It covers an area of 47,194.6 ha of which 81% consists of
inland water bodies. The site was designated for the conservation of 42 bird
species listed under Annex I and 15 species of migratory birds not listed on
Annex I. The Annex I species Acrocephalus paludicola (aquatic warbler) and
Ficedula parva (red-brested flycatcher) are listed as vulnerable and near
threatened on the IUCN Red List respectively. Full species lists, including
population residency and site assessment can be found in Annex A.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
17
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
3.4.6
PLH 320018 Ujscie Odry i Zalew Szczecinski
PLH 320018 as Ujscie Odry i Zalew Szczecinski was designated as a Site of
Community Importance (SCI) in November 2007. It covers an area of 52,612
ha. It contains Annex I habitats as presented in Table 3.3, of which 84%
comprises inland water bodies.
Table 3.3
PLH 320018 Habitats
%
Cover
Global
assessment
Molinia meadows on calcareous, peaty or clayey-silt-laden
soils
0.1
C
6430
Hydrophilous tall herb fringe communities of plains and of
the montane to alpine levels
0.25
B
6510
Lowland hay meadows (Alopecurus pratensis, Sanguisorba
officinalis)
1
B
7140
Transition mires and quaking bogs
0.02
C
7230
Alkaline fens
0.01
91D0
Bog woodland
0.2
B
91E0
Alluvial forests with Alnus glutinosa and Fraxinus excelsior
(Alno-Padion, Alnion incanae, Salicion albae)
0.5
B
1130
Estuaries
0.2
A
1150
Coastal lagoons
84
A
1230
Vegetated sea cliffs of the Atlantic and Baltic Coasts
0.01
A
1330
Atlantic salt meadows (Glauco-Puccinellietalia maritimae)
0.1
A
3150
Natural eutrophic lakes with Magnopotamion or
Hydrocharition - type vegetation
4
B
3270
Rivers with muddy banks with Chenopodion rubri p.p. and
Bidention p.p. vegetation
0.5
B
Code
Type
6410
Note: Global Assessment is a function of representativity, relative cover and degree of
conservation in accordance with the Standard Data Form for Natura 2000 Sites applied to all
Natura 2000 sites across Europe: A – excellent value; B – good value; C – significant value; no
code signifies that the habitat in question is not significant within the site.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
18
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
The site was designated for the conservation of 32 species of birds listed under
Annex I and 23 species of migratory birds not listed on Annex I. In addition
three species of mammal (two of which are listed as Near Threatened on the
IUCN Red List – Barbastella barbastellus, Western Barbastelle bat and Lutra
lutra, Eurasian Otter), two species of amphibian/reptile, five species of fish
and one invertebrates listed under Annex II. Full species lists, including
population residency and site assessment can be found in Annex A.
3.4.7
PLH 320033 Uroczyska w Lasach Stepnickich
PLH 320033 Uroczyska w Lasach Stepnickich was designated as a Site of
Community Importance (SCI) in December 2008. It covers an area of 47,194.6
ha of which 81% consists of inland water bodies. It contains the following
Annex I habitats.
Table 3.4
PLH 320033 Habitats
Code
Type
%
Cover
Global
assessment
6410
Molinia meadows on calcareous, peaty or clayey-silt-laden
soils
1
C
6510
Lowland hay meadows (Alopecurus pratensis, Sanguisorba
officinalis)
2
C
7110
Active raised bogs
1.7
B
7120
Degraded raised bogs still capable of natural regeneration
0.3
9190
Old acidophilous oak woods with Quercus robur on sandy
plains
10
C
91D0
Bog woodland
30
B
91E0
Alluvial forests with Alnus glutinosa and Fraxinus excelsior
(Alno-Padion, Alnion incanae, Salicion albae)
10
A
Note: Global Assessment is a function of representativity, relative cover and degree of
conservation in accordance with the Standard Data Form for Natura 2000 Sites applied to all
Natura 2000 sites across Europe: A – excellent value; B – good value; C – significant value; no
code signifies that the habitat in question is not significant within the site.
The site was designated for the conservation of 27 species of bird listed under
Annex I and 9 migratory bird species not listed on Annex I as well as 1 species
of mammal and one species of amphibian listed in Annex II. The Annex I
species Ficedula parva (red-brested flycatcher) is listed as near threatened on
the IUCN Red List. Full species lists, including population residency and site
assessment can be found in Annex A.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
19
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
3.4.8
PLB 320007 Laki Skoszewskie
PLB 320007 Laki Skoszewskie was designated as a Special Protection Area
(SPA) in July 2004. It covers an area of 9083.4 ha of which 65% consists of
grassland and scrub habitats. The site was designated for the conservation of
33 species of bird listed under Annex I. The Annex I species Acrocephalus
paludicola (aquatic warbler) and Ficedula parva (red-brested flycatcher) are
listed as vulnerable and near threatened on the IUCN Red List respectively.
Full species lists, including population residency and site assessment can be
found in Annex A.
3.4.9
PLB 320011 Zalew Kamienski i Dziwna
PLB 320011 Zalew Kamienski i Dziwna was designated as a Special Protection
Area (SPA) in September 2007. It covers an area of 12,506.9 ha, of which 38%
is inland water bodies and 35% is agricultural habitats. The site was
designated for the conservation of 26 species of bird listed under Annex I and
an additional 11 species of migratory bird not listed on Annex I. Full species
lists, including population residency and site assessment can be found in
Annex A.
3.4.10
PLB 320012 Puszcza Goleniowska
PLB 320012 Puszcza Goleniowska was designated as a Special Protection Area
(SPA) in September 2007. It covers an area of 25039.2 ha, of which 65%
consists of grassland and scrub habitats. The area does not contain any Annex
I habitats. The site was designated for the conservation of 36 species of bird
listed under Annex I and 4 regularly occurring migratory birds not listed on
Annex I of Council directive 79/409/EEC. The Annex I species Ficedula parva
(red-brested flycatcher) is listed as near threatened on the IUCN Red List. Full
species lists, including population residency and site assessment can be found
in Annex A.
3.5
PROTECTED AREAS
In addition to passing through Natura 2000 Sites, the pipeline passes through
parts of Wolin National Park and several areas valuable for wildlife as well as
near Olszanka Wildlife reserve (between Stepnica and Goleniov). As Figure
3.1 shows, these areas are far from mutually exclusive with the Natura 2000
sites.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
20
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
3.5.1
Wolin National Park
Wolin National Park was established in 1960 and is located in the vicinity of
the external port of Swinoujscie and spoil disposal sites. It covers an area of
4,700 ha and includes the following areas:
the Baltic cliff coast;
the Reverse delta of Świna;
the border of Mierzeja Przymorska;
a portion of Miedzydrojski forest;
coastal waters of the Baltic Sea; and
the coastal waters of the Szczecin Lagoon.
The project area is located about 4 km from the border of the buffer zone of
the Wolin National Park. Due to the distance from the project to the park, it is
not anticipated that operation of the planned facilities will have any impact on
the National Park. The only potential impact on the Park may result from
increased environmental pollution in the event that gas is transported from
the Terminal by tanker trucks. Also, the pipeline passes through parts of the
National Park.
In terms of the important species, Wolin National Park has a small population
of White-tailed Eagles (Haliaetus albicilla).
3.5.2
Olszanka Wildlife Reserve
The pipeline route passes near Olszanka Wildlife Reserve. This area is
covered by Galio-Carpinetum oak-hornbeam forests, a habitat listed on
Annex I.
In terms of the important species, Olszanka Wildlife reserve also has a small
population (2-3 pairs) of White-tailed Eagles (Haliaetus albicilla).
3.6
SPECIES OF CONSERVATION INTEREST
Of the Natura 2000 sites detailed above, additional species of conservation
interest are found in the three SCIs:
Wolin i Uznam SCI (PLH 320019);
Ujscie Odry i Zalew Szczecinski (PLH 320018); and
Uroczyska w Lasach Stepnickich (PLH 320033).
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
21
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
The species of conservation interest have been selected due to their
appearance on the national red list, being an endemic species, being protected
by International Conventions (incl. Bern, Bonn and Biodiversity) or for other
reasons, namely the quality and importance of the site for the species. The
other important species of flora and fauna found in Natura 2000 sites are listed
in Annex A, along with their reason for inclusion and population occurrence
within the site.
In addition to these species Talitrus saltator (sand hopper), which is found on
the beaches of the project area, is included on the Polish Red List.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
22
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
4
OVERVIEW OF POLISH ENVIRONMENTAL REGULATIONS
4.1
GENERAL OVERVIEW OF THE POLISH ENVIRONMENTAL REGULATORY SYSTEM
4.1.1
EIA
The Act on Providing Information on the Environment and Environmental
Protection, Public Participation in Environmental Protection and on
Environmental Impact Assessment, dated 3 October 2008 (Journal of Laws no.
199, item 1227) is a normative act that governs the procedures for assessing the
environmental impact of investments and public participation in such
procedures. The EIA Act implements the relevant EU legislation on EIAs, in
particular Council Directive 85/337/EEC of 27 June 1985 on the assessment of
the effects of certain public and private projects on the environment (Official
Journal L 175/40 of 5 July 1985, as amended). The EIA Act differentiates between
the types of projects where:
EIA is mandatory, or
the Competent Authority decides case-by-case decision whether an EIA is
required.
The Regulation of the Ministers Council, 9 November 2004 dated (Journal of
Laws no 257, item 2573, as amended) specifies the competent authorities, which
shall screen projects in terms of potential environmental impact and classify as
Annex I or II. The four Project Components were each screened and classified
by the competent authorities as per the EIA Regulation as follows:
Gas Pipeline and Jetty (Annex I projects) – EIAs were obligatory as per the
full scope of the EIA Act;
LNG terminal and Breakwater (Annex II project) the responsible authorities
are required to conduct an EIA and specify the scope.
The EIA Reports were prepared by the respective developers as required for
each Project Component and submitted to the authorities. For Annex I or II
projects that may have an impact on the Natura 2000 sites, an appropriate
assessment (habitat assessment) is part of the EIA.
For any other project (not included in Annex I or II) where the competent
authority issues a development-like permit and recognises that a project may
potentially have a significant impact on a Natura 2000 site, it shall issue a
decision to impose the obligation to submit the approval application to the
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
23
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Regional Director for Environmental Protection, which is competent in terms
of jurisdiction. Where it is found that the project will not have significant
impact on a Natura 2000 site, the Regional Director for Environmental
Protection shall provide, by way of a decision, that there is no need to carry
out the assessment of impact of the project on a Natura 2000 site. Otherwise,
the Regional Director for Environmental Protection shall impose the
requirement for the submission of a report on the impact of the project on a
Natura 2000 site and define the scope of this report. The scope of the report
on the impact of the project on a Natura 2000 site shall be limited only to the
determination of the impact of the project on the Natura 2000 site in terms of
the integrity and coherence of these sites.
In case the assessment of the impact of the project on a Natura 2000 site
indicates that the project may have a significant adverse impact on this site
and there is no reason of overriding public interest, the Regional Director for
Environmental Protection shall refuse to approve the conditions for the
implementation of the project.
After the assessment of the impact of a project on a Natura 2000 site has been
carried out, the Regional Director for Environmental Protection shall issue a
decision to approve the conditions for the implementation of the project in the
scope of the impact of the project on the Natura 2000 site.
Figure 4.1 presents the decision-making process for projects that might have
significant effects on Natura 2000 site.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
24
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Applicant requests the authority to permit implementation of the project
Authority recognizing that the project could have significant effects on area Natura 2000,
requires the applicant to submit documentation to the Regional Director of Environmental
Protection (RDEP)
Applicant shall submit to RDEP documentation, including Project Information Sheet with
information enabling a preliminary evaluation of the habitat impacts
RDEP on the basis of the provided documentation, after evaluation shall issue an order
imposing the obligation to
conduct habitat impact
assessment and defining the
scope of report
stating no need for habitat
assessment due to absence
of significant impacts on
Natura 2000
Report on the impact on Natura 2000 sites submitted by the applicant
RDEP submits to the authority to
carry out public consultation
Authority carries out a 21-day
public consultation and forward
RDEP all the comments and
conclusions
RDEP aproves the conditions for the implementation of the project or refuses to
aprove it, if it significantly affects the integrity of the Natura 2000 sites
Authority issues a decision authorizing the implementation of the project, taking into account
specific RDEP conditions or refuses to authorize the project
After habitat assessment the decision must be given to the public and the occured in course of
public disclosure comments and conclusions must be included in the grounds of the decision
Figure 4.1
Decision-making Process for Appropriate Assessment
4.1.2
Public Consultation
Pursuant to the EIA Act, all persons have the right to submit comments and
recommendations in procedures requiring public consultation, such as
procedure to issue a decision on environmental conditions or project
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
25
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
implementation on Natura 2000 site, when the approval of the Regional
Director for Environmental Protection is required. Prior to issuing or
changing a decision requiring public consultation, the authorities issuing the
decision are obliged to make the required information public without
unnecessary delay. Complaints and recommendations submitting can be
done in written form, orally and recorded in a log, or by email. Comments
and recommendations submitted after the deadline (statutory 21 days) will
not be examined.
4.1.3
Permitting
In accordance with the Law on Nature Protection, dated 16 April 2004 (Journal
of Laws no 151, item 1220, as amended) any activities that may destroy or disturb
protected species of fungi, plants or animals or their habitats are not allowed.
The protected species or habitats are listed in appropriate regulations of
Minister of Environment:
Regulation of the Minister of Environment of 9 July 2004 on the species of
wild plants under protection;
Regulation of the Minister of Environment of 9 July 2004 on the species of
wild fungi under protection; and
Regulation of the Minister of Environment of 28 September 2004 on the
species of wild animals under protection.
Additionally, the Regional Director for Environmental Protection can issue an
ordinance to protect the species of plants, animals or fungi not covered by the
protection provided by the national legislation, in the way of a regionally
applicable law for a specified period. The General Director for Environmental
Protection may grant exceptions to the prohibitions of picking, removal,
damage, translocation and breeding of strictly protected species of plants and
fungi, and also may allow deliberately killing, capturing or disturbing the
strictly protected species of animal. The General Director for Environmental
Protection also issues permits for these actions, if an area extends beyond the
boundaries of one region or if it has to do with the efforts made by the
minister responsible for the environment. The Regional Director for
Environmental Protection can authorise activities regarding partially
protected species of plants, fungi or animals that are located in the area of his
operation.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
26
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Permits may be issued on an application containing, respectively, among
others:
Purpose of implementing the proposed action;
Description of activities, which can be authorized;
Name of one or more species, which are the subject of activities;
Volume or number of individuals that will fall under the permit;
Methods and equipment used for catching, trapping, killing animals or
how the plants / fungi will be relocated and replanted;
Location and time of execution of the activities and the potential risks; and
Indication of who will be catching, disturbing or killing animals.
The Regional Director for Environmental Protection may permit to implement
a project that may adversely affect the Natura 2000 site, where there are
overriding interests of public order and at the same time there are no project
alternatives. In such cases, adequate nature compensation must be provided
to ensure integrity and proper functioning of the Natura 2000 site. In the
permit the Regional Director for Environmental Protection sets out the scope,
location, time and manner of implementation of the nature mitigation and
compensation activities (srodki minimaliyujace oddzialzywania), requiring its
implementation no later than the date of commencement of action that bring
the negative impacts. The project developer covers all nature mitigation and
compensation costs.
The EC Habitats Directive is the basis of Polish law providing for the
protection of many species of conservation interest. Article 12 of the Habitats
Directive provides that Member States shall take the requisite measures to
establish a system of strict protection for the animal species listed in Annex IV
(a) (which includes for instance all species of cetacean and bats) in their
natural range, prohibiting:
All forms of deliberate capture or killing of specimens of these species in
the wild;
Deliberate disturbance of these species, particularly during the period of
breeding, rearing, hibernation and migration;
Deterioration or destruction of breeding sites or resting places.
The prohibition referred to above applied to all stages of life of the animals to
which this Article applies.
In accordance with Water Law regulations, a business is required to possess
water permits if it carries out activities connected with water management
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
27
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
(e.g. operating surface or underground water intakes, discharging wastewater
or rainwater into water or soil) or discharging effluent into the sewage
systems that may contain substances that are particularly harmful to the
aquatic environment. Water permits are issued by the appropriate
administrative body: District Governor (Starosta), Regional Marshal (Marszałek
Województwa) or the Regional Director of Water Management Board
(Regionalny Zarząd Gospodarki Wodnej). Decisions are issued on the application
of the entity carrying out operations. A statement of water management
conditions should be attached to an application as well as other documents
required in a specified case.
Waste owners, depending on the type of activity being carried out, are
required to obtain a waste processing permit / decision approving a
hazardous waste management programme in such a degree of detail
according to the quantities of generated waste. An application for one of the
above decisions to be issued should be submitted to the competent authority,
which depending on the scale of the venture will be either the Regional
Marshal (Marszałek Województwa) or the District Governor (Starosta) in the
place where waste is processed. The total operating area should be provided
in the application. The developer is required to submit an application for
approval of a hazardous waste management programme to the appropriate
authority two months before the operations that create hazardous waste
commence or a change in operations affecting the type and amount of
hazardous waste created or the way it is managed. The Waste Management
Act places a requirement on each owner of waste to maintain a qualitative and
quantitative waste register in accordance with the relevant waste catalogue
and list of hazardous waste. This requirement does not concern producers of
communal wastes and private individuals.
Organisational units emitting pollution into the air are required to obtain a gas
and dust emission permit, in which emission standards are set out. The
issuing of permits for emitting pollution is governed by Regulation of the
Minister of Environment of 20 December 2005 on emission standards of
installation. Permits for emitting pollution into the air are issued for a period
of 10 years. Furthermore, cases of installations that do not require permits for
emitting pollution but require the operation of which needs to be notified are
set out also in Polish law.
An integrated permit is one of the types of permit for emitting substances or
energy and replaces the so-called component permits: for gas and dust
emission into the atmosphere, water permits for discharging the wastewater
into surface water or soil, for waste processing and permits for water
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
28
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
abstraction. These permits are issued by the Regional Marshal (Marszałek
Województwa) or the District Governor (Starosta). The total effect of the
pollution on all elements of the environment must be reflected in the permit as
well as the necessity of applying the best available techniques.
In Poland, there is a system of environmental charges for emitting gas and
dust into the atmosphere, discharging wastewater into the surface water or
the soil, water abstraction, waste disposal or reuse. The charges are set out in
the Regulation of Ministers Council dated 14 November, 2008. The charges
are set each year and are published in an announcement by the Minister of
Environment.
4.2
KEY ENVIRONMENTAL REGULATORY CONDITIONS
For the individual project components appropriate decisions and permits
were issued to enable the commencement of construction works.
Table 4.1, Table 4.2, Table 4.3 and Table 4.4 present the permits and decisions
already received as well as outstanding permits that will have to be obtained
prior to operation.
Table 4.1
Breakwater
Permit/ Decision
Date
Issued
Decisions on environmental conditions for implementation the
breakwater - for both on- and off-shore sections as an output of EIA
procedures
May 6, 2009;
June 9, 2009
Acceptance decisions on a design for a building and construction permits September 3, 2009;
January 15, 2010
for construction of the protective breakwater for the external port in
Świnoujście
Water permit for discharging the runoff water from the breakwater to the July 09, 2009
surface water in accordance with the Water Law Act;
Required Prior to Operation
Operation permit
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
29
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Table 4.2
Jetty
Permit/ Decision
Date
Issued
Decision on environmental conditions for implementation of the jetty
construction in the external port in Świnoujście
June 18, 2009
Acceptance decision on a design for a building and construction permit
for the jetty
January 15, 2010
Required Prior to Operation
Water permit for discharging the runoff water from the jetty area to the
surface water in accordance with the Water Law Act
Appropriate waste management consents according to Waste
Management Act
Wildlife derogations – if it is required during the construction stage in
accordance with the environmental supervisor recommendations
Operation permit
Table 4.3
LNG Terminal
Permit/ Decision
Date
Issued
Permissions for location of LNG terminal in a flooding area
May 27, 2009;
April 22, 2009
Non-forest land use permissions for the forest areas within the planned
LNG terminal site
June 12, 2008; June
15, 2009
Permission for trees/shrubs clearance
August 17, 2009
Permission to transfer the creeping lady‟s tresses from plots No. 150/4
and 20/4 in survey district 11 Świnoujście-Warszów, (situated in
Świnoujście, Ku Morzu street) to Międzyzdroje Forest District
November 14, 2008
Permission to remove the habitat of Epipactis atrorubens dark red
helleborine on plots No 4, 15, 16, 17, 12/4, and 150/4 in survey district 11
Świnoujście-Warszów
April 28, 2009
Permission to remove the habitats of plants subject to partial protection
on plots No 17, 20/4, 28, 29, and 31 in survey district 11 ŚwinoujścieWarszów
April 28, 2009
Permission to remove the habitats and refuges of animal species subject
to protection on plots No 4, 5,15,17, 20/4,29,31, 38,52, 64, 146/5, and
150/4 in survey district 11 Świnoujście-Warszów
April 29, 2009
Permission to remove the habitats and refuges of plants subject to strict
protection on plots No 15, 16, 17, 20/4, 52, 146/5, and 150/ in survey
district 11 Świnoujście-Warszów
April 29, 2009
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
30
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Permit/ Decision
Date
Permission to remove some fungi (lichens) species habitats from plots
No. 17, 28, 31, 146/5 in survey district 11 Świnoujście-Warszów
April 29, 2009
Permission to relocate from the place of regular occurrence, i.e. plots No
20/4, 52, and 146/5 in survey district 11 Świnoujście-Warszów species of
wild occurring animals (amphibians) subject to species protection to
another location
June, 8, 2009
Decisions on environmental conditions for implementation of the project
- for both on- and off-shore sections as an output of EIA procedures
February 12, 2009;
March 4, 2009
Water supply and sewage effluent disposal consent for intake and
discharging water in LNG tanks hydrotesting process
April 30, 2009
Rainwater discharge consent for LNG terminal area
January 8, 2010
Acceptance decisions on a design for a building and construction permits July 15, 2009; March
for the LNG terminal in Świnoujście
3, 2010
Required Prior to Operation
Water permit for the construction of water facilities and disposal of
wastewater into the soil or to the surface waters according to Water Law
Act;
Integrated permit according to Act on Environmental Protection Law
Appropriate waste management consents and waste register according to
Waste Management Act
Operation permit
Table 4.4
Pipeline
Permit/ Decision
Date
Issued
Decision on environmental conditions for implementation of a highpressure transmission gas pipeline Świnoujście – Goleniów
January 12, 2010
Required Prior to Operation
Decision on setting the location (to be issued by the Voivodeship of WestPomerania Region)
Wildlife derogations – if it is required during the construction stage in
accordance with the environmental supervisor recommendations
Tree clearance permits
Waste management consents
Waste register will be required while constructing
Acceptance decisions on a design for a building and construction permits
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
31
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
4.3
COMPLIANCE
The General or Regional Director for Environmental Protection may at any
time inspect the conditions set out in their issued permits connected with
nature protection or Natura 2000 compensation activities. Regarding the
decisions on environmental conditions issued for all four project components,
the developers can commence the constructions works, which should be
carried out under environmental supervision. The developer, before
commencement of the works, will submit to the Regional Director for
Environmental Protection in Szczecin a notification of having selected a
specialist who will perform the duties of the environmental supervisor. In the
case of any doubts raised by the Regional Director for Environmental
Protection in Szczecin about the competences of the selected person, his/her
candidacy will be forwarded to the Regional Council for Environmental
Protection for approval. In the case of a well-founded negative opinion
expressed by the Council, the developer will propose another candidate.
