Att no 1 - List of investments and progress of work

Transkrypt

Att no 1 - List of investments and progress of work
Table No. 1 - List of investments and progress of work RZGW Wrocław
No.
STRUCTURE
TASK (Subcomponent)
COMPONENT
Measurement
Preliminary
s,
documentation,
Zoning permit/Location
investigations,
Surveying and legal
TechnicalEnvironmental permit
permit/Local land use
calculations
documentation
ekonomic
plan
and expert's
concept
reports
Geological,
geotechnical,
engineering and
hydraulic
documentation
Detailed
design
Construction permit
Other
documentation
related to
environmental
protection, e.g.
hydraulic project
appraisal report,
tree survey
Other
administrative
permits
Working
drawings and
Bidding documents Engineer's
specifications
for works
cost estimate
(execution
design)
COMPONENT 1 - Lower and Middle Odra River
1B Protection of Middle and Lower Odra River
1
2
Regulation of the Odra River in the section from Brzeg Doly to the
Nysa Łużycka confluence with respect to the following works:
Rehabilitation and improvements of river training structures of the
free flowing Odra River – reconstruction and improvements of river
Reconstruction of river control infrastructure on Odra
training structures to upgrade the Odra River section from
River. Adaptation to the conditions of Class III
Malczyce to the Nysa Łużycka River mouth to Class III waterway
roadway. Stage II
standard. Stage II
Reconstruction of river control infrastructure on Odra
Regulation of the Odra River in the section from Brzeg Doly to the
River. Adaptation to the conditions of Class III
Nysa Łużycka confluence with respect to the following works:
roadway. Stage III
Rehabilitation and improvements of river training structures of the
(1 bridge - Krosno Odrzanskie)
free flowing Odra River – reconstruction and improvements of river
training structures to upgrade the Odra River section from
Malczyce to the Nysa Łużycka River mouth to Class III waterway
standard. Stage III
yes
yes
yes
yes
yes
yes
yes
yes
yes
no
yes
no
yes
no
no
no
no
no
no
no
no
no
no
no
no
no
no
no
no
no
no
1B.1
COMPONENT 2 - LOOD PROTECTION O KŁODZKO VALLEY
2A - Active protection
Construction of the Boboszów dry polder on the Nysa Kłodzka
River
1
Construction of "Boboszów" - a dry flood control
reservoir on Nysa Kłodzka River and Construction of
"Roztoki Bystrzyckie" - a dry flood control reservoir on
Goworówka stream
yes
no
no
no
(Special Law)
There are
extracts from
the land
register
yes
yes
no
2A.1
2
Construction of the “Roztoki Bystrzyckie" on the Goworówka creek
near the village of Goworówka, Municipality of Kłodzko in Lower
Silesian Voivodeship
yes
no
no
no
(Special Law)
There are
extracts from
the land
register
yes
no
no
no
no
no
no
no
3
Construction of the Szalejów Górny dry polder on the Bystrzyca
Dusznicka River
yes
no
no
no
(Special Law)
There are
extracts from
the land
register
yes
no
no
no
no
no
no
no
4
Construction of the “Krosnowice” dry polder on the Duna creek
near the village of Krosnowice, Municipality of Kłodzko in Lower
Silesian Voivodeship
yes
yes
no
no
(Special Law)
There are
extracts from
the land
register
yes
yes
no
yes
no
no
no
no
1
 lood protection of the Nysa Kłodzka valley
no
no
no
no
no
no
no
no
no
no
no
no
no
no
no
no
no
no
no
no
no
no
no
no
no
no
no
no
no
no
no
no
no
no
no
no
no
no
no
no
no
no
no
no
no
no
no
no
no
no
no
no
Construction of "Szalejów Górny" - a dry flood control
reservoir on Bystrzyca Dusznicka River and
Construction of "Krosnowice" - a dry flood control
reservoir on Duna creek
2A.2
2B - Passive protection
lood protection of Nysa Kłodzka River Valley lood
protection of Ścinawka River Valley
2B.1
2
 lood protection of the Ścinawka River valley
3
lood protection of the valleys of the Biała Lądecka River and the
Morawka River
4
lood protection of Biała Lądecka River valley and
Morawka River and lood protection of Bystrzyca
Dusznicka River Valley and Kamienny Potok River.
2B.2
 lood protection of the valleys of the Bystrzyca Dusznicka River
and the Kamienny Potok River