Environmental supervision includes activities such as:
Training for employees supervising the construction site;
Protective recommendations during the project development;
Inspection of the construction sites;
Reports in the form of periodic reports on the phases of construction works;
Recommendations on monitoring and reports on the performed
monitoring;
Any protective measures and reports on the protective measures taken.
In the case of disagreement between recommendations expressed by the
environmental supervisor and the site manager, the final solution will be
worked out with the participation of both the Regional Director for
Environmental Protection in Szczecin and the developer.
In order to confirm that all environmental conditions are met, inspections will
be made bythe Provincial Environmental Inspectorate (Inspekcja Ochrony
Środowiska). The process of inspections carried out by the Environmental
Protection Inspectorate is governed by the Environmental Protection
Inspectorate Act.
Waste management inspections are carried out by Environmental Protection
Inspectorate Inspectors and by authorised representatives of public offices
that issue decisions regarding waste management or verify required data
submitted on the basis of certain acts. In the event that any irregularities are
confirmed, the Environmental Protection Inspectorate is equipped with a wide
range of instruments to enforce the environmental protection requirements.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
32
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
The Environmental Protection Inspectorate also inspects the companies that
emit gas and dust into the atmosphere. In the event that acceptable emission
limits are exceeded as set out in permits, the provincial environmental
protection inspector levies a financial penalty.
Environmental Protection Inspectorate, as indicated by law, also has the
responsibility to measure noise emissions. Noise requirements are governed
by the Environmental Protection Act and the acoustic standards are set out in
the Regulation of the Minister of the Environment of 14 June 2007 on the
permissible noise levels in the environment. If acoustic standards are
exceeded the environmental protection body, either the District Governor
(Starosta) or the Environmental Protection Inspectorate (Wojewódzki Inspektorat
Ochrony Środowiska), issues a decision regarding the acceptable level of noise.
The integrated permits should be issued for installations together with an
acoustic analysis of the environmental impact.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
33
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
5
BASELINE STUDIES SUMMARY
Environmental impacts have been assessed on the basis of thorough
investigations that adequately describe the species present and their ecology
in the study area influenced by the Project. Table 5.1 presents the existing
baseline studies.
Table 5.1
Existing Baseline Studies in Support of Present EIA
Year
Subject
Investigator(s)
2007
Inventory and survey of bird fauna, bats, reptiles, amphibians
and snakes and invertebrate fauna.
Andrzej Zawal Ph.D.
- Team Manager;
Professor Aleh
Aleksandrovich Ph.D.
hab., Professor
Eugeniusz Biesiadka
Ph.D. hab., Stanisław
Czachorowski Ph.D.
hab., Professor at
UWM (WarmińskoMazurski University),
Piotr Dąbkowski
Ph.D., Dariusz Janicki
Ph.D., Grzegorz
Michoński M.A.,
Robert Rozwałka
Ph.D., Andrzej Zawal
Ph.D., Lech Pietrzak
Ph.D., Ewa Sarnacka
M.Eng., Dariusz
Wysocki Ph.D. hab.,
Sebastian Guentzel
M.A., Michał Jasiński
M.A., Zbigniew
Kajzer M.A., Łukasz
Ławicki, Magdalena
Dzięgielewska Ph.D.,
Robert Kościów M.A.
Summary: Analyses of fauna were carried out using observation
methods suitable to the individual groups of animals and their
biology.
Invertebrate fauna - species and distribution; the analysis
included taxonomy of most of the protected species covered by
European Conventions, including in particular water and land
snails, spiders, daddy longlegs, water mites, dragonflies, day
butterflies, epigeic beetles, water beetles and true bugs, caddis
flies and hymenopteras.
Batrachofauna and herpetofauna - species and distribution.
Teriofauna - species and distribution. In vivo observations.
Analysis of autumn and winter activities of bats.
Bird nesting - species, distribution and quantity.
Migrating birds - species, number, monitoring; also using the
results of analyses performed in previous periods.
2008
Floral inventory and survey
Krzysztof Ziarnek
Ph.D., Tomasz Łabuz
Summary: Studies were undetaken to assess plant cover of vasPh.D., Małgorzata
cular plants and bryophytes, identification of floral communities
Stasińska Ph.D.,
and natural habitats within the context of the Habitat Directive.
Anetta Wieczorek
Distribution of protected species and rare species and distribution
Ph.D., Magdalena
of vegetation sheets were mapped. Mycological samples (fungi
Ziarnek D.Eng., Piotr
and lichens) were taken for indexation and analysis of distribuWaloch M.Eng.
tion of rare and protected species.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
34
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Year
Subject
Investigator(s)
2008
Inventory of quality and plant composition of interdune
depressions (Habitat Code 2190)
Krzysztof Ziarnek
Ph.D., Magdalena
Ziarnek D.Eng.
Summary: A study was undertaken to identify species within,
distribution and areal extent of the code 2190 natural habitat ("inter-dune depressions") on the entire "Wolin i Uznam" refuge area.
This natural habitat was identified during work on the project's
environmental impact study. There were no data on it in the publications and documentation prepared for the Nature 2000 area.
The planned investment's impact on this habitat was analyzed in
the context of its existence in the entire refuge.
2008
Assessment of use of military facilities by bats
Summary: The military facilities adjacent to the planned investment were inspected. Facilities which may be of greatest significance to bats were selected. Protection measures were proposed to secure these locations as winter hibernation sites.
2008
Monitoring of bat population in military facilities
Summary: Monitoring of bat winter hibernation sites in military
fortifications located next to Świna river's eastern estuary near the
planned construction of the LNG terminal in Świnoujście in terms
of species and quantities as well as the population's winter hibernation conditions. Protection measures were proposed.
2008
Inventory and assessment of sediment quality and benthos in
marine and coastal environment
Summary: A benthic survey was carried out to assess the condition of basic elements of the marine and coastal faunal communities in the area directly adjacent to the planned construction of the
terminal. The composition and quantities of main components of
the seacoast biocoenosis were analyzed i.e. meiobentos and macrobentos, on the basis of field and laboratory research. In addition, tentative data on marine pollution were obtained through
laboratory determination of the polycyclic aromatic hydrocarbons
(PAH) content in the coastal sediments.
2007
Inventory of fish species
Summary: Qualitative and quantitative composition of ichthyofauna taking into consideration the species which have economic
significance, as well as endangered and protected species. Fish
communties in Sz. Lagoon and Pomeranian Bay were analysed.
2007
Forest habitat assessment
Magdalena
Dzięgielewska Ph.D.
Magdalena
Dzięgielewska Ph.D.
Teresa Radziejewska
Ph.D., Brygida
WawrzyniakWydrowska Ph.D.
Józef Domagała
Ph.D., Professor at the
University of
Szczecin, Marek Szulc
Ph.D.
Henryk Klimek Ph.D.
Summary: Evaluation of the forest ecosystem, including tree
stands (species, afforestation and density, health, age structure,
resources, quality), comparison of consistency of species occurring in tree stands with the potential tree stands resulting from
the types of habitat and environmental value of forests. Impact
Assessment of forest and shrub land in terms of the identified
values and changes brought about by the investment.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
35
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Year
Subject
Investigator(s)
2009
Assessment of species and habitat quality in Natura 2000 areas
along pipeline route
Environmental
Conservation Office
in Szczecin: Jolanta
Summary: This assessment entailed a comprehensive study aimed
Katarzyna
at identifying species and habitats of conservation interest along
Dylawerska, Marek
the designated gas pipeline route and the adjacent areas (the
Dylawerski,
installation zone and its vicinity). Emphasis was on identifying
Małgorzata Zimnickanatural habitats and species that are considered important in
Pluskota, Damian
accordance with annexes I and II of the Habitat Directive
Spieczyński
92/43/EEC and annex I of the Bird Directive 79/409/EEC).
The habitats studies include lagoons and lake lagoons; salt
marshes; mixed forests and dune woodlands; inter-dune
depressions; oxbows and natural eutrophic reservoirs with
Nympheion and Potamnion vegetation; Pohlio-Callunion
heathlands; thermophilic, inland sand turfs; Variegated Purple
Moor Grass meadows; Galio-Urticenea; Luzulo-Fagenion;
acidophilic oak forests; marsh woods and forests; willow marshes.
Animal species form Annex II of the habitat directive include:
river lamprey, sea lamprey, salmon, twaite shad, spined loach,
great crested newt, european fire-bellied toad, otter, beaver, thick
shelled river mussel, gray seal, large blue butterfly.
Bird species from Annex I of the Bird Directive include: tawny
pipit, eurasian golden plover, bluethroat, kingfisher, smew, redthroated loon, whooper swan, barred warbler, woodlark,
goatsucker, red-backed shrike, middle spotted woodpecker, black
woodpecker, corn crake, crane, white stork, honey buzzard,
western marsh harrier, red kite, white-tailed eagle.
The survey work included field work and desktop research
carried out for the purpose of obtaining and presenting the
specified information on the subject matter of the analyses. An
important element of work included analysis of historical data,
researcher‟s observations from previous years and collecting of
data that have not been published. Field work was performed
from spring 2008 to spring 2009.
The floral survey spanned the entire route of the planned gas
pipeline and included inventorying the flora and taking
photographs in the 2008 vegetation period, covering different
seasons.
The faunal research involved several inspections of the planned
gas pipeline's routes, taking into account the requirements for
observation of individual fauna groups and gathering anecdotal
information in the form of the survey (mostly among the
fishermen).
Thematic maps were prepared that present the information on
topographic maps on a 1:10000 and 1:50000 scale.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
36
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Whilst these studies informed the baseline information, a number of
additional studies were carried out aimed at obtaining a better understanding
of the possible interactions between the project and the environment. This has
facilitated the drawing up of feasible mitigation measures that were
incorporated in siting and design considerations. Table 5.2 lists additional
studies carried out in support of the EIA.
Table 5.2
Existing Technical Studies in Support of Present EIA
Year
Subject
Investigator(s)
2007
Preliminary assessment of environmental impacts.
Jolanta Sikorska,
M.Eng.
Summary: The project's potential environmental impact was
assessed by analyzing, among other things, the possible mutual
interactions between the project and the environment, which
may occur at the stage of executing the project as well as during
its operation and decommissioning. The transboundary context
was examined in terms of biotic conditions (fish fauna, migrating
birds, plant cover), and abiotic conditions (geomorphology,
geology and hydrogeology, acoustic climate, emissions,
hazardous incidents such as fires and explosions, tourism,
community impact). The assessment was made on the basis of
the project concept's degree of advancement as at 2007.
2007
Hazard and risk assessment
Wojciech Gola, Ph.D.
Summary: The assessment included the possible occurrence of a
natural disaster or technical failure, and also the foreseeable
consequences of such an event. The optimal methods and the
ways of preventing such situations were analysed, as well as the
factors mitigating their potential consequences. In addition, the
procedures aiming at limiting the extent of threats or secondary
events were analyzed.The analyses and forecasts pertain to the
system of transporting LNG from ships to tanks, the area around
the plant, as well as the areas located in its impact zones during
construction and future operation. The primary emphasis was
placed on the risk to humans, the natural environment and the
existing infrastructure.
2007
Technical design study
Filip Moskal, D.Eng
Summary: Description of the system of interconnected
technological lines, installations, devices and structures used for:
• unloading the liquefied natural gas from ships;
• storing LNG;
• regasification of the stored LNG;
• delivery of natural gas to the National Transmission System.
The demand for utilities was described and the issues related to
fire safety were discussed.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
37
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Year
Subject
Investigator(s)
2008
Assessment of water use, sewage and waste management
Paweł Molenda,
M.Eng.
Summary: The procedure for usage of water and discharge of
sewage as well as waste management was discussed. The types
of waste produced and its impact on the environment were
analysed, as well as the methods of handling this waste. The
impact on the water environment of the construction of
underground reinforcements was analyzed (sanitary sewage
system and rainwater drainage system, water network, drainage
of excavations). Recommendations were formulated for further
procedure in the area of water and sewage management and
waste management.
2007
Geomorphological impact assessment
Summary: Geomorphology of the onshore zone and the coastal
zone and trends in their changes in the area of the planned
project on the basis of: analysis of changes in the landscape and
sedimentological and geomorphological processes on the coast
and on the beach; predicted changes in the landscape on the
basis of the existing data concerning the development on the
area of the investment and information on potential threats to
the landscape resulting from interaction of strong storm winds;
predicting the course of natural geomorphological processes on
the basis of field analyses and observations, including in
particular the course of accretion and erosion processes as well
as eolic deflation and accumulation processes. In addition,
determination of the project's impact on geomorphology of the
onshore zone and the coastal zone during construction,
operation and liquidation of the project, and the scope of
environmental monitoring. The conclusions and
recommendations aiming at removing the threats to the
environment in the area of the conducted work and the project's
potential impact were formulated.
2008
Geological and geohazard assessment
Professor Ryszard K.
Borówka Ph.D.
A. Piotrowski Ph.D.
Summary: Geological structure (drilling 8 geological wells) and
tectonics of the area, geological and engineering conditions separation of the geotechnical layers, analysis of locations of the
existing mineral deposits in the light of the existing studies.
Examination of possible incidence of rarely occurring but violent
events such as earthquakes, tsunamis, landslides. Analysis of
water in the geological wells. The seismic properties of the area
were analysed. The analyses performed by GEOPROJEKT were
used for the needs of the terminal.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
38
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Year
Subject
Investigator(s)
2008
Hydrogeological assessment
Ryszard Hoc M.A.
Summary: Analysis of hydrogeological conditions in the context
of the aquifers in tertiary and quaternary formations, carried out
on the basis of the previously drilled geological wells. The water
provisioning methods and the water intakes were identified in
relation to the existing conditions and the planned demand. The
study further included an analysis of the impacts of the
investment in relation to the surface water.
2008
Air quality impact assessment
Summary: Calculations of the planned impact were performed
on the basis of the investment's description and the planned
technological process taking into account the existing
atmospheric conditions, (wind rose, air condition and quality), in
the context of possible application of various technical solutions
(various LNG regasification methods) for two types of gas: light
gas and heavy gas. Calculations were performed for the
proposed technical solutions which involve emissions i.e. LNG
regasification and LNG transport using motor vehicles. For
determination of emissions, the option of regasificators'
operation with water injection was adopted.
2007
Noise impact assessment
Summary: The noise level was analyzed in the context of the
anticipated technology taking into consideration the provisions
of the local spatial development plan and the actual
development of the investment area and the adjacent areas. The
permissible figures were determined separately for day and
night taking into account type of terrain, its development and
type of noise sources. Recommendations were put forward for
minimizing the noise levels at various stages of the investment
such as sound insulating barriers, noise silencers, planting
vegetation.
Wojciech
Paterkowski D.Eng.
Kazimierz Hundert
M.A.
Additional monitoring studies will be carried out throughout the construction
and project implementation stage. These monitoring studies are listed in
Chapter 8 of this Biodiversity Action Plan.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
39
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
6
OVERVIEW OF POTENTIAL IMPACTS TO BIODIVERSITY
This section provides an overview of the potential impacts to biodiversity as a
result of the project with special reference whether the project or any of its
components will or will not impact critical habitat and species of conservation
interest.
Impacts to biodiversity and critical habitats have been assessed as being not
significant in itself, or become or not significant once mitigation measures have
been implemented. Mitigation measures can be found in Section 7 of this BAP.
6.1
CONSTRUCTION
6.1.1
Breakwater and Jetty
The use of heavy equipment such as pile drivers, dredgers and floating cranes
for the duration of the jetty and breakwater construction near the mouth of the
Swina may disturb marine manammal and fish. As a result some species may
avoid the area during pile driving operations, and the fish migrations between
the Bay and the Lagoon may be temporarily disturbed. However, on
completion of works they are likely to return to the area. The area affected is a
not a critical habitat for mammals or fish.
In order to minimise the potential for disturbance of fish and mammals from
underwater noise, vibration piling will be the primary method of piling.
Exceptionally, if due to technical reasons the vibration piling will not be
possible to conduct, a hydraulic hammer will be used. Soft start procedures
will be applied to piling operations. If piling will have to be executed during
herring spawning, the piling will be reduced to technologically possible
minimum. Mitigation measures in the Decision on Environmental conditions
include a financial contribution towards a fish restocking programme over a
period of three years. Overall these mitigation and compensation measure will
reduce this impact to not significant.
Dredging and dredge disposal will lead to a loss or disturbance of seabed
habitat. The dredged area will be approximately 2 km2. Dredge spoil disposal
will occur at two designated sites of both altogether of approximately 15 km2
(12 km2 for the breakwater and 3 km2 for the jetty). Many benthic species are
tolerant of displacement and/or smothering, however, some inevitable loss of
benthic organisms will occur. No protected or unique species are present in
the area affected. Benthic communities are likely to recover; however, species
abundance and distribution may be altered due to changed hydrodynamic
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
40
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
conditions. This impact is considered not significant given the temporary loss
of a limited area of benthic communities and no notable secondary impacts to
fisheries productivity, marine mammals or birds.
The creation of the breakwater will add hard substrate in a predominantly
sandy environment. The structure will quickly become colonised by a
possibly diverse community of mussels, crustaceans (e.g.barnacles), macroalgae and other organisms that are currently also found on the existing
breakwater. The breakwater will also provide an important resting ground
for waders and gulls in the area. The impact of the breakwater on organisms
can be considered positive and is not included in Table 6.1.
6.1.2
LNG Terminal
The construction of the gas transmission installation and communication
infrastructure connecting the jetty with the LNG terminal will result in the
temporary loss of a 90 m strip of embryonic dune and white dune habitat
(habitat types 2110 and 2120 according Annex I of the EU Habitats Directive).
This habitat will largely regenerate after construction ceases although a
permanent loss of this habitat will occur along a narrow strip in the vicinity of
the proposed infrastructure (flyover) connecting the breakwater with the
terminal. This habitat is not considered critical habitat. This impact will be
not significant.
The impact of construction works on coastal dunes with herbaceous
vegetation (habitat type 2130 grey dunes) will be limited to an area of 0.3 ha.
This habitat will regenerate following construction and therefore this impact is
expected to be not significant. Similarly, about 0.46 ha of humid dune slacks
(habitat type 2190) will be directly impacted, but due to the small spatial
extent of the impact area, this impact will be not significant.
A loss of forested areas will result from tree felling and surface leveling
required for the installation of the LNG Terminal facilities. Mixed forest and
coniferous forest on the dunes (habitat type 2180) constitutes approximately
3.2 ha, i.e. less than 12% of the forested area within the LNG Terminal area
and is located on the outer areas of the forest. This habitat will be partially
preserved for screening purposes and impacts to this habitat will be minimal.
Although there will be a loss of habitat, impacts to this priority habitat will be
not significant.
In the south part of the site an area of 0.89 ha of humid intra-dune hollows
(habitat 2190) is found within an area of peat bog habitat. Common
Bladderwort (Utricularia vulgaris) and the Warnstorfia cfr. pseudostraminea moss
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
41
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
are regarded as species of particular importance within the peat bog habitat.
Impacts to the aquifer will result in the small areas of this habitat becoming
dried out temporarily although an area of 0.43 ha of this habitat will be
preserved in the screening green strip. After completion of construction,
conditions of the impact areas will return to normal. Impacts to humid intradune hollows will be not significant.
Within the habitats identified at the northern margin of the LNG Terminal
site, two known areas with a high number of amphibians (eg Moor Frog Rana
arvalis) will be damaged. Adverse impacts on one or some generations of
amphibian reproduction will occur although this will be spatially limited.
Amphibians have been moved to substitute habitats as per respective
Permission from RDOS (April 2009) and thus impacts to amphibians will be
not significant.
Approximately 30 ha of planted pine forests within the LNG Terminal site will
be removed. Any protected plant species occurring in the area will be
replanted in the adjacent forests managed by the Międzyzdroje Forest
Inspectorate. Although some of the pine forest will be removed, mitigation
measures to transplant protected plants to adjacent forest reduce the impact to
protected species to not significant.
Plants such as common ivy (Hedera helix), guelder rose (Viburnum opulus)
found across the project site are likely to be impacted during the construction
phase. In addition, there are a number of more sensitive plant species within
the project area which would suffer at a local or regional level if impacted by
construction works e.g. creeping rattlesnake plantain (Goodyera repens).
Mitigation to minimise impacts to the sensitive species Goodyera repens,
Epipactis atrorubrns and Utricularia vulgaris includes the translocation of these
species to nearby areas. Impacts to vegetation will be not significant.
Common and abundant fungi species occur within the LNG Terminal site.
Rare, endangered and protected species may occur within the site, however,
these are common across the wider area (Western Pomerania) and therefore
the terminal site is not a critical habitat for these species. Impacts to fungi
communities from disturbance are not significant.
Noise resulting from tree felling and other construction works will cause
disturbance to some invertebrates, amphibian, reptiles and mammals,
including protected species. Impacts will not affect these species at a
population level. Some bird species such as the protected woodlark (Lullula
arborea) and the red-backed shrike (Lanius collurio) are likely to find alternative
habitats to breed nearby. Tree felling will take place outside of the bird
breeding season (from mid-March to the end of August) to minimise
disturbance to breeding birds. In addition, to minimise impacts to hibernating
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
42
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
bats, felling will start at the end of August, from the north of the site towards
the south. The described mitigation measures together with the temporary
duration of increased noise indicate that impacts to fauna will be not
significant.
6.1.3
Pipeline
Construction
Habitat loss that may be caused by vegetation clearance necessary for the
construction of the pipeline is minimised due to the routing of the pipeline
parallel to existing pipeline corridors. Overall, the 80 km of pipeline require
the clearing of only 15 ha of forest and woodland. The width of the regular
construction strip will be 26 m, however, in forest areas it is reduced to 18 m.
Some of the cleared strip will be replanted but a 4 m wide zone free of trees
and bushes must be maintained. In areas of conservation concern, works will
be strictly limited to a reduced working strip to minimise disruption to
habitats and species. Reinstatement of the working strip after construction,
including replacement of vegetation that was temporarily transplanted will
mitigate the disruption to habitats.
The pipeline route passes through 1,370 m of thermophilous inland calcerous
grasslands (priority habitat type 6120) and 1,800m of dry heathland (habitat
4030); it is anticipated that these habitats will recover during the operational
phase of the project following construction activities. These measures reduce
the impact of habitat loss to being not significant.
Bird breeding may be disrupted by construction activities or tree felling.
However, these impacts are not significant due to mitigation measures to avoid
construction during the breeding season, i.e. construction only occurs during
two autumn and winter periods. In addition, according to the Decision of
RDOS, in areas in close proximity to protection zones designed for the whitetailed eagle, construction activities will not be carried out between 1 January
to 30 September, and along the whole route trees or bushes will not be felled
during the vegetation and birds breeding season, i.e. the period from 1 March
to 30 October. An additional measure to reduce the impact of construction on
birds is that before commencement of works in a particular section, an
ornithologist will check the route.
Habitats may be damaged by construction trench drainage. However, in
sections with high ground water table, the construction trench will be
temporarily drained by a special method that minimises drainage of the
surrounding habitats and reduces the impact to being not significant.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
43
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Impacts to flora and fauna within Natura 2000 sites due to pipeline
construction are reduced to not significant due to the mitigation measures
outlined in Chapter 7.
6.2
OPERATION
6.2.1
Breakwater and Jetty
Shallow sand bars present within the external harbour may be lost due to a
change in hydrodynamic conditions. Mitigation measures to create a similar
habitat through a foreshore nourishment programme directly to the east of the
breakwater will reduce the impact to not significant.
The beach to the east of the new breakwater may be adversely impacted by
the change in hydrodynamic regime. Beach replenishment is foreseen if postconstruction monitoring demonstrates that the beach to the east is adversely
affected by the structure. This impact is therefore not significant.
The beach and dune system bordering the external harbour will shift to a
mature dune system at the expense of a limited area that is currently
conducive to pioneer vegetation. However, pioneer vegetation will continue
to be present to the east of the new breakwater. This impact is not significant.
The presence of the breakwater and jetty poses a risk of collision with lowflying birds during fog conditions. Directional lights will be used to
illuminate the marine facilities in fog conditions, while keeping light pollution
to a minimum during night time. Monitoring will be carried out to establish
the magnitude of this impact. This impact is not significant.
6.2.2
LNG Terminal
The planned pipeline connecting the jetty with the terminal will be routed
overhead on columns. The spacing of these columns was designed to
minimise interference with the grey dune habitats (priority habitat type 2130).
Earthworks are expected to promote regeneration of some of the open habitats
(e.g. embryonic shifting dune and white dune complexes - habitat types 2110
and 2120). In the areas where no permanent land take occurs and provided
that the habitats are modified to a minimum extent as per intended mitigation,
the dune habitats are expected to regenerate fast. Impacts to dune habitats
will be not significant during the operational phase of the project.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
44
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Species of fungi are likely to be disturbed or lost during the construction
phase; however fungi communities are expected to recover following
construction, during the operational phase of the project. This impact will be
not significant.
The loss of approximately 30 ha of pine forest from tree clearance will reduce
available feeding grounds for bats, food resources for insectivorous bats and
disturbe bat migration routes. Artificial lighting emitted from the LNG
Terminal at night will attract nocturnal insects (eg moths), which may not only
affect the population of these invertebrates but also the available food
resources for bats although this has not been fully confirmed. The wintering
grounds of bats should not be adversely affected by the project provided that
forest stands are maintained around the facilities and appropriate mitigation
is carried out. This will ensure that species affected during construction will
return to the site. Impacts to bats will be not significant.
Similar to bats, should appropriate mitigation be carried out, bird species
affected from the clearing of the pine forest will return to the area during the
operational phase of the project. Small trees and shrubs (e.g. hawthorn, wild
European elderberry etc.) present on site will be favourable for these species.
The tall parts of the LNG terminal – being mainly the LNG storage tanks with
a height of 50 m and the 65 m tall flare – may pose a hindrance for bird
migration at the terminal location, which is near one of the main European
flyways for migrating birds. Field studies being performed to date in the
terminal area have, however, shown that fortunately the migration route is
apparently not directly at the Project site, but nevertheless PLNG is obliged to
undertake various mitigation measures, including placing appropriate
lighting on the tank shells as well as continued monitoring. With this
mitigation measures, impacts to birds will be not significant.
Various hymenoptera populations are likely to recover within the LNG
Terminal site during operation particularly if a stable population of seed
plants regenerates following earth works from the construction phase. It is
anticipated that invertebrates including protected species (e.g. ground beetles,
wasp spider) will flourish within the vicinity of forest stands and the lake.
Impacts to invertebrates will be not significant.
6.2.3
Pipeline
Regular pipeline operation is not associated with adverse impacts to the
environment. The pipeline is buried, and only occasionally tree removal will
be carried out to prevent trees and shrubs from damaging the pipeline. These
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
45
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
activities will take place outside the nesting season of birds of conservation
interest.
The pipeline will be embedded within a layer of gravel sand. If the trench is
cutting an impervious layer of silt or clay, there could be a lasting drainage
effect to the overlying and/or adjoining wet habitats. As appropriate and
required, additional mitigation measures will be implemented as per water
permits still to be obtained (This may include isolating of trench sections with
clay and loam barriers when the trench is filled back where necessary).
6.3
DECOMMISSIONING
The impacts that may result from decommissioning of any of the project
components are comparable to those associated with the construction phase.
It is currently not planned to remove any of the project components at the end
of the project lifetime. However, if decommissioning is required, disposal of
hazardous materials, demolition of structures and landscaping of the site will
occur in accordance with the environmental regulations at the time.
6.4
TRANSBOUNDARY IMPACTS
A distance of 4.5 km separates the project location in Poland from the German
border. The closest marine protected area on the German side is is the Natura
SCI Site Pommersche Bucht mit Oderbank (DE1652301) at about 30 km off shore
to the north-west of the LNG Project. In addition, there is the harbour
porpoise which is listed as an Annex IV species in need of strict protection
under the Habitat Directive.
Impacts which have been considered in this BAP-assessment that could have
potential transboundary impacts include an unplanned gas explosion, LNG
tanker spills, impacts to marine mammals and herring spawning from
underwater noise from piling activities during construction of the jetty as well
as impacts to marine organisms from sediment plumes. Based on the current
project design and proposed mitigation measures put forward in this BAP as
per Table 7.1 and 7.2, it is expected that the project will not result in significant
transboundary impacts to biodiversity.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
46
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
6.5
CUMULATIVE IMPACTS
Combined effects from LNG Project Components:
Whilst no explicit, overall cumulative impact assessment has been undertaken
as part of the EIA process for the LNG Project, the separate EIAs (and the
summary “Memorandum1”) have to some extent discussed this topic for each
component. Because the overall project straddles across three spatially
different areas each with different flora and fauna at risk, (i) the pipeline
route, (ii) the LNG terminal site and (iii) the external harbour (breakwater and
jetty) and dredge disposal sites, there is little chance of a significant
cumulative impact to biodiversity stemming from the interrelations of the
project components. The impacts of the individual project components
concentrate in these respective areas and there is little spatial overlap or
synergy in impacts to biodiversity to be expected.
Cumulative Impacts of the LNG Project with other plans or projects:
With respect to cumulative impacts resulting from the LNG Project and other
projects in the region, no significant impact potential has been identified.
The EIAs report the following projects to take place at the same time as the
LNG Project between the present up to about 2014:
Construction of a road tunnel under the Swina River to connect Wolin
and Uznam Islands as part of National Road No.3 (E75)
•
Construction of a parking lot with 75 spots for trucks at the EuroTerminal site (located on the right bank of the Swina about 5km from the
river mouth, and approx. 2 km from the LNG Terminal site)
•
Modernization and construction of new buildings and a new dock at the
Marine Renovation Shipyard (located on the right bank of the Swina
about 3.5 km from the river mouth and approx. 2 km from LNG
Terminal site)
•
Several various small projects in/around several villages along the Gas
Pipeline.
None of the above projects are in the immediate vicinity of the proposed LNG
Project construction sites and thus there are no expected cumulative impacts
to biodiversity due to construction area noise, emissions, or other effects.
1
BKP Memorandum „LNG Terminal on the Polish Coast in Swinoujscie, BKP, dated May 2010;
this document summarises the information of the three EIA Reports for the LNG Terminal, the
breakwater and the Jetty (i.e. does not include the Pipeline)
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
47
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
6.6
SUMMARY IMPACTS TO BIODIVERSITY, CRITICAL HABITATS AND SPECIES OF
CONSERVATION INTEREST
Table 6.1
Summary of Impacts to Biodiversity, Critical Habitats and Species of
Conservation Interest
Environmental Impact
Significant Not
Significant
Brief Justification
Construction
Breakwater and Jetty
Underwater noise on
marine mammals and fish
The area affected is not a critical
habitat for marine mammals or fish.
Disturbance of fish
migrations by heavy
machinery
Mitigation measures are in place to
compensate for the disturbance.
Dredging and dredge
disposal on benthic
communities (approx. 2 km²
dredge area and 12 km²
plus 3 km² dredge disposal
sites)
No protected or unique species.
Temporary loss of a limited area of
benthic communities. Recovery
within 3 years. No secondary impacts.
LNG Terminal
Damage and disturbance to
dune (enbryonic, white,
grey dune and humid dune
slacks) habitats
The limited area disrupted is not
considered critical habitat and the
dunes will regenerate following
construction. Pipeline route to the
jetty has been chosen to minimise
footprint.
(grey dunes = 0.3 ha, humid
dune slacks = 0.46 ha)
Damage and disturbance to
mixed forest and coniferous
forests on the dunes
Parts of this habitat will be preserved
and untouched. No critical habitat.
(loss of 3.2 ha)
Damage and disturbance to
humid intra-dune hollows
Impacts will be temporary and the
habitat will recover following
construction.
(0.46 ha)
Disturbance of amphibians
from impacts to habitat
Amphibians affected are accustomed
to fluctuations in water levels and
populations of affected species are
not at risk.
Removal of pine forests on
protected plant species
Protected plant species will be
transplanted to nearby forests. No net
loss of species will occur.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
48
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Environmental Impact
Significant Not
Significant
Brief Justification
Disturbance to fungi
communities
Fungi communities are abundant and
common across the wider area. This
area of forest is not critical habitat for
these species.
Noise disturbance to fauna
including birds, amphibians
and mammals
Time period constraints will minimise
impacts to birds and bats. Increased
noise will be temporary and cease at
the end of the construction period.
Pipeline
Habitat loss due to
vegetation clearance
(15 ha)
Mitigation measures are in place to
reinstate the baseline conditions in
the disturbed area.
Bird breeding disruption
caused by construction
activities and tree felling
Construction will not occur during
the bird breeding season and so
critical habitat will not be disturbed.
Habitat damage caused by
construction trench
drainage
Trench drainage methods will
minimise habitat disturbance; the EIA
report and the Decision identify
valuable habitats where a change of
water conditions could result is
advesre impact. This will be avoided
in the relevant sections by laying the
gas pipeline in a water filled cut or
during wintertime.
Loss of fauna and flora in
Natura 2000 sites
Mitigation measures are in place to
avoid and minimise impacts to flora
and fauna species of conservation
interest.
Operation
Breakwater and Jetty
Sand bars lost due to
hydrodynamic regime
changes
Mitigation measures are in place to
create new habitat to the east of the
new breakwater.
Beach habitat degradation
due to hydrodynamic
changes
Mitigation measures are in place for a
beach replenishment scheme if
warranted by monitoring.
Loss of pioneer vegetation
due to maturing sand dunes
Pioneer vegetation will be present
nearby.
Collision of birds with the
breakwater during fog
Directional lights will be used to
illuminate the breakwater in fog and
avoid impacts to birds.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
49
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Environmental Impact
Significant Not
Significant
Brief Justification
LNG Terminal
Disturbance to dune (white
and grey) habitats
This habitat is not critical habitat and
will regenerate relatively quickly
following construction.
Damage and disturbance to
vegetation
Mitigation measures include the
translocation of sensitive species to
nearby areas.
Disturbance to fungi
communities
Fungi communities are abundant and
common across the wider area. This
area is not critical habitat.
Disturbance to bat feeding
and migration
Mitigation measures are in place to
reduce impacts to prey and forest
stands.
Disturbance to birds and
hindrance to migration
Mitigation measures are in place to
minimise disturbance to migration.
Birds are expected to return to the
area following construction.
Disturbance of
invertebrates including
hymenoptera
Populations are expected to recover
Pipeline
Disturbance from tree and
shrub removal activities
Disturbance will take place outside
breeding season of birds of
conservation interest.
Possible lowering of water
table that affects adjacent
habitats
Mitigation measures will be taken
during construction to prevent a
lowering of the water table alongside
the trench.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
50
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
6.7
APPROPRIATE ASSESSMENT
Impacts to species and habitats were considered as part of the EIAs, decision
documents and gap analysis for this project and the results of which are
presented in this BAP. Particular attention has been paid to impacts to Natura
2000 sites, as per Polish regulatory requirements, since the project site is
within or in the vicinity of several Natura 2000 sites (see Chapter 2).
Screening as part of an the appropriate assessment (habitat assessment) of the
impacts of the project and project components on the integrity and
conservation objectives of Natura 2000 sites has been undertaken for this
project. The screening has established that the project does not adversely
affect the integrity of the Natura 2000 sites and therefore the project
components are exempted from a full appropriate assessment.
For one species, the marsh frog (Rana arvalis) which is listed in Annex IV of the
Habitat Directive as a species in need of strict protection, a derogation (1) has
been granted to move specimens of the frog to alternative sites and that the
success of the undertaking will be monitored. The species is considered a
common species in Poland in a favourable conservation status, typical of the
habitats in the study area and is encountered in many communities across the
region. The project site itself is not a crucial area for the maintenance of their
population. The species habitat extends over a wide area to the east of the site.
Despite being assessed as not detrimental to the integrity of Natura 2000 or
any species, the Competent Authority has imposed a number of monitoring
measures to ensure this indeed being the case. If the monitoring suggests that
impacts are occurring, the Competent Authority may request additional
mitigation or compensation measures to offset any adverse impacts.
(1) Derogation under Article 16 of Council Directive 92/43/EEC of 21 May 1992.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
51
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
7
PROPOSED MITIGATION MEASURES
The following tables present the mitigation measures for the project as
stipulated by the Competent Authorities permitting and approval conditions.
The tables include a number of additional mitigation measures to comply with
international standards and international standards covering Natura 2000
sites.
The source of the mitigation measure – either Competent Authority (“CA”) or
supplementary measure agreed by Sponsors with Lenders (”suppl.”) is
indicated in the tables. As can be seen from the action item tables, the
Competent Authorities have set out a comprehensive set of mitigation
requirements that make up the largest part of the action items reflected in the
tables. Where mitigation measures are not yet specified in detail, further
required actions have been added as well as the Performance Indicators in the
last column were inserted in addition. The columns indicating
“Species/habitat - Desired Outcome”, “Responsibility”, “Time Scale”,
“Additional Action” and “Performance Indicator” were supplemented by the
Consultant.
The tables focus on those mitigation measures related to the protection of
biodiversity and habitats (Further details and mitigation measures regarding
other environmental impacts can be found in the ESAP).
Mitigation measures for this project have followed the mitigation hierarchy as
set out by the EBRD‟s PR6. Mitigation measures have been designed firstly to
avoid impacts then to minimise, mitigate and offset impacts with the aim to
achieve no net loss or a net gain. Avoidance of impacts to biodiversity, species
and habitats was initially accomplished by appropriate site selection.
A performance indicator has been added that corresponds to the reporting
and communications strategy and that allows for the tracking and periodic
review of how the BAP is being implemented. This ensures that the client has
a means to monitor progress towards targets and objectives as well as to
measure performance in their achievement. Indicators are set at site and
company levels depending on needs.
An important condition imposed by the Competent Authorities requires that the
implementation of the entire project and application of mitigation and monitoring
measures is done under environmental supervision, i.e. under the supervision of
environmental protection specialist. The environmental protection specialist
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
52
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
must have documented experience in this field, as well as a higher education
degree in environmental protection. The details of this environmental
supervision are outlined in Section 4.3.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
53
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
7.1
BREAKWATER
Table 7.1
Mitigation Measures - Breakwater
Item
Source
Mitigation Measure - Breakwater
Species/habitat
Desired Outcome
Responsibility Time Scale
Additional Action
(if required)
Performance
Indicator
Minimise
disruption to fish
and marine
mammals
Investor
Include the
requirements of the
Environmental
Decision in tender
specifications
Environmental
Design
Requirements
Avoid impacts to
protected habitats
Investor
To be considered in
the work plan and
construction layout
plans of the
contractors
Environmental
Design
Requirements
Include relevant
measures in work
instructions for
contractors
Contractor scope
specifications and
contractor QMS
Pre-construction
BAP – CA
B1
BAP – CA
B2
Design the project to use the least acoustically annoying
techniques during construction.
Plans should be made to avoid interference to protected habitats
where possible; detailed recommendations regarding this issue
should be agreed under the Environmental Supervision.
Throughout
design
EPC contractor
planning
Throughout
design
EPC contractor
planning
Audit reports
Audit reports
Construction
BAP B3
Suppl.
Vibration piling will be the primary method of piling.
Exceptionally, if due to technical reasons the vibration piling will
not be possible to conduct, a hydraulic hammer will be used. Soft
start procedures shall be applied to piling operations.
If piling will have to be executed during herring spawning, the
piling will be reduced to technologically possible minimum
BAP – CA
B4
BAP – CA
B5
Ensure construction works are carried out in a manner that
ensures prevention of the soil-water environment pollution with
solid and liquid waste.
Minimise the footprint of any infrastructure, laydown areas or
equipment used.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
Minimise
Investor
Throughout
disturbance to
construction
EPC contractor
marine mammals
and fish, especially
herring
Avoid impacts to
water column and
beaches from
pollution
Investor
Avoid impacts to
coastline habitats
and Talitrus
Investor
FINAL
54
EPC contractor
Throughout
construction
Inspection and
monitoring of
piling according to
overall EMS and
QMS
Environmental
Design
Requirements
Audit reports
EPC contractor
Throughout
construction
Environmental
Design
Requirements
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Item
Source
Mitigation Measure - Breakwater
Species/habitat
Desired Outcome
Responsibility Time Scale
Additional Action
(if required)
Performance
Indicator
Dredging
mitigation
measures need to
be defined and
incorporated in
tender
specifications
Contractor scope
specifications;
salator.
BAP – Suppl.
B6
During application for dredging licences and permits, clarification Minimise benthic Investor
of the conditions is required from harbour authority (and
habitat and species
EPC Contractor
dredging Environmental Study Reports).
disturbance and
CA
avoid pollution.
Reduction of Dredging impacts on water quality and aquatic life:
Minimise impacts
1) Timing:
to herring
As per the environmental studies for dredge spoil disposal,
spawning
sediment disposal will be undertaken only outside the herring
spawning season (usually April-May, but subject to real
Minimise
environmental conditions of the spawning activity).
increased turbidity
2) Selection of vessels:
in the water
Use of Trailer Suction Hopper Dredgers TSHD to reduce the
column
overall period of high turbidity from dredging-related activities.
(2-5)
Reduce overflow allowed from TSHD whilst dredging.
3) Selection of equipment and methods:
use excavation and dredging methods to minimise suspension of
sediments (e.g. adjust the size of grabs, use of environmental
grab, silt screens (if needed), green valves (where possible),
recycling (part of) overflow water, overflow with bottom exit).
4) Apply Feedback Monitoring:
Depending on actual construction sequence: It is planned that all
dredging will be carried out in the area enclosed by the new
breakwater – with just about 10% access to the open sea.
Currently (beginning November 2010) there is 800m of
breakwater built and it is planned to be 70% complete prior to any
dredging.
In case of changes in the above envisaged sequence(ie dredging
takes place with wider open access to the sea), feedback
monitoring will be applied as follows: Turbidity levels generated
by dredging in the near shore area are to be monitored at the time
of dredging. Should turbidity measurements taken at 1 m below
surface at 600m downdrift of dredging operation exceed the
range of natural background levels, then the Contractor shall
adjust the operation by either (i) slow down dredging; (ii) move
dredge location to areas less prone plume dispersion; or (iii)
cease dredging.
5) Inspection and monitoring:
of dredging activities to be conducted to evaluate the
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
55
Preconstruction
and throughout
construction
Contractor QMS;
Ongoing inspection
and monitoring of
dredging activities
and turbidity
according to
overall EMS and
QMS –
readjustment of
strategies may be
required
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Item
Source
Mitigation Measure - Breakwater
Species/habitat
Desired Outcome
Responsibility Time Scale
Additional Action
(if required)
Performance
Indicator
Dredging
mitigation
measures need to
be defined and
incorporated in
tender
specifications
Design
specifications
effectiveness of impact prevention strategies, and re-adjusted
where necessary.
BAP – CA
B7
With regard to dredge spoil disposal:
a.) dump the dredged spoil only at locations designated for that
purpose;
b.) Dredged material will be analysed in order to select
appropriate disposal option and only used in subsequent
construction works when it contains no pollutants as specified in
the Regulation of the Minister of Environment on types of
substances and concentrations which determine that the spoil is
contaminated;
Minimise benthic Investor
Throughout
habitat and species
construction
EPC contractor
disturbance and
avoid pollution
Minimise impacts
to herring
spawning
Dredge disposal
plume modelling
will have to be
carried out.
c.) following completion of the dredging works, dispose of any
pollutants generated during the construction phase;
Permits for dredge
disposal
Dredge materials
handling and
disposal plan
Audit reports
d.) the dredging works shall be performed taking account of the
requirements for protection of marine waters against pollution;
e.) dredge spoil disposal to take place outside the herring
spawning season (subject to real environmental conditions).
BAP – CA
B8
Replenish beaches if significant losses of the beach sediment occur Mitigate impacts
due to construction activities.
to beach habitat
and shoreline –
loss of sediment
Investor
Throughout
construction/
after
construction
Reinstatement
Plan for
methods need to be reinstatement
defined
Instruction to
workers
Audit reports
BAP – CA
B9
BAP – CA
B10
During the implementation of the project, killing wild animals
and destroying their burrows, dens, other shelters and breeding
grounds is prohibited.
Form a very shallow (and partially raised of the water level)
sandbar on the eastern side of the newly-constructed breakwater,
in order to provide a convenient feeding and resting ground for
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
Avoid impacts to
Investor
species and
biodiversity –
decrease in species
population/
biodiversity
Throughout
construction
Offset the changes Investor
Following
to bird
construction of
EPC contractor
feeding/resting by
FINAL
56
Plan prePre-construction
construction survey survey
Habitat and species
protection plan
Instruction to
workers
Plan and design
foreshore
nourishment
Design
specifications
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Item
Source
Mitigation Measure - Breakwater
Species/habitat
Desired Outcome
Responsibility Time Scale
the species of birds currently occurring in the vicinity of the
creating an
existing breakwater (minimum height of 1.0 m and area of 2.5 ha). alternative
resting/feeding
place on the new
breakwater
BAP – CA
B11
During site restoration following the completion of construction,
existing habitat conditions must be taken into account.
Minimise changes
to baseline
conditions
breakwater
Additional Action
(if required)
Performance
Indicator
scheme
Contractor scope
specifications
Audit reports
Investor
Immediately
after
EPC contractor
construction
Reinstatement
Plan for
methods need to be reinstatement
defined
Instruction to
workers
Audit reports
BAP – CA
B12
The earth moved during the construction must be relocated in a
way that avoids changes to valuable habitats. Recommendations
should be made by the Environmental Supervisor.
Avoid impacts to
valuable habitats
Investor
Immediately
after
Environmental
construction
Supervision
EPC contractor
Reinstatement
Plan for
methods need to be reinstatement
defined
Instruction to
workers
Audit reports
Environmental
Supervision
recommendations
BAP – Suppl.
B13
General measures concerned with port operation that would also
apply to construction vessels are listed in Table 7.2 under
operation.
Operation
BAP – CA
B14
With regard to drainage:
Use equipment for cleaning rainwater from the breakwater;
Avoid pollution of Investor
the marine
environment,
especially the
water column
Throughout
operation
Environmental
Design
Requirements
Audit reports
Permits
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
57
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Item
Source
BAP – CA
B15
Mitigation Measure - Breakwater
Species/habitat
Desired Outcome
Replenish beaches if significant losses of the beach sediment occur Offset impacts to
during operation.
the shoreline
Responsibility Time Scale
Additional Action
(if required)
Investor
Reinstatement
Plan for
methods need to be reinstatement
defined
Instruction to
workers
Throughout
operation
Performance
Indicator
Audit reports
Photographic time
series analysis
Monitoring of the
coastal zone
BAP – CA
B16
Following the completion of the construction works, the beach
biocoenosis must be reconstructed in order to create in a natural
habitat for the protected species, namely the crustacean Talitrus
saltator
Minimise impacts
to Talitrus saltator
Investor
After
Reinstatement
Habitat and species
construction for methods need to be protection plan
5 years
defined
Plan for
reinstatement
Instruction to
workers
Annual monitoring
on rehabilitated
site (first 5 years).
BAP – CA
B17
Take measures to actively protect the dune ramparts being
formed or destroyed within the vicinity of the beach.
Avoid impacts to
sand dunes
Investor
Throughout
operation
Prepare dune
rehabilitation plan.
Analysis of time
series photographs
Dune rehabilitation
plan (if required)
BAP – CA
B18
The Sponsor should participate in increasing both the volume of, Offset disturbance
and the expenditure on, stocking the marine areas with fish,
to fish migrations
carried out by the Fish Stocking Committee (Komisja Zarybieniowa)
at the Ministry of Agriculture, and so far financed entirely from
the national budget. The increase in the stocking should amount
to a minimum of 20 % of the sums allocated by the Fish Stocking
Committee in each year for stocking the Odra river basin and the
Szczecin Lagoon with fish. The period of participation should last
a minimum of 3 years following the completion of the works.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
58
Investor
Fish Stocking
Committee
(The
Committee will
determine the
stocking area,
as well as the
fish species.)
For three years
after
construction
Establish
mechanism for
financial support
Minutes of meeting
Annual reports (3
years)
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Item
Source
Mitigation Measure - Breakwater
Species/habitat
Desired Outcome
Responsibility Time Scale
Additional Action
(if required)
Performance
Indicator
CA
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
59
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
7.2
JETTY
Table 7.2
Mitigation Measures - Jetty
Item
Source
Mitigation Measure - Jetty
Species/habitat
Desired Outcome
Responsibility Time Scale
Additional Action
(if required)
Performance
Indicator
Investor
Draw up specific
action plans aimed
at avoiding
interference with
protected habitats
Habitat and species
protection plan
Pre-construction
BAP – CA
J1
In the framework of measures aimed at minimising the impact on Minimise impacts
and supporting protection of the habitats a protective measures
to all habitats
plan should be developed and implemented, including:
Throughout
design
EPC contractor
planning
a.) with regard to the planned project‟s possible collision with
protected species‟ stands the Investor shall be obliged to acquire
permits to divergence from prohibition pursuant to Article 56
Point 4 of the Law on Nature Protection, dated 16 April 2004
(Journal of Laws Dz. U. No. 151, item 1220, as amended).
Instruction to
workers
b.) to abstain from fertilisation, providing rich soil layers, and
covering sand with peat or garden mould.
BAP – CA
J2
BAP – CA
J3
BAP – CA
J4
To design the project with consideration of water/ground
environment's condition in a way that precludes penetration of
any pollution whatsoever to the environment, inclusive of
providing the ship berth with equipment protecting the water
environment against accidental pollution.
Minimise impacts
to all marine and
beach habitats and
species
Investor
To design locations of storage of substances in quantities
necessary for the works‟ continuity, and to situate material and
waste storage as far from the coastline as possible with the aim of
counteracting potential threats to the sea ecosystem in the course
of construction.
Minimise impacts
to all marine
habitats and
species
Investor
Design project so that storage locations, vehicle manoeuvre yards, Avoid impacts to
access roads, and temporary auxiliary facilities in particular to
protected habitats
avoid interaction with protected habitats. Recommendations
should be agreed upon under the environmental supervision
framework.
Investor
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
60
Throughout
design
EPC contractor
planning
Environmental
Design
Requirements
Audit reports
Throughout
design
EPC contractor
planning
Environmental
Design
Requirements
To be followed
through
construction
Throughout
design
Environmental
planning
Supervision
EPC contractor
Audit reports
Draw up specific
action plans aimed
at avoiding
interference with
protected habitats.
Environmental
Design
Requirements
Habitat and species
protection plan
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Item
Source
Mitigation Measure - Jetty
Species/habitat
Desired Outcome
Responsibility Time Scale
Additional Action
(if required)
Performance
Indicator
Audit reports
Environmental
Supervision
recommendations.
BAP – CA
J5
Killing wild animals and destroying their burrows and lairs, as
well as other shelters and reproduction sites, shall be prohibited
during the project procurement.
Avoid impacts to
species and
habitats
Investor
Throughout
design
EPC contractor
planning and
procurement
Plan prePre-construction
construction survey survey
Habitat and species
protection plan
Instruction to
workers
Construction
BAP – CA
J6
To examine the dredged materials and to either use or dump the
dredged material that has been found to be non contaminated in
a dedicated location
Avoid impacts to
the water column,
benthic habitats
and all marine
species
Investor
Preconstruction
EPC contractor
and throughout
construction
Dredging
mitigation
measures need to
be defined and
incorporated in
tender
specifications
Environmental
Design
Requirements
Permits for dredge
disposal
Dredge materials
handling and
disposal plan
Audit reports
Routine monitoring
of seabed sediment
– annual reports
BAP – CA
J7
BAP – Suppl.
J8
In the event of spill of a petroleum product from a machine or a
vehicle on the construction site, to apply sufficient measures to
protect against penetration of harmful substances to water and
ground.
Avoid impacts to
the all beach and
marine habitats
and species
Investor
Vibration piling will be the primary method of piling.
Exceptionally, if due to technical reasons the vibration piling will
not be possible to conduct, a hydraulic hammer will be used. Soft
Minimise
disturbance to
marine mammals
Investor
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
61
EPC contractor
Throughout
construction
Plan for spill
response
Spill containment
equipment
Instruction to
workers
EPC contractor
Throughout
construction
Include relevant
Contractor scope
measures in tender specifications and
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Item
Source
Mitigation Measure - Jetty
start procedures shall be applied to piling operations.
If piling will have to be executed during herring spawning, the
piling will be reduced to technologically possible minimum
BAP – CA
J9
If during and after construction the project is responsible for the
significant loss of beach material (for example by heavy
machinery movements) the beach should be replenished with a
habitat compliant material.
Species/habitat
Responsibility Time Scale
Desired Outcome
and fish, especially
herring
Additional Action
(if required)
specifications
Performance
Indicator
contractor QMS
Mitigate impacts to Investor
Throughout
beach habitat and
and after
EPC contractor
shoreline
construction
Reinstatement
Plan for
methods need to be reinstatement
defined
Instruction to
workers
Inspection and
monitoring of
piling according to
overall EMS and
QMS
Audit reports
BAP – CA
J10
During site restoration, clean up and remediation following the
completion of construction, existing habitat conditions must be
taken into account.
Minimise changes
to baseline
conditions
Investor
Immediately
after
EPC contractor
construction
Reinstatement
Plan for
methods need to be reinstatement
defined
Instruction to
workers
Audit reports
Operation of jetty
BAP – CA
J11
Following the completion of the construction works, the beach
biocoenosis must be reconstructed in order to create in a natural
habitat for the protected species Talitrus saltator
Minimise impacts
to Talitrus saltator
Investor
After
Reinstatement
Habitat and species
construction for methods need to be protection plan
EPC contractor
5 years
defined
Plan for
reinstatement
Instruction to
workers
Annual monitoring
on rehabilitated
site (first 5 years).
BAP – CA
J12
To operate the project in a manner that precludes penetration of
any contamination whatsoever to the environment.
Avoid impacts to
all species and
habitats
Investor
EPC contractor
Throughout
operation
Environmental
Design
Requirements
specifications
Audit reports
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
62
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Item
Source
BAP – CA
J13
Mitigation Measure - Jetty
To ensure protection of the beach and shore zone within the
external port by way of the shore zone‟s permanent monitoring.
Species/habitat
Responsibility Time Scale
Desired Outcome
Allow for
Investor
Throughout
mitigation and
operation for
offsetting of
up to 5 years
unforeseen impacts
to species and
habitats
Additional Action
(if required)
Prepare plan for
monitoring
Performance
Indicator
Analysis of time
series photographs
Operation / construction of external harbour (general measures)
BAP – Suppl.
J14
The Project and project contractors will comply with IMO
requirements (MARPOL 73/78 and Annexes), HELCOM
recommendations and IFC guidelines where relevant. A number
of IMO Conventions and/or HELCOM recommendations will
enter into force as the Project progresses and therefore a system
will be in place to incorporate any changes in the Project design
or its activities.
Avoid impacts to
all species and
habitats
Investor
Throughout
planning,
construction
and operation
Include relevant
Relevant criteria
measures in tender implemented in
specifications
detailed design. All
requirements built
into an
Environmental
Management
System which will
assist in ensuring
that the project
remains compliant.
BAP – Suppl.
J15
All personnel will be provided with training on basic safety and
Avoid impacts to
environmental issues and procedures specific to the protection of all species and
the environment (e.g. spill response etc.) prior to assuming their
habitats
duties. This training should provide personnel with the necessary
skills and knowledge needed to conduct their jobs in a safe
manner, provide for health and safety of all persons, and protect
the environment.
Investor
Throughout
planning,
construction
and operation
Include relevant
Project general
measures in tender EMS System via
specifications
specific training
procedures and
within contractor
scope specifications
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
63
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Item
Source
BAP – Suppl.
J16
Mitigation Measure - Jetty
Species/habitat
Desired Outcome
Ship-based transportation of materials to or from the location of
Avoid impacts to
the LNG terminal and breakwater are to be carried out under the all species and
administration of those requirements and guidelines laid down in habitats
the Safety of Life at Sea Convention (SOLAS), including in
particular Chapter IX pertaining to the International Safety
Management (ISM) Code, The International Convention on Oil
Pollution Preparedness, Response and Co-operation OPRC), and
the International Convention on the Prevention of Pollution from
Ships (MARPOL 73/78), among others. The basis of the ship
owners management system should include guidelines, codes
and relevant international conventions to safeguard those
additional requirements of the Baltic Sea Special Area such as
those established by the Marine Environment Protection
Committee (MEPC) and Maritime Safety Committee (MSC) of the
International Maritime Organization.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
64
Responsibility Time Scale
Investor
Throughout
planning,
construction
and operation
Additional Action
(if required)
Include relevant
measures in tender
specifications
Performance
Indicator
Ship owners
management
system should
include guidelines,
codes and relevant
international
conventions.
Criteria
implemented into
vessel contractor
specifications and
contractors scope
for procurement.
EMS procedures
implemented into
contractor scope
and supervision
required
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
7.3
LNG TERMINAL
Table 7.3
Mitigation Measures – LNG Terminal
Item
Source
Mitigation Measure - Terminal
Species/habitat
Responsibility Time Scale
Desired Outcome
Additional Action
(if required)
Performance
Indicator
Pre-construction
BAP – CA
T1
While designing the pipeline bridge, in particular the location of
the supports on which the bridge is to be placed, the location of
natural habitats must be taken into account and their preservation
ensured.
Avoid impacts Investor
to natural
Environmental
habitats,
Supervision
especially sand
dunes
Throughout
design
planning and
procurement
Plan prePre-construction
construction survey survey
Include relevant
Environmental
measures in tender Design
specifications
Requirements.
Environmental
Supervision
recommendations.
Instruction to
workers.
BAP – CA
T2
The site establishment plan, in particular designation of the
laydown areas, vehicle circulation areas, access roads and location
of provisional auxiliary facilities, should take into account the
distribution of the patches of protected habitats in order to prevent
interference with them where possible; detailed recommendations
regarding this issue should be agreed under the Environmental
Supervision.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
Avoid
disruption to
protected
habitats
FINAL
65
Investor
Environmental
Supervision
Throughout
design
planning and
procurement
Incorporate in
layout plan for the
LNG Terminal. Loss
of breeding or
resting sites at the
northern margin of
the planned
terminal could be
minimised. This
option should be
checked and if not
feasible a proper
explanation is
needed.
LNG terminal site
layout plan.
Site manager
inspections –
construction
logbook.
Environmental
Supervision
recommendations.
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Item
Source
Mitigation Measure - Terminal
Species/habitat
Responsibility Time Scale
Desired Outcome
Additional Action
(if required)
Performance
Indicator
Construction
BAP – CA
T3
Minimise the range of the planned cutting of the existing forest
Minimise
Investor
stand, especially on the south and south-west side of the site of the impacts to
Environmental
project.
forest and
Supervision
avoid
Preserve the woodlots situated around the objects serving as bats'
disruption to
hibernacula.
bat hibernacula
Prior to
Plan prePre-construction
commencemen construction survey survey
ts of works
Instruction to
workers.
Environmental
Supervision
recommendations.
Audit report
BAP – CA
T4
Preserve the environmentally valuable natural habitats, using
them as vegetated buffer strips surrounding the site of the
planned project on the southern side, in the form of:
Avoid/
minimise
impacts to
habitats and
a. a patch of an older pine-stand with undergrowth vegetation
speciestypical of a seaside coniferous forest in the north-west side of the
including
area, with abundant share of dwarf shrubs in the undergrowth
undergrowth
(crowberry Empetrum nigrum, common heather, bilberry
vegetation,
Vaccinium myrtillus and red whortleberry Vaccinium vitis-idaea),
pine
including the sites of creeping lady's tresses Goodyera repens and
underwood
common honeysuckle Lonicera periclymenum, having an area of
and peatbog.
1.6 ha (a semi-natural forest growing on a dune with natural
woodland vegetation, and also initial pine forests growing on
dunes),
Investor
Environmental
Supervision
Prior to
Incorporate in
commencemen layout plan
ts of works and
throughout
construction
Environmental
Supervision
recommendations
and reports
Instruction to
workers.
b. a patch of a pine underwood with a share of birch, which
constitutes an initial forest community on a dune, probably
formed intrinsically on the southern edge of the site, between the
railway line and the managed tree stands, having an area of 0.25
ha (a semi-natural, initial pine forest growing on dunes),
c. a water hole with an adjacent peatbog near the southern edge of
the planned project site (raised bog).
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
66
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Item
Source
Mitigation Measure - Terminal
Species/habitat
Responsibility Time Scale
Desired Outcome
BAP – CA
T5
Earthworks in the vicinity of water bodies must be carried out
Minimise
outside the amphibian breeding season, ie outside the period from impacts to
March to June, unless the works commence outside these months. amphibians
Investor
EPC contractor
Throughout
construction
Additional Action
(if required)
Performance
Indicator
Plan preInstruction to
construction survey workers.
Include relevant
Environmental
measures in tender Supervision
specifications
recommendations
and reports.
Site manager
inspections –
construction
logbook.
BAP – CA
T6
During implementation of the project, killing wild animals and
destroying their burrows, dens, other shelters and breeding
grounds is prohibited.
Avoid impacts
to species
Investor
EPC contractor
Throughout
entire project
Plan prePre-construction
construction survey survey
Instruction to
workers.
Environmental
Supervision
recommendations
and reports.
Site manager
inspections.
BAP – CA
T7
While carrying out earthworks and performing excavations,
appropriate methods should be applied in order to limit the
possibility that vertebrates or invertebrates might fall into them.
Minimise
Investor
impacts to
EPC contractor
vertebrates and
invertebrates
Throughout
construction
Include relevant
Instruction to
measures in tender workers.
specifications
Environmental
Supervision
recommendations
and reports.
Site manager
inspections.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
67
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Item
Source
Mitigation Measure - Terminal
Species/habitat
Responsibility Time Scale
Desired Outcome
BAP – CA
T8
Animals which have fallen to an excavation must not be killed but Mitigate
helped to get out with minimum stress instead.
impacts to
fauna
Investor
EPC contractor
Throughout
construction
Additional Action
(if required)
Performance
Indicator
Prepare protocol
(instruction to
workers)
Instruction to
workers.
Environmental
Supervision
recommendations
and reports.
Site manager
inspections.
BAP – CA
T9
While implementing the project, earthworks and other works
involving use of mechanical equipment or technical appliances
should be carried out in the manner least harmful to trees and
shrubs.
Minimise
Investor
impacts to
EPC contractor
flora- trees and
shrubs
Throughout
construction
Include relevant
Instruction to
measures in tender workers.
specifications
Environmental
Supervision
recommendations
and reports.
Site manager
inspections.
BAP – CA
T10
Protect trees against mechanical damage.
Avoid impacts
to trees
Investor
EPC contractor
Throughout
construction
Include relevant
Instruction to
measures in tender workers.
specifications
Environmental
Supervision
recommendations
and reports.
Site manager
inspections.
BAP – CA
T11
The root clumps exposed during the works should be protected
against drying out.
Avoid impacts
to trees
Investor
EPC contractor
Throughout
construction
and operation
if necessary
Include relevant
Instruction to
measures in tender workers
specifications
Environmental
Supervision
recommendations
and reports.
Site manager
inspections.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
68
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Item
Source
Mitigation Measure - Terminal
Species/habitat
Responsibility Time Scale
Desired Outcome
BAP – CA
T12
Any cutting trees of shrubs must be carried out outside the bird
breeding season, ie outside the period from the 1st March to 31st
August, unless the works commence outside this period.
Avoid
disturbance to
bird breeding
Investor
EPC contractor
Throughout
construction
Additional Action
(if required)
Performance
Indicator
Include relevant
Instruction to
measures in tender workers.
specifications
Environmental
Supervision
recommendations
and reports.
Site manager
inspections.
BAP – CA
T13
Cutting trees and levelling of terrain must be carried out before
erecting the fence around the site. Alternatively, the fence must be
erected in a manner that enables animals to escape.
Minimise
disturbance to
fauna
Investor
EPC contractor
Throughout
construction
Include relevant
Instruction to
measures in tender workers.
specifications
Environmental
Supervision
recommendations
and reports.
Site manager
inspections.
BAP – CA
T14
When cutting trees commences in September, the works must be
started on the northern edge and move towards south.
Minimise
disturbance to
fauna –
especially bats
Investor
EPC contractor
Throughout
construction
Include relevant
Instruction to
measures in tender workers.
specifications
Environmental
Supervision
recommendations
and reports.
Site manager
inspections.
BAP – CA
T15
In order to minimise the effects of the project on hibernating bats it Minimise
Investor
is necessary to:
impacts to bats
EPC contractor
a. fix gratings temporarily (from November to February) on the
window and door openings in the selected military facility
included in the complex of flak batteries “Warszów – East”
situated 300 m away from the seaside artillery battery “Forst”,
b. increase the number of available hiding places and fissures in
this military facility (for example by means of applying
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
Throughout
construction
and operation
Include relevant
Instruction to
measures in tender workers.
specifications
Environmental
Prepare habitat and Supervision
species protection
recommendations
plan
and reports.
Site manager
FINAL
69
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Item
Source
Mitigation Measure - Terminal
Species/habitat
Responsibility Time Scale
Desired Outcome
horizontally perforated bricks or hollow masonry units),
Additional Action
(if required)
Performance
Indicator
inspections.
c. clear ventilation ducts of obstructions; this will enable inflow of
rainwater to the inside of the indicated facility in order to improve
its internal microclimatic conditions.
BAP – CA
T16
Ventilation ducts should be protected in order to prevent bats
Minimise
Investor
from entering, for example with a fine mesh; possibly, the fixed
impacts to bats.
EPC contractor
guards should enable animals to easily get out of them. Therefore,
consulting a specialist will be necessary.
Throughout
construction
and operation
Include relevant
Environmental
measures in tender Supervision
specifications
recommendations
and reports.
Identify specialist
Site manager
Prepare habitat and
inspections.
species protection
plan
BAP – CA
T17
Any structures jutting up more than 10 m above the tree tops (for
example a flare stack or LNG tanks) must be equipped with
floodlights in order to illuminate them as to prevent migrating
birds from colliding with the structures, in agreement with the
competent services
Throughout
construction
and operation
Include relevant
Environmental
measures in tender Supervision
specifications
recommendations
and reports.
Minimise
impacts to
migrating
birds.
Investor
EPC contractor
Site manager
inspections.
The transmission pipeline should be placed at a height not
exceeding the height of the nearby tree tops, where possible.
BAP – CA
T18
BAP – CA
T19
The night time lighting should be designed in such a manner so as Minimise
Investor
to illuminate only the desired surfaces, in order to prevent
impacts of light
EPC contractor
emission of unnecessary “light pollution"; therefore, lanterns
on birds.
providing directional light need to be applied, in agreement with
the competent services.
Throughout
construction
and operation
As part of the measures minimising the impact and supporting the Minimise
protection of habitats, the Investor shall implement the plan of
impacts to
protective tasks The protective tasks will include:
habitats
Throughout
construction
and operation
Investor
Environmental
Supervision
a.) a strip of natural habitats within the limits of the habitat refuge
“Wolin i Uznam” having an area of approx. 200 ha, agreed under
the Environmental Supervision,
Avoid impacts
from invasive
species and
protection of
b. control of invasive species, in particular trees and shrubs within
Elymus farctus
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
70
Include relevant
Environmental
measures in tender Supervision
specifications
recommendations
and reports.
Site manager
inspections.
Prepare habitat and Implementation of
species protection
Plan of Protective
plan
Tasks (Habitat and
species protection
Plan for preplan).
construction survey
and subsequent
Environmental
monitoring
Supervision
recommendations
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Item
Source
Mitigation Measure - Terminal
Species/habitat
Desired Outcome
the area described in the subparagraph a. above, which especially and Goodyera
concerns the following species: laurel willow Salix pentandra,
repens and
sharp-leaved willow Salix acutifolia, silverberry Elaeagnus
dunes.
commutata, black locust Robinia pseudoacacia, wild black cherry
Prunus serotina, box alder Acer negundo, Japanese knotweed
Reynoutria japonica; this control requires a methodology of
measures to be set in order to take into account the legal and
organisational procedures for the land administered by the
Maritime Office and the Forest District Office of Międzyzdroje.
The Investor‟s share in this programme would be limited to cofinancing of both the protection programme and the works
consisting in elimination of invasive species, as well as monitoring
the efficiency of this action, in agreement with the owner of the
land,
c.) co-financing of the measures as part of the protection
programme for sand couch grass Elymus farctus, prepared
together with the Environmental Supervisor, with participation of
the land administrators,
d.) transfer of the sites of creeping lady‟s tresses Goodyera repens,
on the basis of the already received approval of the Minister of
Environment,
e.) as regards the other protected species, for which an interference
of the planned project with their sites has been identified, the
Investor is obliged to obtain permissions for derogation from the
prohibitions pursuant to Article 56 of the Nature Conservation Act
of 16 April 2004 (Dz.U. [Journal of Laws] No. 92, Item 880 as
amended),
Responsibility Time Scale
Additional Action
(if required)
Performance
Indicator
Include relevant
and reports.
measures in tender
Invasive species
specifications
monitoring reports.
The feasibility of the
Transferring plant
following needs to
reports (3 years).
be checked
Audit report.
“Designation of a
little bog and initial
pine forest on a
dune at the
southern margin of
the site to be
preserved as part of
a vegetated buffer
strip between the
LNG Terminal and
an adjoining
railway line” (p. 169
EIA, Section I C No.
15 b+c main
decision document):
at least the bog
should not be part
of a buffer strip, but
rather needs a
buffer strip itself to
be protected against
adverse impacts.
f.) organisation of the tourist traffic by means of construction,
carried out together with the local self-government, of a new
walkway down to the beach, as well as construction of a parking
area serving the tourists visiting the beach, to the west from the
side of Ku Morzu street; the creation of such a parking area would
in a natural manner shift the main mass tourism impact on the
beach to the east from the planned project; the Investor‟s share
would be limited to financing and construction of both the
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
71
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Item
Source
Mitigation Measure - Terminal
Species/habitat
Responsibility Time Scale
Desired Outcome
Additional Action
(if required)
Performance
Indicator
walkway down to the beach and the parking area, on the basis of
the approved and submitted design, as well as a building permit
(the Investor would not be responsible for obtaining the building
permit and developing the design of the parking area),
g.) putting under protection the best preserved, in terms of
environmental condition, part of dunes on the Przytorska Spit,
indicated in the natural valorisation as an ecological site; it
concerns, in particular, preparation of documentation concerning
the ecological site, and submitting a request to the local selfgovernment body for designation of the ecological site; marking
the area to be put under protection, including education and
information boards.
BAP – CA
T20
In order to minimise the impact of the project on the other patches
of natural habitats situated distantly from the planned project, it is
necessary to take measures to prevent a permanent lowering of the
surface water and groundwater levels outside the site of the
project.
Minimise
impacts to
habitats
situated at a
distance from
project site.
Investor
Offset tree
felling and
ground
clearance
Investor
EPC contractor
Throughout
design
planning,
construction
and operation
Include relevant
Environmental
measures in tender Design
specifications
Requirements
Prepare for
groundwater level
monitoring
Groundwater level
monitoring report.
Operation
BAP – CA
T21
Following completion of the project, as part of landscaping works
provide additional planting of trees (5-10 years old) and shrubs
from the side of the built-up areas, so that they would form a
dense vegetated buffer strip in the future.
EPC contractor
After
construction
Prepare plan for
replanting
Plan for replanting
Environmental
Include relevant
Supervision
measures in tender recommendations.
specifications
Site manager
inspections.
Audit report.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
72
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Item
Source
Mitigation Measure - Terminal
Species/habitat
Responsibility Time Scale
Desired Outcome
BAP – CA
T22
Provide the vegetated buffer strip in such a manner as to ensure
that lower trees and shrubs (for example hawthorn, elder and
others) are located between the taller trees in order to create
habitats for birds such as red-backed shrike Lanius collurio.
Offset ground
clearance
Investor
EPC contractor
After
construction
Additional Action
(if required)
Performance
Indicator
Prepare plan for
replanting
Plan for replanting
Environmental
Include relevant
Supervision
measures in tender recommendations
specifications
and reports.
Site manager
inspections.
BAP – CA
T23
BAP – CA
T24
All the plantings should be made using species compatible with
Avoid
Investor
the currently existing habitat conditions (introduction of alien and introduction of
EPC contractor
potentially invasive plant species is prohibited).
alien and
potentially
invasive plant
species
After
construction
Upon the construction work‟s completion the beach biocoenoses
should be restored, thus naturally providing habitat for protected
species, Talitrus saltator.
After
construction
for 5 years
Offset impacts
to the habitat
for protected
species,
Talitrus
saltator.
Investor
EPC contractor
Prepare plan for
replanting
Include relevant
measures in tender
specifications
Environmental
Supervision
recommendations
and reports
Reinstatement
Habitat and species
methods need to be protection plan
defined
Plan for
reinstatement
Instruction to
workers
Annual monitoring
on rehabilitated
site (first 5 years).
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
73
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
7.4
PIPELINE
Table 7.4
Mitigation Measures - Pipeline
Item
Source
Mitigation Measure - Pipeline
Species/habitat
Responsibility
Time Scale
Additional Action
(if required)
From design
through to
construction
and operation
Include relevant
Environmental
measures in tender Design
specifications
Requirements
From design
and
throughout
construction
Include relevant
Environmental
measures in tender Design
specifications
Requirements
Throughout
construction
Include relevant
measures in tender
specifications;
consequently,
contractor to
include in the
detailed site
planning for the
construction spread
and layout plans
(also applies to
below).
Desired Outcome
Performance
Indicator
Pre-construction
BAP – CA
P1
BAP – CA
P2
Taking into account the ground and water environment setting,
design, implement and operate the project in a manner excluding
the penetration of any pollutants to that environment
Avoid pollution to Investor
habitats and
EPC Contractor
impacts to species
Use technology for the design, works and workmanship that will
Minimise impacts
cause the least possible interference with the groundwater
to habitats
environment and natural and plant and animal habitats, including:
Investor
EPC Contractor
Design the crossings of the pipeline through any obstacles
encountered in the area such as rivers, natural watercourses and
drainage/irrigation ditches in a manner minimising changes to the
flowing waters caused by disturbing the bottom sediments, silting
up or contamination due to the works on the passage or drilling,
Audit reports
Check on
Audit reports
cumulative impacts
along the whole
pipeline
Construction
BAP – CA
P3
Minimise areas designed for the construction backup facilities,
places for storing wastes and materials as well as technological
roads, and, upon completion of the construction, reclaim the areas.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
Minimise impacts
to habitats
FINAL
74
Contractor
Confirmation
reported by
Environmental
Construction
Supervisor
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Item
Source
Mitigation Measure - Pipeline
Species/habitat
Responsibility
Time Scale
Additional Action
(if required)
Desired Outcome
Performance
Indicator
BAP – CA
P4
When deciding on areas for materials and equipment bases,
exclude locations with shallow ground waters in permeable
deposits and in the proximity of watercourses, water reservoirs and
drainage/irrigation systems; prefer existing paved areas for this
use.
Avoid impacts/
pollution to the
ground
environment
Contractor
Throughout
construction
Include relevant
Environmental
measures in tender Design
specifications and
Requirements
layout plan
Confirmation
reported by
Environmental
Construction
Supervisor
BAP – CA
P5
Avoid locating storage areas and construction backup facilities
within the reach of heads of trees.
Avoid damage to
trees
Contractor
Throughout
construction
Include relevant
measures in tender
specifications and
layout plan
Environ,mental
Design
Requirements
Confirmation
reported by
Environmental
Construction
Supervisor
BAP – CA
P6
Ensure that the construction works are carried out in a manner not
to pollute the groundwater environment with solid or liquid
wastes.
Avoid impacts/
pollution to the
ground
environment
Contractor
Throughout
construction
To be included in
work plan of
contractors
Environmental
Design
Requirements
Instruction to
workers
Confirmation
reported by
Environmental
Construction
Supervisor
BAP – CA
P7
Upon completion of the earthworks, it is necessary to reclaim the
entire working strip in order to bring land to a state as close to its
original condition as possible.
Minimise changes Contractor
to baseline
conditions
After
construction
completion
Reinstatement
methods and plan
to be developed by
contractor and
agreed with
environmental
supervisor
Plan for
reinstatement for
each construction
spread
Instruction to
workers.
Confirmation
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
75
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Item
Source
Mitigation Measure - Pipeline
Species/habitat
Responsibility
Time Scale
Desired Outcome
Additional Action
(if required)
Performance
Indicator
reported by
Environmental
Construction
Supervisor
BAP – CA
P8
In order to reduce noise emission that may affect species:
carry out any construction works in the proximity of areas
protected against noise in daytime, ie between 6 am and 10 pm;
at places protected against noise and particularly
environmentally sensitive areas, avoid overlapping and
cumulating noise sources, eg simultaneous operation of engines,
saws, excavators and transport vehicles.
BAP – CA
P9
A protection task plan should be prepared and implemented for
the ban on location of locating the construction backup facilities
and storing construction materials, excavated earth etc. on areas
with high natural value where precious species of plants, animals
and fungi were found, as well as areas with protected nature
habitats or plants and animals habitats that were incorporated in
the Natura 2000 network
Avoid/ minimise
impacts to noise
sensitive species,
such as bats
Implementation
by Contractor
Avoid/ minimise
impacts to
sensitive species
and or habitats
including Natura
2000 sites
Investor
Throughout
construction
Supervision by
Gaz-System‟s
Construction
Supervisor
Contractor
Throughout
construction
Include relevant
measures in tender
specifications
Instruction to
workers
Include relevant
measures in tender
specifications and
layout plan
Habitat and species
protection
requirements
reflected in
construction layout
and time plan
Supervisors report
Instruction to
workers.
Confirmation
reported by
Environmental
Construction
Supervisor
BAP – CA
P10
A protection task plan should be prepared and implemented for
the protection of the Natura 2000 network areas where protected
plant and animal species as well as nature habitats and habitats of
plants and animals exist, as identified and marked on maps. These
locations should be marked with proper signs on site and protected
in a manner ensuring that throughout the entire time of the
construction works they remain intact, and if this is impossible,
then permissions should be sought.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
Minimise and
avoid impacts to
Natura 2000 sites
and species
FINAL
76
Investor
Contractor
Throughout
construction
Include relevant
measures in tender
specifications and
layout plan
(implementation of
measures as per
Annex No. 2 of the
Decision on
Environmental
Habitat and species
protection
requirements
reflected in
construction layout
and time plan
Instruction to
workers.
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Item
Source
Mitigation Measure - Pipeline
Species/habitat
Responsibility
Time Scale
Desired Outcome
BAP – CA
P11
A protection task plan should be prepared and implemented for
construction works in the proximity of amphibian breeding sites.
Open trenches should be maintained for a time as short as possible
so as not to cause the water level to lower in the reservoirs. If a
trench is maintained for a longer time, it should be appropriately
secured.
Minimise
disturbance to
amphibian
breeding
Investor
Contractor
Throughout
construction
Additional Action
(if required)
Performance
Indicator
Conditions of
RDOS dated …
January 2010 (ref.
no. RDOŚ-32WOOŚ.TŚ-6613/379/09/at)
Confirmation
reported by
Environmental
Construction
Supervisor
Include relevant
measures in tender
specifications and
layout plan
Habitat and species
protection
requirements
reflected in
construction layout
and time plan.
Instruction to
workers.
Confirmation
reported by
Environmental
Construction
Supervisor
BAP – CA
P12
Any construction and preparatory works in the proximity of partial Avoid disruption
protection zones designed for white-tailed eagle breeding pairs
to white-tailed
within the territory of Międzyzdroje Forest District (Nadleśnictwo eagle breeding
Międzyzdroje) (two locations at a distance of 20 m from each other)
and in Woliński National Park (Woliński Park Narodowy) (one
location) should be carried out beyond the breeding season, ie
beyond the period from 1 January to 30 September.
Investor
Contractor
Throughout
construction
Include relevant
Habitat and species
measures in tender protection
specifications
requirements
reflected in
construction layout
and time plan.
Instruction to
workers.
Confirmation
reported by
Environmental
Construction
Supervisor
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
77
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Item
Source
Mitigation Measure - Pipeline
Species/habitat
Responsibility
Time Scale
Additional Action
(if required)
Throughout
construction
Include relevant
Confirmation
measures in tender reported by
specifications
Environmental
Construction
Supervisor
Throughout
construction
Include relevant
Soil handling
measures in tender requirements
specifications
reflected in
construction layout
plan
Desired Outcome
BAP – CA
P13
Trees or bushes may not be felled during the birds breeding season Avoid impacts to
and tree-growing season, ie the period from 1 March to 30 October. tree growth and
bird breeding
Investor
BAP – CA
P14
Organic earth material (humus) should be gathered near the
construction site and subsequently used to improve the quality of
the surface area at places (and any surplus should be supplied to
interested parties for a similar use). It is recommended that humus
be stored separately in heaps to prevent mixing with natural
ground and degradation due to changes in temperature, humidity
and weathering and to preserve the microorganisms living in it. It
is particularly important in the case of humus collected in areas
with high natural value, where the material contains rhizomes,
corms, resting spores and other forms of phytocenoses of such
areas. Such an operation should be carried out beyond the plantgrowing season, ie beyond the period from 1 March to 30 October.
Mitigate
disruption to
construction site
biodiversity
Investor
In order to minimise the investment‟s impact on the protected
nature habitats and the habitats of plants and animals, perform the
instructions set out in Schedule 2 to the Decision. In particular, in
justified cases the following is recommended:
Minimise impacts
to habitats and
species, including
grasslands and
birds
BAP – CA
P15
Transplant grasslands – remove the upper layer of soil along with
plant resting spores (bulbs, rhizomes, roots, corms and seeds) and
spread it back over the surface of the (assembly) trench when the
basic construction works are completed; this action is obligatory in
the immediate surounding of the trench;
Confirmation
reported by
Environmental
Construction
Supervisor
The places of storage of the respective elements of protected
habitats and habitats of plants and animals as well as the methods
of storage and upkeep will be defined by a nature conservation
officer within the scope of the supervision and monitoring in the
course of the investment implementation;
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
Contractor
Instruction to
workers.
Transplant elements of protected habitats (single plant patches) for
the time of the works and replant them back in their places once
the basic construction works are completed;
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
Contractor
Performance
Indicator
Investor
Contractor
Throughout
construction
Prepare
transplantation plan
and protocol for
specific species
Habitat and species
protection
requirements
reflected in
construction layout
and time plan
Include relevant
measures in tender
specifications
Instruction to
workers
Addition mitigation
includes isolating
Confirmation
trench sections with reported by
clay and loam
Environmental
barriers when the
Construction
trench is filled back Supervisor
Inspections
FINAL
78
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Item
Source
Mitigation Measure - Pipeline
Species/habitat
Responsibility
Time Scale
Investor
Throughout
construction
Desired Outcome
Additional Action
(if required)
Performance
Indicator
Works within the habitats should be performed during the
recommended season of the year, in accordance with Schedule 2
hereto;
Anticipating works including preparation of the assembly surface
should be performed in early spring or late autumn; this applies to
mowing meadows and rushes, removal of shrubs during winter
time in order to exclude the possibility of animals starting to breed;
Ensure that the area is inspected by an ornithologist before any
works are commenced, which will ensure that any negative impact
on birds will be excluded, eg affecting an occupied nest or a pair
with non-flying chicks in the nest; such an inspection can also make
it possible to start works earlier, if no counter-indications are
reported, eg relating to breeding birds.
BAP – CA
P16
Within the biotopes of the Eurasian beaver (Castor fiber) and otter
(Lutra lutra), remove trees and shrubs in the zone where the
pipeline crosses the banks of watercourses.
Minimise impacts
to the Eurasian
beaver and otter
Contractor
Habitat and species
protection
requirements
reflected in
construction layout
and time plan
Instruction to
workers
Confirmation
reported by
Environmental
Construction
Supervisor
BAP – CA
P17
Within the biotope of the European fire-bellied toad (Bombina
bombina), start the preparatory and construction works in the
period from October to March and avoid changing the water
conditions in this area.
Avoid impacts to Investor
the European fireContractor
bellied toad
Throughout
construction
Include relevant
Habitat and species
measures in tender protection
specifications
requirements
reflected in
construction layout
and time plan
Instruction to
workers
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
79
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Item
Source
Mitigation Measure - Pipeline
Species/habitat
Responsibility
Time Scale
Desired Outcome
Additional Action
(if required)
Performance
Indicator
Confirmation
reported by
Environmental
Construction
Supervisor
BAP – CA
P18
Within the biotopes of the woodlark (Lullula arborea) and nightjar
(Caprimulgus europaeus), perform the preparatory and
construction works in the period from October to March.
Avoid impacts to
the woodlark and
nightjar
Investor
Contractor
Throughout
construction
Include relevant
Habitat and species
measures in tender protection
specifications
requirements
reflected in
construction layout
and time plan
Instruction to
workers
Confirmation
reported by
Environmental
Construction
Supervisor
BAP – CA
P19
Within the biotope of the tawny pipit (Anthus campestris), perform Avoid impacts to
the preparatory and construction works in the period from
the tawny pipit
September to March.
Investor
Contractor
Throughout
construction
Include relevant
Habitat and species
measures in tender protection
specifications
requirements
reflected in
construction layout
and time plan
Instruction to
workers
Confirmation
reported by
Environmental
Construction
Supervisor
BAP – CA
P20
Within the biotope of the golden plover (Pluvialis apricaria),
Avoid impacts to
perform the preparatory and construction works in the period from the golden plover
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
80
Investor
Contractor
Throughout
construction
Include relevant
Habitat and species
measures in tender protection
requirements
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Item
Source
Mitigation Measure - Pipeline
Species/habitat
Responsibility
Time Scale
Desired Outcome
November to February and from June to September.
Additional Action
(if required)
Performance
Indicator
specifications
reflected in
construction layout
and time plan
Instruction to
workers
Confirmation
reported by
Environmental
Construction
Supervisor
BAP – CA
P21
Within the biotopes of the bluethroat (Luscinia svecica), barred
warbler (Sylvia nisoria), corncrake (Crex crex), red-backed shrike
(Lanius collurio), perform the preparatory and construction works
in the period from November to March.
Avoid impacts to Investor
the blue throat,
Contractor
barred warbler,
corncrake and redbacked shrike
Throughout
construction
Include relevant
Habitat and species
measures in tender protection
specifications
requirements
reflected in
construction layout
and time plan
Instruction to
workers
Confirmation
reported by
Environmental
Construction
Supervisor
BAP – CA
P22
Within the biotope of the black woodpecker (Dryocopus martius), Avoid impacts to
perform the preparatory and construction works in the period from the black
October to February.
woodpecker
Investor
Contractor
Throughout
construction
Include relevant
Habitat and species
measures in tender protection
specifications
requirements
reflected in
construction layout
and time plan
Instruction to
workers
Confirmation
reported by
Environmental
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
81
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Item
Source
Mitigation Measure - Pipeline
Species/habitat
Responsibility
Time Scale
Desired Outcome
Additional Action
(if required)
Performance
Indicator
Construction
Supervisor
BAP – CA
P23
Within the biotope of the white stork (Ciconia ciconia), red kite
(Milvus milvus), honey buzzard (Pernis apivorus), perform the
preparatory and construction works in the period from October to
April.
Avoid impacts to
white stork, red
kite and honey
buzzard
Investor
Contractor
Throughout
construction
Include relevant
Habitat and species
measures in tender protection
specifications
requirements
reflected in
construction layout
and time plan
Instruction to
workers
Confirmation
reported by
Environmental
Construction
Supervisor
BAP – CA
P24
Within the biotope of the white-tailed eagle (Haliaetus albicilla),
perform the preparatory and construction works in the following
periods:
from August to December – in the case no direct impact is exerted,
Avoid impacts to Investor
the white-tailed
Contractor
eagle, its breeding
and roosting
Throughout
construction
from October to December – due to the protection of breeding sites,
from May to October – due to the protection of winter roosting.
Include relevant
Habitat and species
measures in tender protection
specifications
requirements
reflected in
construction layout
and time plan
Instruction to
workers
Confirmation
reported by
Environmental
Construction
Supervisor
BAP – CA
P25
Carry out mitigation measures for habitats (biotopes) of animals
incorporated in the Natura 2000 network in accordance with
Schedule 3 to the Decision, provided that consent of the Chief
Regional Officer for Environmental Protection (Regionalny
Dyrektor Ochrony Środowiska) or General Chief Officer for
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
Mitigate impacts
to Natura 2000
sites
FINAL
82
Investor
Contractor
Throughout
construction
Include relevant
Habitat and species
measures in tender protection
specifications
requirements
reflected in
construction layout
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Item
Source
Mitigation Measure - Pipeline
Species/habitat
Responsibility
Time Scale
Desired Outcome
Additional Action
(if required)
Environmental Protection (Generalny Dyrektor Ochrony
Środowiska) is required, in accordance with the provisions of
Article 56 Sections 1 and 2, and Article 52 Section 1, items 4 and 11
of the Environmental Protection Act dated 16 April 2004 (Dz. U. of
2009, No. 151, item 1220).
BAP – CA
P26
Mitigation measures for plant species and other animals protected
under the Nature Conservation Act, including for the area of the
Woliński National Park, natural heritage sites and other areas with
high natural value, distinguished based on the assessment of the
relative importance of nature sites in the respective communes or
municipalities, should be carried out in accordance with Schedule 4
hereto,
and time plan
Instruction to
workers
Confirmation
reported by
Environmental
Construction
Supervisor
Mitigate impacts
to plant species
and other animals
protected under
the Nature
Conservation Act,
including trees
Investor
Contractor
Throughout
construction
Include relevant
Habitat and species
measures in tender protection
specifications
requirements
reflected in
construction layout
and time plan
Instruction to
workers
Trenches within forest areas in the direct proximity of trees should
be excavated in a manner not to damage the rhizosphere (root
layer) of trees.
BAP – CA
P27
Performance
Indicator
Confirmation
reported by
Environmental
Construction
Supervisor
Net loss of forest (total about 33 ha) should be compensated by
Offset loss of
reforestation of fallow land in order to sustain quantitatively the
forest
regional forest stand. Suitable sites may be found in close vicinity
to the existing natural or near-natural forests of the reserves
impacted. Reforestation should be done using tree and scrub
species according to the potential natural vegetation of the selected
sites.
Investor
Contractor
Throughout
construction
Secure permits for
use of land
Prepare plan for
reafforestation
Habitat and species
protection
requirements
reflected in
construction layout
and time plan
Include relevant
measures in tender
Instruction to
specifications
workers
Confirmation
reported by
Environmental
Construction
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
83
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Item
Source
Mitigation Measure - Pipeline
Species/habitat
Responsibility
Desired Outcome
Time Scale
Additional Action
(if required)
Performance
Indicator
Supervisor
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
84
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
8
MONITORING PROGRAMME
Monitoring measures presented in the tables below have been extracted from
the decision documents of the Competent Authority for each of the project
components. The tables below focus on the monitoring requirements for
biodiversity and habitats.
Overarching conditions of the environmental monitoring programme that
apply to all project components include:
Environmental monitoring should cover both the site of the project
including ecologically sensitive boardering areas and the environment of
the beach and dunes and the environment of the beach and dunes,.
The detailed scale and scope of the monitoring shall be determined under
the Environmental Supervision.5
The monitoring should be performed separately for each of the 4 seasons
(spring, summer, autumn, winter), at the designated reference stations.
The results and conclusions from the monitoring research shall be
submitted to the Regional Director for Environmental Protection by the end
of each calendar year.
The scope of the monitoring shall be submitted for approval to the Regional
Director for Environmental Protection in Szczecin; it may be subject to
verification by the Regional Director for Environmental Protection in
Szczecin and, if necessary, it will be supplemented with the issues
indicated by this authority; and
The Regional Director for Environmental Protection in Szczecin, according to
the Decision on Environmental Conditions of RDOS, January 2010 (ref. no.
RDOŚ-32-WOOŚ.TŚ-6613/37-9/09/at) on the basis of the provided results of
the monitoring, may decide, for example, to require additional mitigation
measures or compensatory actions as appropriate.
All monitoring should be outlined in more detail and consistency, including
crucial problems/impacts, questions to answer, statistical methods, suitable
indicators, frequency of monitoring (including seasons) and actions in case of
identification of adverse impacts. Keystone species may be identified that can
be used as indicators to detect any significant. The design of a comprehensive
monitoring programme will require input from specialists and the scope shall
be discussed with and approved by the Competent Authority.
(1) 5 for the Terminal the „Monitoring Program and Mitigation Measures Plan“, dated 29-Jul2010 is availabe
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
85
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
8.1
BREAKWATER
Table 8.1
Breakwater Monitoring
Item
Monitoring (Breakwater)
Targeted
Species/Habitat
Period
Compliance/reporting mechanism
BAP –
MB1
Monitoring of protected habitats and species within the designated
Natura 2000 sites.
Protected species,
habitats and Natura
2000 sites
Once before the
commencement of the
construction works, during
construction phase and
continued for 5 years following
the completion of the project
Monitoring program agreed with
Environmental Supervisor and endorsed
by Competent Authority (CA - RDOS in
Szczecin)
Annual monitoring report
BAP –
MB2
Monitoring of the changes in the quantitative and qualitative status
of the birds and their habitats. Common methods such as counting
along a transect, counting over the sample plots at fixed points,
observing changes in the biology of the selected species should be
used. The magnitude of impact of birds colliding with the
breakwater during fog will be established.
Birds
Once before the
Monitoring program agreed (see above)
commencement of the
Annual monitoring report
construction works and
continued for 5 years following
the completion of the project
BAP –
MB3
Monitoring research on spring herring stocks coming to the bay for
spawning and research on the economically valuable freshwater
fish species and the flat fish (European flounder, turbot, zander,
common whitefish). This monitoring should be compared with
previous research (Domagała 2007, 2008; Dziewulska 2008, PileckaRapacz 2008; Pilecka-Rapacz, Sałacińska 2008; Pilecka-Rapacz et al.
2008).
Herring and
economically valuable
fish
Once before the
Monitoring program agreed (see above)
commencement of the
Annual monitoring report
construction works and
continued for 5 years following
the completion of the project
BAP –
MB4
Monitoring of the time and spatial variability,
including taxonomic composition, population size,
biomass and the observed water blooms of
phytoplankton, zooplankton and benthic organisms
(including organisms inhabiting the beach).
Phytoplankton,
zooplankton, benthos
and beach fauna and
flora
Once before the
Monitoring program agreed (see above)
commencement of the
Annual monitoring report
construction works and
continued for 5 years following
the completion of the project
BAP –
Monitor of the time and spatial variability of the physicochemical
Water column
Once before the
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
86
Monitoring program agreed (see above)
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Item
Monitoring (Breakwater)
MB5
parameters of the deep water (salinity, temperature, transparency,
suspended matter, biogenic compounds, organic matter).
commencement of the
Annual monitoring report
construction works and
continued for 5 years following
the completion of the project
BAP –
MB6
Monitoring of the time and spatial variability of the occurrence of
Marine mammals
mammals under Environmental Supervision should be undertaken.
Once before the
Monitoring program agreed (see above)
commencement of the
Annual monitoring report
construction works and
continued for 5 years following
the completion of the project
BAP –
MB7
Monitoring of the geomorphological and sedimentological changes
in the underwater zone situated to the east of the external
breakwater.
Benthic habitat
Once before the
Monitoring program agreed (see above)
commencement of the
Annual monitoring report
construction works and
continued for 5 years following
the completion of the project
BAP –
MB8
Carry out inspections of the condition of the systems for carrying
off and treatment of rainwater and surface runoffs.
Water column
Annual inspections during
construction and operation
Audit reports
BAP –
MB9
Perform checks on the bottom deposits in the site operated and
administered by the Maritime Office, i.e. in the fairway and the
turning basin.
Water column, seabed
and land
disposal/remediation
sites
Incorporated in regular
monitoring plan
Monitoring program agreed (see above)
BAP –
MB10
Monitoring of the soil-water environment if required by water
permits
Water column
as per water permits
as required by water permits
BAP –
MB11
Monitoring of the effectiveness of the measures applied to minimise All species and habitats
and restrict the impact of the project.
found in Table 7.1.
After one year from
commencement of operation
Evaluation report submitted no later
than 18 months from commencement of
operation
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
Targeted
Species/Habitat
Period
FINAL
87
Compliance/reporting mechanism
Bathymetric survey reports
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
8.2
JETTY
Table 8.2
Jetty Monitoring
Item
Monitoring (Jetty)
Targeted
Species/Habitat
Period
BAP –
MJ1
Monitoring of protected habitats and species within the designated
Natura 2000 sites.
Protected species,
habitats and Natura
2000 sites
Once before the
Monitoring program agreed (see above)
commencement of the
Annual monitoring report
construction works and
continued for 5 years
following the completion of
the project
BAP –
MJ2
Monitoring of the changes in the quantitative and qualitative status of
the birds and their habitats. Common methods such as counting along
a transect, counting over the sample plots at fixed points, observing
changes in the biology of the selected species should be used. The
magnitude of impact of birds colliding with the breakwater during fog
will be established.
Birds
Once before the
Monitoring program agreed (see above)
commencement of the
Annual monitoring report
construction works and
continued for 5 years
following the completion of
the project
BAP –
MJ3
Monitoring research on spring herring stocks coming to the bay for
spawning and research on the economically valuable freshwater fish
species and the flat fish (European flounder, turbot, zander, common
whitefish). This monitoring should be compared with previous
research (Domagała 2007, 2008; Dziewulska 2008, Pilecka-Rapacz 2008;
Pilecka-Rapacz, Sałacińska 2008; Pilecka-Rapacz et al. 2008).
Herring and
economically valuable
fish
Once before the
Monitoring program agreed (see above)
commencement of the
Annual monitoring report
construction works and
continued for 5 years
following the completion of
the project
BAP –
MJ4
Monitor of the time and spatial variability of the physicochemical
parameters of the deep water (salinity, temperature, transparency,
suspended matter, biogenic compounds, organic matter).
Water column
Once before the
Monitoring program agreed (see above)
commencement of the
Annual monitoring report
construction works and
continued for 5 years
following the completion of
the project
BAP –
MJ5
Monitoring of the time and spatial variability of the occurrence of
mammals under Environmental Supervision should be undertaken.
Marine mammals
Once before the
commencement of the
construction works and
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
88
Compliance/reporting mechanism
Monitoring program agreed (see above)
Annual monitoring report
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Item
Monitoring (Jetty)
Targeted
Species/Habitat
Period
Compliance/reporting mechanism
continued for 5 years
following the completion of
the project
BAP –
MJ6
Monitoring of the geomorphological and sedimentological changes in
the underwater zone situated to the east of the external breakwater.
BAP –
MJ7
At the berth pre-development stage water quality control examination Water column
should be carried out in the framework of the environment‟s protective
examination programme.
Procurement/ pre
development – baseline
monitoring
Monitoring program agreed (see above)
BAP –
MJ8
Sea water quality shall be monitored during project construction and
after completion thereof.
Procurement/ pre
development through to
operation for 6 years in
total
Monitoring program agreed (see above)
BAP –
MJ9
At the project procurement stage a programme of water quality control Water column
examination shall be implemented, covering the Świnoujście bathing
beach in particular.
Procurement/ pre
development through to
operation for 6 years in
total
Monitoring program agreed (see above)
BAP –
MJ10
After project completion noise should be measured that is emitted to
the environment at LNG unloading operation.
Birds, bats and other
species affected by
noise
During operation
Monitoring program agreed (see above)
Monitoring report
BAP –
MJ11
Monitoring of the soil-water environment
Water column
During operation
Monitoring program agreed (see above)
Evaluation report
BAP –
MJ12
Monitoring of the effectiveness of the measures applied to minimise
and restrict the impact of the Project.
All species and
habitats found in
Table 7.2.
During operation
Monitoring program agreed (see above)
Evaluation report
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
Benthic habitat
Once before the
Monitoring program agreed (see above)
commencement of the
Annual monitoring report
construction works and
continued for 5 years
following the completion of
the project
Water column
FINAL
89
Monitoring report
Annual monitoring report (6yrs)
Annual monitoring report (6yrs)
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Item
Monitoring (Jetty)
Targeted
Species/Habitat
Period
Compliance/reporting mechanism
BAP –
MJ13
Monitoring of beach and sand dune vegetation and fauna
- the organic matter
Pre-construction /
Monitoring program agreed (see above)
deposited on the beach construction and operation Monitoring report
(kidzina),
(5 yrs.) as specified in the
the Decision on
- the population of
Environmental Conditions
elymus farctus,
- the population of
talitrus saltator
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
90
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
8.3
LNG TERMINAL
Table 8.3
LNG Terminal
Item
Monitoring (Terminal)
Targeted
Species/Habitat
Period
Compliance/reporting mechanism
BAP –
MT1
Monitoring of the project site and the environment of the beach and
dunes, and the adjacent areas within the distance of approx. 100 m
from the boundaries of the project site, whereby the southern boundary
of the site is formed by the existing railway line in order to assess the
impact of the project on the natural environment, and to prevent
adverse changes to this environment, it is necessary to perform.
All habitats within the
project site as well as
beach and dunes and
adjacent areas.
Once before the
commencement of the
construction works and
continued for 5 years
following the completion
of the project.
Monitoring program agreed
BAP –
MT2
Monitoring should cover the impact of the project on natural habitats
and on the protected plant and animal species, within both the
designated Natura 2000 sites and the habitats of protected plant,
animal and fungi species, i.e. it shall include the selected plant and
animal species, their habitats as well as conditions for habitat
preservation.
Protected plant,
animal and fungi
species, habitats and
Natura 2000 sites
Once before the
commencement of the
construction works and
continued for 5 years
following the completion
of the project.
Environmental Supervision reports
BAP –
MT3
Monitoring of avifauna- it is necessary to carry out field observations
and to keep checks on the mortality rate of birds colliding with the
planned high structures.
Birds
Once before the
commencement of the
construction works and
continued for 5 years
following the completion
of the project.
Environmental Supervision reports
BAP –
MT4
Monitoring the dune slacks adjacent to the project site on the eastern
side, which should cover the groundwater level and the condition of
habitats; as part of the measure, before the commencement of the
works the pipezometers monitoring system will be installed and some
of observational wells will be located nearby the dune slacks outside
the project site, and to designate areas to be permanently monitored.
Habitats- dunes
Once before the
commencement of the
construction works and
continued for 5 years
following the completion
of the project.
Environmental Supervision reports
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
FINAL
91
Environmental Supervision reports
Annual monitoring reports (5 yrs)
Annual monitoring reports (5 yrs)
Annual monitoring reports (5 yrs)
Annual monitoring reports (5 yrs)
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
8.4
PIPELINE
Table 8.4
Monitoring - Pipeline
Item
Monitoring (Pipeline)
Targeted
Species/Habitat
Period
Compliance/reporting mechanism
BAP –
MP1
In the course of the drainage works, specify a number of metering
points (including trees) to be monitored throughout the entire time of
drainage works performance.
Trees and habitats
During excavation
(trenching) works
Environmental Supervision reports
All species and
habitats, particularly
species of protected
plants, fungi and
animals and habitats
Once before the
commencement of the
construction works, and
continued for five years
after the completion of the
investment
The results and conclusions from the
monitoring will be presented to the
Regional Chief Officer for Environmental
Protection by the end of the first quarter of
the calendar year following the
commencement of the construction works.
If any deviations from normal conditions (drying of trees etc) are
identified during the drainage works, the drainage works should be
stopped and then, within the scope of the investor‟s supervision and
nature conservation supervision, a decision should be taken regarding
any possible changes in further works relating to the drainage of
trenches,
BAP –
MP2
The monitoring should take into account the impact of the investment
on the condition and behaviour of nature habitats and habitats of
plants and animals protected within the Natura 2000 network and also
rare, threatened and protected plant, animal and fungi sites as well as
other areas with high natural value specified as a result of the
assessment of the relative importance of nature sites in communes and
shown in nature sites stocktaking carried out for the purposes of the
investment. The scope of the monitoring must be agreed by the
Regional Chief Officer for Environmental Protection in Szczecin, who
may, based on the monitoring results, decide to apply other mitigation
measures.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
Monitoring Reports delivered by GazSystem to RDOS
Monitoring Plan submitted to RDOS and
approved
FINAL
92
OCTOBER 2010
BIODIVERSITY ACTION PLAN
Annex A
Natura 2000 Species List
ANNEX A NATURA 2000 SPECIES LISTS
Explanatory note for the Species lists
The following is a brief explanation of the codes used in Tables A.1-A.10 for
each of the categories listed in the table under Site Assessment.
Population - Size and density of the population of the species present on the
site in relation to the populations present within national territory. The
optimal measure would be a percentage, resulting from the ratio of the
population in the site / population in the national territory.
A: 100% >= p > 15%
B: 15% >= p > 2%
C: 2% >= p > 0%
D: non-significant population
Conservation - Degree of conservation of the features of the habitat which are
important for the species concerned and possibilities for restoration.
A. conservation excellent: defined as elements in an excellent condition,
independent of the grading of the possibility of restoration
B: good conservation defined as elements well conserved independent of the
grading of the possibility of restoration OR elements in average or partially
degraded condition and restoration easy.
C: average or reduced conservation defined as all other combinations
Isolation - Degree of isolation of the population present on the site in relation
to the natural range of the species.
A: population (almost) isolated
B: population not-isolated, but on margins of area of distribution
C: population not-isolated within extended distribution range
Global - Global assessment of the value of the site for conservation of the
species concerned.
A : excellent value
B : good value
C : significant value
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
ANNEXES
1
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Table 8.5
PLH 320019 Species
Code
Name
Common name
Population
Site Assessment
Population
Birds Listed on Annex I of Council directive 79/409/EEC
A294
Acrocephalus paludicola
Aquatic warbler
A089
Aquila pomarina
Lesser Spotted Eagle
A222
Asio flammeus
Short-eared Owl
B, S
S
S
D
D
D
A060
A021
A215
A138
A197
A031
A030
A080
A081
A082
A084
A122
Ferruginous Duck
Great Bittern
Eurasian Eagle-owl
Kentish Plover
Black Tern
White Stork
Black Stork
Short-toed Snake-eagle
Western Marsh-harrier
Northern Harrier
Montagu‟s Harrier
Corncrake
S
B
B
S
S
B, S
B, S
S
B
S
B
B
D
D
D
D
D
D
D
D
D
D
D
D
A037
A038
A238
A236
A379
A103
Aythya nyroca
Botaurus stellaris
Bubo bubo
Charadrius alexandrinus
Chlidonias niger
Ciconia ciconia
Ciconia nigra
Circaetus gallicus
Circus aeruginosus
Circus cyaneus
Circus pygargus
Crex crex
Cygnus bewickii (Cygnus
columbianus bewickii)
Cygnus cygnus
Dendrocopos medius
Dryocopus martius
Emberiza hortulana
Falco peregrinus
Bewick‟s Swan
Whooper Swan
Middle Spotted Woodpecker
Black Woodpecker
Ortolan Bunting
Peregrine Falcon
S
S
B
B, S
S
S
D
D
D
D
D
D
A320
A154
A002
A001
A127
Ficedula parva
Gallinago media
Gavia arctica
Gavia stellata
Grus grus
Red-breasted Flycatcher
Great Snipe
Arctic Loon
Red-throated Loon
Common Crane
S
S
S
S
B
D
D
D
D
D
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
ANNEXES
2
Conservation
Isolation
Global
IUCN Status
Vulnerable
Least Concern
Least Concern
Near
Threatened
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Not listed
Not listed
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Near
Threatened
Least Concern
Least Concern
Least Concern
Least Concern
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Code
Name
Common name
Population
Site Assessment
Population
A075
Haliaeetus albicilla
White-tailed Eagle
B
A190
Hydroprogne caspia
Caspian Tern
S
Α022
Ixobrychus minutus
Little Bittern
B
A339
Lanius collurio
Red-backed Shrike
B
A176
Larus melanocephalus
Mediterranean Gull
B, S
A177
Larus minutus
Little Gull
S
A157
Limosa lapponica
Bar-tailed Godwit
S
A272
Luscinia svecica
Bluethroat
B, S
A068
Mergus albellus (Mergellus albellus) Smew
W, S
A073
Milvus migrans
Black Kite
B
A074
Milvus milvus
Red Kite
B
A023
Nycticorax nycticorax
Black-crowned Night-heron
S
A094
Pandion haliaetus
Osprey
S
A019
Pelecanus onocrotalus
Great White Pelican
S
A072
Pernis apivorus
European Honey-buzzard
B, S
A170
Phalaropus lobatus
Red-necked Phalarope
S
A151
Philomachus pugnax
Ruff
S
A140
Pluvialis apricaria
Eurasian Golden Plower
S
A007
Podiceps auritus
Horned Grebe
S
A119
Porzana porzana
Spotted Crake
B
A191
Sandwich Tern
S
Sterna sandvicensis
A195
Sternula albifrons
Little Tern
B, S
A307
Barred Warbler
B
Sylvia nisoria
A166
Tringa glareola
Wood Sandpiper
S
Regularly occurring Migratory Birds not listed on Annex I of Council directive 79/409/EEC
A054
Anas acuta
Northern Pintail
B
A051
Anas crecca
Common Teal
B, S
A050
Anas penelope
Eurasian Wigeon
B
A055
Anas querquedula
Garganey
B
A043
Anser anser
Greylag Goose
B, W, S
A059
Aythya ferina
Common Pochard
B, S
A061
Aythya fuligula
Tufted Duck
B, S
A067
Bucephala clangula
Common Goldeneye
B, S
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
ANNEXES
3
Conservation
Isolation
Global
IUCN Status
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
D
D
D
D
D
D
D
D
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Code
Name
Common name
Population
Site Assessment
Population
Conservation
Isolation
Global
IUCN Status
A064
Clangula hyemalis
Long-tailed Duck
A130
Haematopus ostralegus
Eurasian Oystercatcher
A065
Melanitta nigra
Black Scoter
A070
Mergus merganser
Common Merganser
A069
Mergus serrator
Red-breasted Merganser
A063
Somateria mollissima
Common Eider
A048
Tadorna tadorna
Common Shelduck
Mammals listed on Annex II of Council directive 92/43/EEC
2647
Bison bonasus
European Bison
1337
Castor fiber
Eurasian Beaver
1364
Halichoerus grypus
Grey Seal
W, S
B
W, S
B, W
W, S
W, S
B, S
D
D
D
D
D
D
D
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
R
R
S
D
D
D
1355
Lutra lutra
Eurasian Otter
1324
Myotis myotis
Greater Mouse-eared Bat
1351
Phocoena phocoena
Harbour Porpoise
Amphibians and Reptiles listed on Annex II of Council directive 92/43/EEC
1188
Bombina bombina
Fire-bellied Toad
1166
Triturus cristatus
Northern Crested Newt
Fishes listed on Annex II of Council directive 92/43/EEC
1103
Alosa fallax
Twaite Shad
2522
Pelecus cultratus
Ziege
1095
Petromyzon marinus
Sea Lamprey
Invertebrates listed on Annex II of Council directive 92/43/EEC
1088
Cerambyx cerdo
Greater Capricorn Beetle
1083
Stag Beetle
Lucanus cervus
R
R
S
C
C
D
A
B
C
C
B
C
Vulnerable
Least Concern
Least Concern
Near
Threatened
Least Concern
Least Concern
R
R
C
C
B
B
C
C
C
C
Least Concern
Least Concern
R
R
R
B
D
C
B
C
B
B
C
C
Least Concern
Least Concern
Least Concern
R
R
C
D
B
A
C
1084
R
C
B
C
B
Osmoderma eremita
Hermit Beetle
Vulnerable
Not listed
Near
Threatened
Population: W – wintering, S – staging, B – breeding, R – resident
Site Assessment: See explanatory note at beginning of Annex A.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
ANNEXES
4
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Table 8.6
PLH990002 Species
Code
Name
Common Name
Population
Population
Birds listed on
Annex I
A002
A001
A068
Gavia arctica
Black throated diver
Gavia stellata
Red throated diver
Mergus albellus (Mergellus
Smew
albellus)
Podiceps auritus
A007
Horned Grebe
Regularly occurring Migratory Birds not listed on Annex I
Cepphus grylle
A202
Black guillemot
Clangula hyemalis
A064
Long tailed duck
Melanitta fusca
A066
Velvet scoter
Melanitta nigra
A065
Common scoter
Mergus serrator
A069
Red-breasted Merganser
Podiceps cristatus
A005
Great crested grebe
Podiceps grisegena
A006
Red-necked grebe
A989
Waterfowl
Mammals listed on Annex II
Phocoena phocoena
1351
Harbour porpoise
Fishes listed on
Annex II
Alosa fallax
1103
Twaite shad
Site Assessment
Conservation Isolation
Global
IUCN Status
W
W
W
D
D
D
Least Concern
Least Concern
Least Concern
W
D
Least Concern
W
W
W
W
W, S
W
W
W, S
D
D
D
D
D
D
D
D
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
R
B
B
B
B
Least Concern
R
C
C
C
C
Least Concern
Population: W – wintering, S – staging, B – breeding, R – resident
Site Assessment: See explanatory note at beginning of Annex A.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
ANNEXES
5
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Table 8.7
PLB990003 Species
Code
Name
Common name
Birds listed on Annex I
A002
Gavia arctica
Black throated diver
A001
Gavia stellata
Red throated diver
Mergus albellus
Smew
(Mergellus
A068
albellus)
A007
Podiceps auritus
Horned Grebe
Regularly occurring Migratory Birds not listed on Annex I
A202
Cepphus grylle
Black guillemot
A064
Clangula hyemalis Long tailed duck
A066
Melanitta fusca
Velvet scoter
A065
Melanitta nigra
Common scoter
A069
Mergus serrator
Red-breasted Merganser
A005
Podiceps cristatus Great crested grebe
A006
Podiceps grisegena Red-necked grebe
A989
waterfowl
Population
W
W
W
Population
Site Assessment
Conservation Isolation Global
D
D
IUCN Status
Least Concern
Least Concern
W
C
C
B
B
C
C
C
C
Least Concern
Least Concern
W
W
W
W
W, S
W
W
W, S
B
A
B
A
C
C
A
D
B
C
C
B
C
C
C
C
C
C
C
C
C
C
B
A
B
A
C
C
A
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Population: W – wintering, S – staging, B – breeding, R – resident
Site Assessment: See explanatory note at beginning of Annex A.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
ANNEXES
6
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Table 8.8
PLB 320002 Species
Site Assessment
Code
Name
Common name
Birds listed on Annex I of Council directive 79/409/EEC
A294
Acrocephalus paludicola
Aquatic warbler
A229
Alcedo atthis
Common Kingfisher
A222
Asio flammeus
Short-eared Owl
A021
Botaurus stellaris
Great Bittern
A045
Branta leucopsis
Barnacle Goose
A215
Bubo bubo
Eurasian Eagle-owl
A466
Calidris alpina schinzii
Dunlin
A224
Caprimulgus europaeus
Eurasian Nightjar
Western MarshA081
Circus aeruginosus
harrier
A082
Circus cyaneus
Northern Harrier
A084
Circus pygargus
Montagu‟s Harrier
A122
Crex crex
Corncrake
A038
Cygnus cygnus
Whooper Swan
Middle Spotted
A238
Dendrocopos medius
Woodpecker
A236
Dryocopus martius
Black Woodpecker
A027
Egretta alba (Ardea alba)
Great Egret
A098
Falco columbarius
Merlin
A103
Falco peregrinus
Peregrine Falcon
A320
Ficedula parva
Flycatcher
A002
Arctic Loon
Gavia arctica
A001
Gavia stellata
Red-throated Loon
A127
Grus grus
Common Crane
A075
Haliaeetus albicilla
White-tailed Eagle
A190
Hydroprogne caspia
Caspian Tern
Α022
Ixobrychus minutus
Little Bittern
A339
Lanius collurio
Red-backed Shrike
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
Population
Population Conservation Isolation Global
B
B
B
B
S
B
B, S
B
B
C
D
C
D
D
C
D
B
B
B
C
B
C
B
C
C
B
C
C
B
B
B
B
S
C
C
D
D
C
B
B
C
B
C
C
B
C
C
B
B
B, S
S
S
B
W
W
B
B, W
S
B
B
D
D
D
D
D
D
C
C
D
C
D
D
C
ANNEXES
7
B
B
B
B
B
B
B
C
C
B
C
C
IUCN Status
Vulnerable
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Near Threatened
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Site Assessment
Code
Name
Common name
Population
A177
A246
A272
Larus minutus
Lullula arborea
Luscinia svecica
Mergus albellus (Mergellus
albellus)
Milvus milvus
Little Gull
Wood Lark
Bluethroat
S
B
B
A068
A074
Smew
W
Black Kite
B
European HoneyA072
Pernis apivorus
buzzard
B
A151
Philomachus pugnax
Ruff
B, S
A034
Platalea leucorodia
Eurasian Spoonbill
S
Eurasian Golden
A140
Pluvialis apricaria
Plover
S
A007
Podiceps auritus
Horned Grebe
W
A119
Porzana porzana
Spotted Crake
B
A307
Sylvia nisoria
Barred Warbler
B
A166
Tringa glareola
Wood Sandpiper
S
Regularly occurring Migratory Birds not listed on Annex I of Council directive 79/409/EEC
A051
Anas strepera
Gadwall
A043
Anser anser
Greylag Goose
A039
Anser fabalis
Bean Goose
A059
Aythya ferina
Common Pochard
A070
Mergus merganser
Common Merganser
Red-breasted
A069
Mergus serrator
Merganser
Population Conservation Isolation Global
IUCN Status
B
D
D
B
C
C
Least Concern
Least Concern
Least Concern
C
C
B
B
B
C
B
C
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
D
C
D
B
C
C
B
B
B
B
C
C
C
C
C
C
C
B
B
B
B
B
C
C
C
C
C
C
C
C
C
C
Least Concern
Least Concern
Least Concern
Least concern
Least Concern
B
B
B
B
Least Concern
D
C
D
C
D
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Population: W – wintering, S – staging, B – breeding, R – resident
Site Assessment: See explanatory note at beginning of Annex A.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
ANNEXES
8
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Table 8.9
PLB 320009 Species
Code
Name
Common Name
Birds listed on Annex I of Council directive 79/409/EC
A294
Acrocephalus paludicola
Aquatic warbler
A229
Alcedo atthis
Common Kingfisher
A021
Botaurus stellaris
Great Bittern
A466
Calidris alpina schinzii
Dunlin
A197
Chlidonias niger
Black Tern
A031
Ciconia ciconia
White Stork
Western MarshA081
Circus aeruginosus
harrier
A082
Circus cyaneus
Northern Harrier
A122
Corncrake
Crex crex
A038
Cygnus cygnus
Whooper Swan
Middle Spotted
A238
Dendrocopos medius
Woodpecker
A236
Dryocopus martius
Black Woodpecker
A098
Falco columbarius
Merlin
A103
Falco peregrinus
Peregrine Falcon
RedA320
Ficedula parva
breasted Flycatcher
A127
Grus grus
Common Crane
A075
Haliaeetus albicilla
White-tailed Eagle
A339
Lanius collurio
Red-backed Shrike
A246
Lullula arborea
Wood Lark
Mergus albellus (Mergellus
A068
albellus)
Smew
A073
Milvus migrans
Black Kite
A074
Milvus milvus
Red Kite
A034
Platalea leucorodia
European Spoonbill
Eurasian Golden
A140
Pluvialis apricaria
Plower
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
Site Assessment
ConservatPopulation
Isolation Global
Population
ion
IUCN Status
B
B
B
B
S
B
C
C
C
C
B
D
B
B
B
B
B
B
C
C
C
C
C
C
C
C
B
Vulnerable
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
B
B
B
W, S
C
C
C
B
B
B
B
B
C
B
C
C
C
C
C
B
Least Concern
Least Concern
Least Concern
Least Concern
B
B
S
S
D
D
D
D
B
B
B, W
B
B
D
C
B
C
D
W
B
B
S
S
ANNEXES
9
Least Concern
Least Concern
Least Concern
Least Concern
Near Threatened
Least Concern
Least Concern
Least Concern
Least Concern
B
B
B
C
C
C
C
B
C
A
C
C
D
B
B
B
C
C
C
A
C
C
Least Concern
Least Concern
Least Concern
Least Concern
B
C
C
B
Least Concern
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Site Assessment
IUCN Status
ConservatPopulation
Isolation Global
Common Name
Population
ion
A119
Porzana porzana
Spotted Crake
B
C
B
C
C
Least Concern
A307
Sylvia nisoria
Barred Warbler
B
C
B
C
C
Least Concern
Regularly occurring Migratory Birds not listed on Annex I of Council directive 79/409/EEC
A050
Anas penelope
Eurasian Wigeon
S
D
Least Concern
A043
Anser anser
Greylag Goose
B
C
B
C
C
Least Concern
A039
Anser fabalis
Bean Goose
W, S
D
Least Concern
A059
Aythya ferina
Common Pochard
S
C
B
C
C
Least Concern
A061
Aythya fuligula
Tufted Duck
B, S
B
B
C
B
Least Concern
A062
Aythya marila
Greater Scaup
W, S
A
B
C
A
Least Concern
A067
Bucephala clangula
Common Goldeneye W, S
B
B
C
B
Least Concern
A136
Charadrius dubius
Little Ringed Plover
B
D
Least Concern
Common Ringed
A137
Charadrius hiaticula
Plover
B
C
B
C
C
Least Concern
A125
Common Coot
B, S
C
B
C
C
Least Concern
Fulica atra
A065
Melanitta nigra
Black Scoter
W
C
B
C
C
Least Concern
A070
Mergus merganser
Common Merganser
W, S
A
B
C
A
Least concern
A391
Phalacrocorax carbo sinensis
Great Cormorant
S
C
B
C
C
Not listed
A005
Podiceps cristatus
Great Crested Grebe
B, S
C
B
C
C
Least Concern
A048
Tadorna tadorna
Common Shelduck
B
B
B
B
B
Least Concern
Code
Name
Population: W – wintering, S – staging, B – breeding, R – resident
Site Assessment: See explanatory note at beginning of Annex A.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
ANNEXES
10
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Table 8.10
PLH 320018 Species
Code
Name
Common
Name
Birds listed on Annex I of Council directive 79/409/EEC
Aquatic
A294
warbler
Acrocephalus paludicola
A229
Alcedo atthis
Lesser
A089
Aquila pomarina
Spotted Eagle
A021
Botaurus stellaris
Great Bittern
A197
Chlidonias niger
Black Tern
A030
Ciconia nigra
Black Stork
Short-ties
A080
Circaetus gallicus
Snake-eagle
Western
A081
Circus aeruginosus
Marsh-harrier
Northern
A082
Circus cyaneus
Harrier
A122
Crex crex
Corncrake
Middle
Spotted
A238
Dendrocopos medius
Woodpecker
Black
A236
Dryocopus martius
Woodpecker
A027
Egretta alba (Ardea alba)
Great Egret
A098
Falco columbarius
Merlin
Peregrine
A103
Falco peregrinus
Falcon
Red-breasted
A320
Ficedula parva
Flycatcher
Common
A127
Grus grus
Crane
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
Site Assessment
Population
Population Conservation Isolation Global
IUCN Status
B
B
D
D
Vulnerable
B
B
S
B
D
D
D
D
Least Concern
Least Concern
Least Concern
Least Concern
S
D
Least Concern
B
D
Least Concern
B
B
D
D
Least Concern
Not listed
B
D
Least Concern
B
S
S
D
D
D
Least Concern
Least Concern
Least Concern
S
D
Least Concern
B
D
Near Threatened
B, S
D
Least Concern
ANNEXES
11
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Code
Name
A075
Α022
Haliaeetus albicilla
Ixobrychus minutus
A339
A177
A246
A272
Lanius collurio
Larus minutus
Lullula arborea
Luscinia svecica
Mergus albellus (Mergellus
albellus)
Milvus migrans
Milvus milvus
A068
A073
A074
Common
Name
White-tailed
Eagle
Little Bittern
Red-backed
Shrike
Little Gull
Wood Lark
Bluethroat
Site Assessment
Population
Population Conservation Isolation Global
B, S
B
D
D
Least Concern
Least Concern
B
B
B
B
D
D
D
D
Least Concern
Least Concern
Least Concern
Least Concern
Smew
S
D
Black Kite
B
D
Red Kite
B
D
European
HoneyA072
Pernis apivorus
buzzard
S
D
Eurasian
A034
Platalea leucorodia
Spoonbill
S
D
Eurasian
Golden
A140
Pluvialis apricaria
Plower
S
D
Spotted
A119
Crake
B
D
Porzana porzana
Common
A193
Tern
B
D
Sterna hirundo
Barred
A307
Sylvia nisoria
Warbler
B
D
Regularly occurring Migratory Birds not listed on Annex I of Council directive 79/409/EEC
Northern
A056
Anas clypeata
Shoveler
S
D
Common
A051
Anas crecca
Teal
B
D
Eurasian
A050
Anas penelope
Wigeon
S
D
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
IUCN Status
ANNEXES
12
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Code
Name
A053
A055
A051
Anas platyrhynchos
Anas querquedula
Anas strepera
A043
Anser anser
A059
A061
Aythya ferina
Aythya fuligula
A062
Aythya marila
A067
Bucephala clangula
A136
Charadrius dubius
A137
A036
Charadrius hiaticula
Cygnus olor
A153
A065
Gallinago gallinago
Melanitta nigra
A070
Mergus merganser
A005
Podiceps cristatus
A276
Scolopax rusticola
A063
A004
Somateria mollissima
Tachybaptus ruficollis
A048
A165
Tadorna tadorna
Tringa ochropus
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
Common
Name
Mallard
Garganey
Gadwall
Greylag
Goose
Common
Pochard
Tufted Duck
Greater
Scaup
Common
Goldeneye
Little Ringed
Plover
Common
Ringed Plover
Mute Swan
Common
Snipe
Black Scoter
Common
Merganser
Great
Crested Grebe
Eurasian
Woodcock
Common
Eider
Little Grebe
Common
Shelduck
Green
Site Assessment
Population
Population Conservation Isolation Global
IUCN Status
B
B
B
D
D
D
Least Concern
Least Concern
Least Concern
B
D
Least Concern
B, S
B, S
D
D
Least Concern
Least Concern
S
D
Least Concern
B, S
D
Least Concern
B
D
Least Concern
B
B
D
D
Least Concern
Least Concern
B
S
D
D
Least Concern
Least Concern
S
D
Least Concern
S
D
Least Concern
B
D
Least Concern
S
B
D
D
Least Concern
Least Concern
S
S
D
D
Least Concern
Least Concern
ANNEXES
13
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Code
Name
Common
Name
Site Assessment
Population
Sandpiper
Mammals listed on Annex II of Council directive 92/43/EEC
Western
1308
Barbastella barbastellus
Barbastelle
B
Eurasian
1337
Castor fiber
Beaver
R
Eurasian
1355
Lutra lutra
Otter
R
1324
Myotis myotis
Bat
B
Amphibians and Reptiles listed on Annex II of Council directive 92/43/EEC
Fire-bellied
1188
Bombina bombina
Toad
R
Northern
1166
Triturus cristatus
Crested Newt R
Fishes listed on Annex II of Council directive 92/43/EEC
1103
Alosa fallax
Twaite Shad B, S
1130
Aspius aspius
Asp
R
River
1099
Lamprey
S
Lampetra fluviatilis
2522
Pelecus cultratus
Ziege
R
Atlantic
1106
Salmo salar
Salmon
S
Invertebrates listed on Annex II of Council directive 92/43/EEC
Thick Shelled
1032
Unio crassus
River Mussel R
Population Conservation Isolation Global
IUCN Status
D
Near Threatened
D
Least Concern
D
D
Near Threatened
Least Concern
D
Least Concern
D
Least Concern
B
C
B
B
C
C
B
C
Least Concern
Least Concern
C
B
B
A
C
C
C
C
Least Concern
Low Risk/Least Concern
D
Lower Risk/Least Concern
D
Lower Risk/Near Threatened
Population: W – wintering, S – staging, B – breeding, R – resident
Site Assessment: See explanatory note at beginning of Annex A.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
ANNEXES
14
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Table 8.11
PLH 320033 Species
Site Assessment
CODE
NAME
Common name
Birds listed on Annex I of Council directive 79/409/EEC
A089
Aquila pomarina
Lesser Spotted Eagle
A222
Asio flammeus
Short-eared Owl
A021
Botaurus stellaris
Great Bittern
A215
Bubo bubo
Eurasian Eagle-owl
A224
Caprimulgus europaeus
Eurasian Nightjar
A031
Ciconia ciconia
White Stork
A030
Ciconia nigra
Black Stork
Western MarshA081
Harrier
Circus aeruginosus
A082
Circus cyaneus
Northern Harrier
A084
Montagu‟s Harrier
Circus pygargus
A122
Crex crex
Corncrake
A038
Cygnus cygnus
Whooper Swan
Middle Spotted
A238
Dendrocopos medius
Woodpecker
A236
Dryocopus martius
Black Woodpecker
Red-breasted
A320
Ficedula parva
Flycatcher
A127
Grus grus
Common Crane
A075
Haliaeetus albicilla
White-tailed Eagle
A339
Lanius collurio
Red-backed Shrike
A246
Lullula arborea
Woodlark
A272
Luscinia svecica
Bluethroat
A073
Milvus migrans
Black Kite
A074
Milvus milvus
Red Kite
European HoneyA072
Pernis apivorus
buzzard
A120
Porzana parva
Little Crake
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
IUCN Status
Population
Population Conservation Isolation Global
B
R
R
B
B
R
B
D
D
D
D
D
D
D
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
B
B
B
B
S
D
D
D
D
D
Least Concern
Least Concern
Least Concern
Not listed
Least Concern
B
B
D
D
Least Concern
Least Concern
B
B
R
B
B
R
B
B, S
D
D
D
D
D
D
D
D
Near Threatened
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
B
B
D
D
Least Concern
Least Concern
ANNEXES
15
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Site Assessment
CODE
NAME
Common name
Population
Population Conservation Isolation Global
A119
Porzana porzana
Spotted Crake
B
D
A307
Sylvia nisoria
Barred Warbler
B
D
A107
Tetrao tetrix tetrix
Black Grouse
B
D
Regularly occurring Migratory Birds not listed on Annex I of Council directive 79/409/EEC
A051
Anas strepera
Gadwall
B
D
A059
Aythya ferina
Common Pochard
B
D
A061
Aythya fuligula
Tufted Duck
B
D
A067
Bucephala clangula
Common Goldeneye B
D
A136
Charadrius dubius
Little Ringed Plover B
D
Common Ringed
A137
Charadrius hiaticula
Plover
B
D
Eurasian Green
A235
Woodpecker
R
D
Picus viridis
A276
Scolopax rusticola
Eurasian Woodcock B
D
A165
Green Sandpiper
B
D
Tringa ochropus
Mammals listed on Annex II of Council directive 92/43/EEC
1337
Castor fiber
Eurasian Beaver
R
D
Amphibians and Reptiles listed on Annex II of Council directive 92/43/EEC
Northern-Crested
1166
Triturus cristatus
Newt
R
D
IUCN Status
Least Concern
Least Concern
Not listed
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Population: W – wintering, S – staging, B – breeding, R – resident
Site Assessment: See explanatory note at beginning of Annex A.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
ANNEXES
16
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Table 8.12
PLB 320007 Species
Site Assessment
Code
Name
Common name
Population
Population
Conservation
Isolation
Global
Birds listed on Annex I of Council directive 79/409/EEC
A294
Acrocephalus paludicola Aquatic warbler
A229
Alcedo atthis
Common Kingfisher
A089
Aquila pomarina
Lesser Spotted Eagle
A021
Botaurus stellaris
Great Bittern
A045
Branta leucopsis
Barnacle Goose
A224
Caprimulgus europaeus Eurasian Nightjar
A197
Chlidonias niger
Black Tern
A031
Ciconia ciconia
White Stork
A030
Black Stork
Ciconia nigra
B
B
B
B
S
B
B
B
S
C
C
C
C
D
D
C
D
D
B
B
B
B
B
C
C
C
C
C
C
C
B
C
C
A081
A082
A084
A122
A038
B
B
B
B
S
C
C
C
C
D
B
B
B
B
C
B
C
C
C
C
C
C
B
B
S
S
S
B
B
B
B
B
B
B
D
D
D
D
D
D
C
C
C
C
C
C
A238
A236
A027
A098
A103
A320
A127
A075
Α022
A339
A246
A073
Circus aeruginosus
Circus cyaneus
Circus pygargus
Crex crex
Cygnus cygnus
Western Marsh-harrier
Northern Harrier
Motagu‟s Harrier
Corncrake
Whooper Swan
Middle Spotted
Dendrocopos medius
Woodpecker
Dryocopus martius
Black Woodpecker
Egretta alba (Ardea alba) Great Egret
Falco columbarius
Merlin
Falco peregrinus
Peregrine Falcon
Ficedula parva
Red-breasted Flycatcher
Common Crane
Grus grus
Haliaeetus albicilla
White-tailed Eagle
Little Bittern
Ixobrychus minutus
Lanius collurio
Red-backed Shrike
Lullula arborea
Woodlark
Milvus migrans
Black Kite
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
ANNEXES
17
B
B
B
B
B
B
C
C
C
C
C
C
C
C
C
C
C
C
IUCN Status
Vulnerable
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Not listed
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Near Threatened
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Site Assessment
Code
Name
Common name
Population
A074
Milvus milvus
A072
A151
A120
A119
A307
A166
Pernis apivorus
Philomachus pugnax
Porzana parva
Porzana porzana
Sylvia nisoria
Tringa glareola
Red Kite
European Honeybuzzard
Ruff
Little Crake
Spotted Crake
Barred Warbler
Wood Sandpiper
IUCN Status
Population
Conservation
Isolation
Global
B
C
B
C
C
Least Concern
B, S
S
B
B
B
S
C
D
C
C
C
D
B
C
C
B
B
B
C
C
C
C
C
C
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Population: W – wintering, S – staging, B – breeding, R – resident
Site Assessment: See explanatory note at beginning of Annex A.
Table 8.13
PLB 320011 Species
Site Assessment
Code
Name
Common Name
Birds listed on Annex I of Council directive 79/409/EEC
A229
Alcedo atthis
Common Kingfisher
A197
Chlidonias niger
Black Tern
A031
Ciconia ciconia
White Stork
A081
Circus aeruginosus
Western Marsh-harrier
A082
Circus cyaneus
Northern Harrier
A084
Circus pygargus
Montagu‟s Harrier
A122
Crex crex
Corncrake
Cygnus bewickii (Cygnus
A037
columbianus bewickii)
Bewick‟s Swan
A038
Cygnus cygnus
Whooper Swan
A236
Dryocopus martius
Black Woodpecker
A098
Falco columbarius
Merlin
A103
Falco peregrinus
Peregrine Falcon
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
Population
Population Conservation Isolation Global
B
B
B
B
B
B
B
C
D
D
C
C
C
C
S
S
B
S
S
D
C
D
D
D
ANNEXES
18
B
C
C
B
B
B
B
C
B
C
C
C
C
C
C
B
C
C
IUCN Status
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Not listed
Not listed
Least Concern
Least Concern
Least Concern
Least Concern
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Site Assessment
Code
Name
Common Name
Population
A127
A075
A339
A246
Grus grus
Common Crane
B
Haliaeetus albicilla
White-tailed Eagle
B, W
Lanius collurio
Red-backed Shrike
B
Lullula arborea
Wood Lark
B
Mergus albellus (Mergellus
A068
albellus)
Smew
W
A073
Milvus migrans
Black Kite
B
A074
Milvus milvus
Red Kite
B
A072
Pernis apivorus
European Honey-buzzard B
A140
Pluvialis apricaria
Eurasian Golden Plower
S
A119
Porzana porzana
Spotted Crake
B
A193
Sterna hirundo
Common Tern
B
A307
Sylvia nisoria
Barred Warbler
B
A166
Tringa glareola
Wood Sandpiper
S
Regularly occurring Migratory Birds not listed on Annex I of Council directive 79/409/EEC
A056
Anas clypeata
Northern Shoveler
B
A051
Anas strepera
Gadwall
B
A043
Anser anser
Greylag Goose
S
A039
Bean Goose
S
Anser fabalis
A993
Been&White-fronted geese
S
A067
Common Goldeneye
B, S
Bucephala clangula
A149
Calidris alpina
Dunlin
B
A070
Mergus merganser
Common Merganser
W
A005
Podiceps cristatus
Great Crested Grebe
B
A048
Tadorna tadorna
Common Shelduck
B
A162
Tringa totanus
Common Redshank
B
Population Conservation Isolation Global
D
C
C
D
B
B
C
C
C
C
C
D
C
D
D
C
D
C
D
C
C
C
B
C
C
B
C
C
B
C
C
C
C
C
C
C
C
D
C
C
B
C
B
B
B
C
B
B
C
C
C
C
C
C
C
C
C
C
C
C
B
B
B
B
C
C
C
C
C
C
B
C
IUCN Status
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Not listed
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Population: W – wintering, S – staging, B – breeding, R – resident
Site Assessment: See explanatory note at beginning of Annex A.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
ANNEXES
19
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Table 8.14
PLB 320012 Species
Site Assessment
Code
Name
Common name
Population
IUCN Status
Population
Conservation Isolation Global
B
C
B
C
C
Least Concern
B
B
B
C
D
C
B
C
C
B
C
C
Least Concern
Least Concern
Least Concern
B
C
B
C
C
Least Concern
B
B
B
B
D
D
D
C
C
Least Concern
Least Concern
Least Concern
Least Concern
Birds listed on Annex I of Council directive 79/409/EEC
A229
Alcedo atthis
A089
A222
A021
Aquila pomarina
Asio flammeus
Botaurus stellaris
A215
Bubo bubo
A224
A197
A031
A030
Caprimulgus europaeus
Chlidonias niger
Ciconia ciconia
Ciconia nigra
A080
Circaetus gallicus
A081
A082
Circus aeruginosus
Circus cyaneus
A084
A122
A037
A038
Circus pygargus
Crex crex
Cygnus bewickii (Cygnus
columbianus bewickii)
Cygnus cygnus
A238
Dendrocopos medius
A236
Dryocopus martius
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
Common
Kingfisher
Lesser-Spotted
Eagle
Short-eared Owl
Great Bittern
Eurasian Eagleowl
Eurasian
Nightjar
Black Tern
White Stork
Black Stork
Short-toed
Snake-eagle
Western Marshharrier
Northern Harrier
Montagu‟s
Harrier
Corncrake
Bewick‟s Swan
Whooper Swan
Middle Spotted
Woodpecker
Black
Woodpecker
B
C
D
Least Concern
B
B
C
D
B
C
C
Least Concern
Least Concern
B
B
C
C
B
B
C
C
C
C
Least Concern
Not listed
S
S
D
D
Not listed
Least Concern
B
D
Least Concern
B
D
Least Concern
ANNEXES
20
OCTOBER 2010
BIODIVERSITY ACTION PLAN
ERM Polska Sp. z o.o.
Site Assessment
Code
Name
A098
A103
Falco columbarius
Falco peregrinus
Common name
Population
Population
Merlin
S
D
Peregrine Falcon S
D
Red-breasted
A320
Ficedula parva
Flycatcher
B
D
A127
Grus grus
Common Crane B
C
White-tailed
A075
Haliaeetus albicilla
Eagle
B, W, S
B
Α022
Ixobrychus minutus
Little Bittern
B
D
Reb-backed
A339
Lanius collurio
Shrike
B
D
A246
Lullula arborea
Wood Lark
B
D
A272
Luscinia svecica
Bluethroat
B
C
A074
Milvus milvus
Red Kite
B
C
A094
Pandion haliaetus
Osprey
B
D
European
A072
Honey-buzzard B
C
Pernis apivorus
A151
Philomachus pugnax
Ruff
S
D
Eurasian Golden
A140
Pluvialis apricaria
Plower
S
D
A193
Sterna hirundo
Common Tern
B
D
A195
Sternula albifrons
Little Tern
B
D
A307
Sylvia nisoria
Barred Warbler B
D
A166
Tringa glareola
Wood Sandpiper S
D
Regularly occurring Migratory Birds not listed on Annex I of Council directive 79/409/EEC
A149
Calidris alpina
Dunlin
S
D
A260
Motacilla cinerea
Grey Wagtail
B
D
Eurasian Green
A235
Picus viridis
Woodpecker
B
D
A165
Tringa ochropus
Green Sandpiper B
D
Conservation Isolation Global
IUCN Status
Least Concern
Least Concern
B
B
B
B
C
B
B
B
C
C
C
C
B
C
C
Near Threatened
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Least Concern
Population: W – wintering, S – staging, B – breeding, R – resident
Site Assessment: See explanatory note at beginning of Annex A.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
ANNEXES
21
OCTOBER 2010
BIODIVERSITY ACTION PLAN
Table 8.15
Other Important Species of Flora and Fauna - PLH320019
Scientific name
Insects
Anodonta cygnaea
Apatura iris
Ceruchus chrysomelinus
Helix pomatia
Hirudo medicinalis
Musculium lacustre
Pisidium amnicum
Pisidium henslowanum
Pisidium obtusale
Sphaerium rivicola
Sphaerium solidum
Unio pictorum
Unio tumidus
Valvata pulchella
Helicigona lapicida
Bombus distinguendus
Bombus jonellus
Bombus subterraneus
Fish
Pomatoschistus microps
Pomatoschistus minutus
Amphibians
Pelobates fuscus
Bufo viridis
Bufo calamita
Rana lessonae
Rana esculenta
Rana ridibunda
Rana temporaria
Rana arvalis
Triturus vulgaris
Bufo bufo
Reptiles
Lacerta agilis
Coronella austriaca
Lacerta vivipara
Anguis fragilis
Natrix natrix
Plants
Sphagnum cuspidatum
Sphagnum palustre
Sphagnum squarrosum
Diphasium complanatum
Huperzia selago
Lycopodium annotinum
Lycopodium clavatum
Matteuccia struthiopteris
Osmunda regalis
Polypodium vulgare
Taxus baccata
Myosotis praecox
Population
Motivation
Common
Very rare
Rare
Common
Present
Very rare
Rare
Common
Very rare
Rare
Present
Rare
Present
Very rare
Rare
Rare
Rare
Very rare
A
A
A
C
A
A
D
D
A
A
A
D
D
A
A
A
A
A
Rare
Rare
C
C
Rare
Present
Rare
Present
Common
Common
Common
Common
Rare
Rare
C
C
C
C
C
C
C
C
C
C
Common
Rare
Rare
Present
Common
C
A
C
C
C
Present
Present
Present
Rare
Present
Rare
Rare
Present
Rare
Common
Present
Present
C
C
C
D
D
C
D
D
A
D
A
A
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
ANNEXES
22
OCTOBER 2010
BIODIVERSITY ACTION PLAN
Scientific name
Angelica archangelica
Aster tripolium
Betula humilis
Centaurium erythraea
Centaurium littorale
Chimaphila umbellata
Digitalis purpurea
Drosera anglica
Drosera intermedia
Drosera rotundifolia
Erica tetralix
Eryngium maritimum
Frangula alnus
Galium odoratum
Gentiana pneumonanthe
Glaux maritima
Hedera helix
Helichrysum arenarium
Hepatica nobilis
Hippophae rhamnoides
Ledum palustre
Linnaea borealis
Littorella uniflora
Lonicera periclymenum
Moneses uniflora
Myrica gale
Nuphar lutea
Vipera berus
Nymphaea alba
Nymphaea candida
Ononis spinosa
Orobanche caryophyllacea
Pedicularis sylvatica
Plantago coronopus
Plantago maritima
Potentilla neumanniana
Primula veris
Pulsatilla pratensis
Ribes nigrum
Rubus chamaemorus
Stachys recta
Thalictrum minus
Viburnum opulus
Vinca minor
Galanthus nivalis
Zostera marina
Anthericum liliago
Carex arenaria
Carex limosa
Cephalanthera damasonium
Cephalanthera rubra
Convallaria majalis
Corallorhiza trifida
Dactylorhiza incarnata
Dactylorhiza maculata
Population
Rare
Present
Present
Present
Present
Very rare
Very rare
Present
Present
Present
Present
Very rare
Common
Present
Present
Rare
Present
Present
Very rare
Present
Rare
Rare
Very rare
Present
Rare
Very rare
Rare
Present
Common
Very rare
Rare
Very rare
Present
Rare
Present
Very rare
Rare
Rare
Common
Present
Very rare
Rare
Present
Present
Present
Present
Very rare
Common
Very rare
Very rare
Very rare
Common
Very rare
Present
Present
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
Motivation
D
A
A
D
A
D
D
A
A
A
D
D
D
D
A
D
D
D
D
D
D
D
A
D
C
D
D
C
D
A
D
C
D
A
A
C
D
D
D
A
C
C
D
D
C
D
A
D
A
A
A
D
A
D
A
ANNEXES
23
OCTOBER 2010
BIODIVERSITY ACTION PLAN
Scientific name
Dactylorhiza majalis
Dactylorhiza traunsteineri
Epipactis atrorubens
Epipactis helleborine
Epipactis palustris
Epipogium aphyllum
Eriophorum gracile
Goodyera repens
Hammarbya paludosa
Hierochloe odorata
Listera cordata
Listera ovata
Microstylis monophyllos
Neottia nidus-avis
Ornithogalum umbellatum
Platanthera bifolia
Platanthera chlorantha
Potamogeton alpinus
Potamogeton rutilus
Sparganium angustifolium
Triglochin maritima
Malaxis monophyllos
Atriplex calotheca
Sphagnum magellanicum
Sphagnum fallax
Dianthus arenarius
Mammals
Pipistrellus pipistrellus
Nyctalus noctula
Myotis daubentonii
Pipistrellus nathusii
Myotis nattereri
Plecotus auritus
Eptesicus serotinus
Nyctalus leisleri
Vespertilio murinus
Martes martes
Erinaceus europaeus
Neomys anomalus
Neomys fodiens
Sorex araneus
Sorex minutus
Sciurus vulgaris
Mustela erminea
Mustela nivalis
Population
Common
Present
Rare
Rare
Present
Present
Present
Common
Rare
Rare
Present
Present
Rare
Present
Present
Present
Present
Very rare
Present
Common
Present
Rare
Present
Present
Present
Present
Motivation
D
A
D
D
A
A
A
D
A
A
D
D
A
D
D
D
D
C
A
A
C
A
A
C
C
D
Rare
Rare
Very rare
Present
Very rare
Rare
Present
Very rare
Very rare
Very rare
Rare
Rare
Rare
Common
Rare
Rare
Rare
Rare
C
C
C
C
C
C
C
A
A
C
C
A
C
C
C
C
C
C
Motivation: A – National Red List, B – Endemics, C - International Conventions (incl. Bern,
Bonn and Biodiversity Convention), D – Other.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
ANNEXES
24
OCTOBER 2010
BIODIVERSITY ACTION PLAN
Table 8.16
Other Important Species of Flora and Fauna - PLH320018
Scientific name
Insects
Anodonta cygnaea
Argiope bruennichi
Helix pomatia
Hirudo medicinalis
Sphaerium rivicola
Sphaerium solidum
Unio pictorum
Viviparus viviparus
Fish
Coregonus lavaretus
Leucaspius delineatus
Silurus glanis
Vimba vimba
Amphibians
Pelobates fuscus
Bufo viridis
Hyla arborea
Rana lessonae
Rana esculenta
Rana ridibunda
Rana temporaria
Rana arvalis
Triturus vulgaris
Bufo bufo
Reptiles
Lacerta agilis
Lacerta vivipara
Natrix natrix
Vipera berus
Plants
Sphagnum fimbriatum
Sphagnum palustre
Sphagnum squarrosum
Sphagnum subsecundum
Aulacomnium palustre
Salvinia natans
Dryopteris cristata
Osmunda regalis
Angelica archangelica
Circaea alpina
Dianthus superbus
Drosera anglica
Drosera rotundifolia
Frangula alnus
Gentiana pneumonanthe
Lonicera periclymenum
Menyanthes trifoliata
Myrica gale
Nuphar lutea
Nymphaea alba
Plantago maritima
Population
Motivation
Very rare
Present
Present
Present
Very rare
Very rare
Present
Very rare
A
D
C
A
A
A
D
A
Present
Present
Present
Rare
A
C
C
A
Present
Present
Present
Present
Present
Present
Present
Present
Present
Present
C
C
C
C
C
C
C
C
C
C
Present
Present
Present
Present
C
C
C
C
Common
Common
Common
Rare
Present
Rare
Very rare
Very rare
Rare
Very rare
Rare
Very rare
Very rare
Common
Very rare
Common
Rare
Rare
Rare
Rare
Very rare
C
C
C
C
D
A
A
A
D
C
A
A
A
D
A
D
D
D
D
D
A
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
ANNEXES
25
OCTOBER 2010
BIODIVERSITY ACTION PLAN
Scientific name
Carex pulicaris
Gymnadenia conopsea
Sphagnum contorum
Sphagnum girgensohnii
Sphagnum nemoreum
Sphagnum fallax
Mammals
Myotis daubentonii
Mustela putorius
Erinaceus europaeus
Neomys fodiens
Sorex araneus
Sciurus vulgaris
Martes foina
Meles meles
Mustela erminea
Mustela nivalis
Alces alces
Capreolus capreolus
Cervus elaphus
Lepus europaeus
Population
Very rare
Very rare
Rare
Rare
Rare
Common
Motivation
A
D
C
C
C
C
Present
Present
Present
Present
Present
Present
Present
Present
Present
Present
Present
Present
Present
Present
C
C
C
C
C
C
C
C
C
C
C
C
C
C
Motivation: A – National Red List, B – Endemics, C - International Conventions (incl. Bern,
Bonn and Biodiversity Convention), D – Other.
Table 8.17
Other Important Species of Flora and Fauna - PLH320033
Scientific name
Amphibians
Rana lessonae
Rana esculenta
Rana arvalis
Bufo bufo
Reptiles
Lacerta agilis
Lacerta vivipara
Natrix natrix
Vipera berus
Mammals
Martes martes
Mustela erminea
Mustela nivalis
Alces alces
Capreolus capreolus
Cervus elaphus
Lepus europaeus
Plants
Sphagnum palustre
Sphagnum squarrosum
Aulacomnium palustre
Lycopodium annotinum
Dryopteris cristata
Osmunda regalis
Drosera rotundifolia
Population
Motivation
Present
Present
Present
Present
C
C
C
C
Present
Present
Present
Present
C
C
C
C
Present
Present
Present
Present
Present
Present
Present
C
C
C
C
C
C
C
Rare
Rare
Rare
Present
Present
Common
Present
C
C
D
C
A
A
A
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
ANNEXES
26
OCTOBER 2010
BIODIVERSITY ACTION PLAN
Scientific name
Lathyrus palustris
Ledum palustre
Lonicera periclymenum
Hierochloe odorata
Listera ovata
Sphagnum fallax
Population
Present
Present
Rare
Present
Present
Rare
Motivation
A
D
D
A
D
C
Motivation: A – National Red List, B – Endemics, C - International Conventions (incl. Bern,
Bonn and Biodiversity Convention), D – Other.
PROJECT NO. P0114469, POLSKIE LNG SP. Z O.O.
LNG TERMINAL IN ŚWINOUJŚCIE, POLAND
ANNEXES
27
OCTOBER 2010
BIODIVERSITY ACTION PLAN

Podobne dokumenty